Data Center Record.
Census GEOID: 29510 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 primary source

● Running First recorded September 14, 2026 · 1 Building

H5 Data Centers St. Louis

Street address 210 North Tucker Boulevard, St. Louis, MO 63101, St. Louis city verified address Exact, at the address [1] H5 Data Centers: Data centers

Overview, regulatory gates and specifications

H5 Data Centers operates a commercial colocation facility at 210 North Tucker Boulevard in downtown St. Louis, Missouri. [1] Filings on the record specify disclosed capacity of 8 MW (the developer's figure), 1 planned or operational building. [1] H5 Data Centers lists H5 St. Louis at St. Louis, Missouri on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
8 MW
the developer's figure

Equivalent to ~6,640 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.4% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 210 North Tucker Boulevard, St. Louis, MO 63101.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
8 MW developer figure Equivalent to the continuous electricity demand of about 6,640 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.078 percent) of New York City's summer peak demand in 2024.
[1] h5datacenters.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] h5datacenters.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2016 (10 years)
Who leads it
H5 Data Centers as stated by the source
Official project website
h5datacenters.com (opens in a new tab) verified October 28, 2026
h5datacenters.com (opens in a new tab)
Archived promotional websites
h5datacenters.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. H5 Data Centers St. Louis, capacity: 8 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 8 ÷ 10,245 = 0.00078 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: H5 Data Centers
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for H5 Data Centers St. Louis.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 8 MW 8 MW the developer's figure [1] h5datacenters.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [1] h5datacenters.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 28, 2026 St. Louis, MO St. Louis Board of Aldermen Board Bill 49 Data Center Regulations Vote St. Louis Board of Aldermen 2 clips

On August 28, 2026, the St. Louis Board of Aldermen voted unanimously to advance Board Bill 49, establishing the city's first comprehensive zoning, conditional use, water disclosure, and noise regulations for data centers.

  1. FOX 2 St. Louis Broadcast Report Broadcast Report transcribed from local broadcast report
    "It establishes size classifications for data centers. Restrictions on where they can be built. Noise, regulations and water use its guidelines. The measure also requires new data centers with loads exceeding 5 megawatts to give 100% of their electricity from renewable energy sources. The bill is sponsored by first ward alderwoman and schweitzer. This is all about"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Lot of concerns about the proliferation of data centers and the amount of energy that they use and will continue to use and the effect. On our on our climate, on environment, on our ability to exist in this world. So I think it's really important that we in the local level act to protect the people we represent. Even if that means fighting against some pretty powerful interests."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    H5 Data Centers lists H5 St. Louis at St. Louis, Missouri on its own page of data center locations, read September 14, 2026.

    [1] h5datacenters.com

Nearest data centers in Missouri

Verified data center records in Missouri within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Netrality and Digital Realty 210 North Tucker Carrier Hotel St. Louis, St. Louis city Less than 1 mi Running Netrality Data Centers / Digital Realty 22 MW
TierPoint St. Louis Downtown Data Center (Olive) St. Louis, St. Louis city Less than 1 mi Running TierPoint 10 MW
710 North Tucker Carrier Hotel (Globe Building St. Louis) St. Louis, St. Louis city Less than 1 mi Running Hostirian 10 MW
Netrality St. Louis 900 Walnut Carrier Hotel St. Louis, St. Louis city Less than 1 mi Running Netrality Data Centers 12 MW
TierPoint St. Louis Downtown (2300 Locust Street) St. Louis, St. Louis city Less than 1 mi Running TierPoint 1 building
St. Louis Midtown Chouteau Data Center Proposal St. Louis, St. Louis city 2 mi Proposed Midtown Technology Partners 2 buildings

Blank cell: not disclosed by any source on file.

Common questions about H5 Data Centers St. Louis

Answered directly from the verified filings and local actions on this page.

Who is building H5 Data Centers St. Louis?

H5 Data Centers is the developer. No construction contractor is named on the record yet.

How much power and water does H5 Data Centers St. Louis say it needs?

Power: 8 MW (the developer's figure, h5datacenters.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does H5 Data Centers St. Louis stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. H5 Data Centers: Data centers (opens in a new tab), H5 Data Centers, September 14, 2026

1 source on file.

Regional grid context

This site is in the SERC Midwest (SRMW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "H5 Data Centers St. Louis", https://datacenterrecord.org/projects/h5-st-louis-mo, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "H5 Data Centers St. Louis", https://datacenterrecord.org/projects/h5-st-louis-mo. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
38.6295, -90.1972
How the location is known
Location from the site's street address.
Location source
https://www.h5datacenters.com/
Coordinate source
H5 St. Louis specification
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
8 MW, the developer's figure
Published
September 14, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · H5 Data Centers St. Louis · 1 source, 1 entry · basis and source tier on every row · verified November 6, 2026