Data Center Record.

Data centers in Alabama

Alabama has 11 data center sites, 0 buildings where disclosed on the record: 1 running, 2 being built and 8 proposed. The counties with the most are Jefferson County (2) and Montgomery County (2), and records are in 8 of 67 counties. The largest proposal is Westover Proposed Data Center in Shelby County, 448 acres (third party estimate); it is reported, as reported August 17, 2026.

Alabama decides case by case. From the state's own rule: Alabama Public Service Commission approved two year electric rate freeze and two solar projects for Meta data center, December 3, 2025.

1 site the EPA's registry shows and no record has verified is on the map apart from the count. What not yet verified means.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Projects and campuses on the record

Facility and countyStageOperatorPower (MW)Latest entry
Edged Energy Prichard Data Center Prichard, Mobile CountyProposedEdged Energy
Data Center near Tuscaloosa Tuscaloosa, Tuscaloosa CountyProposed
DC Blox Montgomery data center Montgomery, Montgomery CountyProposedDC Blox
Lowndes County Hyperscale Data Center Lowndes CountyProposed
Patmos Fairfield Data Center Fairfield, Jefferson CountyProposedPatmos
QTS Bessemer Bessemer, Jefferson CountyBeing builtQTS Data CentersNebius AI data center project planned in Oxmoor Valley near Birmingham alreporter.com (opens in a new tab) local outlet reported September 15, 2026
Brookwood Proposed Data Center Brookwood, Tuscaloosa CountyProposedfor Kayvens LLC (affiliated with Meta)Brookwood has a possible data center project near Brookwood Middle School abc3340.com (opens in a new tab) local outlet reported September 8, 2026
Montgomery Meta Investment Montgomery, Montgomery CountyBeing builtMetaMeta data center in Toney area expanding to 2.5 million square feet yahoo.com (opens in a new tab) national outlet reported August 23, 2026
Westover Proposed Data Center Westover, Shelby CountyProposedThe proposed data center project is awaiting engineering confirmation from Alabama Power regarding sufficient incremental electricity capacity and from Shelby County water authority regarding water capacity. yahoo.com (opens in a new tab) national outlet reported August 17, 2026
Google Bridgeport data center Bridgeport, Jackson CountyProposedGoogleThe data center began operating in 2019 youtube.com (opens in a new tab) video reported June 19, 2026
Meta Huntsville Data Center Huntsville, Madison CountyRunningMeta

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 11 Alabama projects.

Every Alabama record 11 records, and 1 site not yet verified listed apart · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Edged Energy Prichard Data CenterPrichard, MobileProposedEdged Energycentroid12026-10-21
Oppidan Data Center, MGMMontgomery, MontgomeryNot yet verifiedEPA registry22026-10-20
Meta Huntsville Data CenterHuntsville, MadisonRunningMetaEPA registry22026-10-04
Data Center near TuscaloosaTuscaloosa, TuscaloosaProposedcentroid42026-09-17
DC Blox Montgomery data centerMontgomery, MontgomeryProposedDC Bloxcentroid42026-09-17
Lowndes County Hyperscale Data CenterLowndesProposedcentroid42026-09-17
Patmos Fairfield Data CenterFairfield, JeffersonProposedPatmoscentroid42026-09-17
QTS BessemerBessemer, JeffersonBeing builtQTS Data Centerscentroid22026-09-17
Brookwood Proposed Data CenterBrookwood, TuscaloosaProposedcentroid12026-10-06
Montgomery Meta InvestmentMontgomery, MontgomeryBeing builtMetacentroid22026-09-08
Westover Proposed Data CenterWestover, ShelbyProposedcentroid42026-09-25
Google Bridgeport data centerBridgeport, JacksonProposedGoogleEPA registry22026-10-04

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every Alabama county (67)

8 of 67 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRules
Jefferson County0107322
Montgomery County0110120
Tuscaloosa County0112520
Jackson County0107110
Lowndes County0108510
Madison County0108910
Mobile County0109710
Shelby County0111712
Baldwin County0100301
Calhoun County0101501
Talladega County0112102

A county without a record is listed, not linked.

56 counties with no records yet
  • Autauga County
  • Barbour County
  • Bibb County
  • Blount County
  • Bullock County
  • Butler County
  • Chambers County
  • Cherokee County
  • Chilton County
  • Choctaw County
  • Clarke County
  • Clay County
  • Cleburne County
  • Coffee County
  • Colbert County
  • Conecuh County
  • Coosa County
  • Covington County
  • Crenshaw County
  • Cullman County
  • Dale County
  • Dallas County
  • DeKalb County
  • Elmore County
  • Escambia County
  • Etowah County
  • Fayette County
  • Franklin County
  • Geneva County
  • Greene County
  • Hale County
  • Henry County
  • Houston County
  • Lamar County
  • Lauderdale County
  • Lawrence County
  • Lee County
  • Limestone County
  • Macon County
  • Marengo County
  • Marion County
  • Marshall County
  • Monroe County
  • Morgan County
  • Perry County
  • Pickens County
  • Pike County
  • Randolph County
  • Russell County
  • St. Clair County
  • Sumter County
  • Tallapoosa County
  • Walker County
  • Washington County
  • Wilcox County
  • Winston County

The rules in Alabama 11 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
Alabamastatecase by caseAlabama Public Service Commission approved two year electric rate freeze and two solar projects for Meta data center. insideclimatenews.org (opens in a new tab) news outlet Dec 3, 20259 acts on this row
Every act on the Alabama row
  1. approval

    Alabama Public Service Commission approved rules requiring the commission to vote on each new data center project exceeding the 150 megawatt threshold within 90 days, with automatic approval if no vote occurs

    streamlinefeed.co.ke (opens in a new tab) international outlet

  2. ordinance

    Alabama Public Service Commission approved new transparency requirements for large data centers expected to draw 150 megawatts or more of electricity on a single contiguous property

    streamlinefeed.co.ke (opens in a new tab) international outlet

  3. rate rule

    Alabama Power to the People Act takes effect in October, requires Alabama Public Service Commission to determine that any large data center contract with Alabama Power recovers full cost of serving that customer before approval

    yellowhammernews.com (opens in a new tab) local outlet

  4. event

    County commissions passed a resolution saying they do not want specific power to regulate data centers

    aldailynews.com (opens in a new tab) local outlet

  5. hearing

    A state senator held a hearing on a proposed Alabama data center

    thebatavian.com (opens in a new tab) local outlet

  6. event

    Alabama Power made a data center contract publicly available with redacted sections

    wbrc.com (opens in a new tab) local outlet

  7. approval

    The Alabama Public Service Commission issued an approval order for Alabama Power to build solar facilities to power Meta data center

    fox10tv.com (opens in a new tab) local outlet

  8. moratorium

    Several Alabama cities placed moratoriums on new data center projects in 2026, including Fort Payne, Cullman, Birmingham, Leeds, and Homewood

    yellowhammernews.com (opens in a new tab) local outlet

  9. approval

    Alabama Public Service Commission approved two year electric rate freeze and two solar projects for Meta data center

    insideclimatenews.org (opens in a new tab) news outlet

Last verified October 6, 2026.

92026-10-06
Westovercityrestrictive until February 18, 20272027-02-18Westover approved a 6 month moratorium on data centers. wbrc.com (opens in a new tab) local outlet Aug 18, 20262 acts on this row
Every act on the Westover row
  1. moratorium adopted

    Westover approved a 6 month moratorium on data centers

    wbrc.com (opens in a new tab) local outlet

  2. moratorium

    Westover city council postponed a vote on a proposed six month moratorium on data centers at a special meeting on August 6, 2026.

    yahoo.com (opens in a new tab) national outlet

Last verified August 18, 2026.

22026-08-18
Brookwoodcitynot ratedBrookwood City Council heard citizens concerns about a proposed data center. reutersconnect.com (opens in a new tab) national outlet Reported Sep 31 act on this row
Every act on the Brookwood row
  1. statement

    Brookwood City Council heard citizens concerns about a proposed data center.

    reutersconnect.com (opens in a new tab) national outlet

Last verified September 3, 2026.

12026-09-03
Annistoncityrestrictive until August 18, 20272027-08-18Anniston City Council adopted Resolution No. 26 R-97 on August 18, 2026, imposing a 12 month moratorium on data center permitting, development, expansion and licensing. weisradio.com (opens in a new tab) local outlet Aug 18, 20263 acts on this row
Every act on the Anniston row
  1. event

    Anniston Planning Commission directed to study zoning, property sizes, residential separation, utility capacity, stormwater, transportation effects, backup generators, emergency response, noise, lighting and screening within six months.

    weisradio.com (opens in a new tab) local outlet

  2. event

    Anniston Planning Commission directed to study data center issues and present recommendations within six months including appropriate locations, minimum lot sizes, electrical demand, water consumption, cooling systems, stormwater impacts, backup generators, noise and lighting standards, and neighborhood compatibility.

    wbrc.com (opens in a new tab) local outlet

  3. moratorium adopted

    Anniston City Council adopted Resolution No. 26 R-97 on August 18, 2026, imposing a 12 month moratorium on data center permitting, development, expansion and licensing.

    weisradio.com (opens in a new tab) local outlet

    Also reported by 1 source

Last verified September 7, 2026.

32026-09-07
Baldwin Countycountynot ratedNo dated act on this row yet.2026-09-08
Chelseacityrestrictive until July 21, 20272027-07-21Chelsea adopted a one year data center moratorium on July 21, 2026. yahoo.com (opens in a new tab) national outlet Jul 21, 20262 acts on this row
Every act on the Chelsea row
  1. moratorium adopted

    Chelsea adopted a one year moratorium on new data center applications

    abc3340.com (opens in a new tab) local outlet

  2. moratorium adopted

    Chelsea adopted a one year data center moratorium on July 21, 2026.

    yahoo.com (opens in a new tab) national outlet

Last verified September 8, 2026.

22026-09-08
Harpersvillecityrestrictive until March 1, 20272027-03-01Harpersville city council approved six month pause on data center projects in August 2026, followed by first of six public information sessions. wvtm13.com (opens in a new tab) local outlet Sep 1, 20262 acts on this row
Every act on the Harpersville row
  1. moratorium adopted

    Harpersville city council approved six month pause on data center projects in August 2026, followed by first of six public information sessions

    wvtm13.com (opens in a new tab) local outlet

  2. moratorium adopted

    Harpersville adopted six month moratorium on data center development in August

    abc3340.com (opens in a new tab) local outlet

Last verified September 8, 2026.

22026-09-08
HomewoodcityrestrictiveHomewood temporarily paused new data center applications. abc3340.com (opens in a new tab) local outlet Sep 8, 20261 act on this row
Every act on the Homewood row
  1. moratorium

    Homewood temporarily paused new data center applications

    abc3340.com (opens in a new tab) local outlet

Last verified September 8, 2026.

12026-09-08
Munfordcitynot ratedPublic interest meeting on proposed data center scheduled for Sept. 10 at 6 p.m. at Munford Recreation Center Gym. annistonstar.com (opens in a new tab) news outlet Reported Sep 81 act on this row
Every act on the Munford row
  1. event

    Public interest meeting on proposed data center scheduled for Sept. 10 at 6 p.m. at Munford Recreation Center Gym

    annistonstar.com (opens in a new tab) news outlet

Last verified September 8, 2026.

12026-09-08
Talladega Countycountynot ratedTalladega County Commission and elected officials seeking one year moratorium on data center development. annistonstar.com (opens in a new tab) news outlet Reported Sep 82 acts on this row
Every act on the Talladega County row
  1. moratorium

    Talladega County Commission and elected officials seeking one year moratorium on data center development

    annistonstar.com (opens in a new tab) news outlet

  2. hearing

    Alabama leaders held a meeting in Talladega County to address questions about data centers

    wbrc.com (opens in a new tab) local outlet

Last verified September 8, 2026.

22026-09-08
Tarrantcityrestrictive until September 9, 20272027-09-09City of Tarrant approved a 12 month moratorium on data centers. abc3340.com (opens in a new tab) local outlet Sep 9, 20261 act on this row
Every act on the Tarrant row
  1. moratorium adopted

    City of Tarrant approved a 12 month moratorium on data centers

    abc3340.com (opens in a new tab) local outlet

Last verified September 9, 2026.

12026-09-09

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

Alabama laws and the full scorecard

Bills and laws in Alabama

1 signed into law, 2 bills tracked

2 bills tracked in the Alabama legislature, 1 of them signed into law, grouped by where each stands. A row opens its own page; the Alabama laws page has what each law requires.

No official summary on file for any of these 2 measures; each row links to the legislature's page for the text.

Signed into law 1

2 bills tracked, 1 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
SB270 2026 Regular Session Signed 2026-04-17 Electric Utilities; review by Public Service Commission of certain contracts with large load data centers further provided for
H.B. 403 2026 Regular Session Passed its first chamber 2026-03-17 Electric Utilities; review by Public Service Commission of certain contracts with large load customers further provided

2 bills tracked in Alabama; First Special Session 2026, legislature adjourned; last checked October 26, 2026. The last check found: 2 bills matched the watch terms as of October 26, 2026. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. Alabama's members: 7 yea, 0 nay. How each member voted

MemberPartyPosition
AderholtRYea
FiguresDYea
Moore (AL)RYea
PalmerRYea
Rogers (AL)RYea
SewellDYea
StrongRYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. Alabama's members: 2 yea, 0 nay. How each member voted

MemberPartyPosition
Britt (R-AL)RYea
Tuberville (R-AL)RYea

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What happened

  1. Moratorium adoptedTarrant

    City of Tarrant approved a 12 month moratorium on data centers

The full Alabama timeline, year by year

What was said

This is an industry that is rapidly changing from day to day, and at some point in time, you've got to address what the problem is, instead of just kind of kicking it down the road. That's been our position, that we need to have something in place, instead of just being fearful like other communities and deciding the easy way out, which is to go ahead and do a moratorium.
James Stewart Jr., Mayor, Irondale, AL · October 22, 2026 · quoted · GovTech (opens in a new tab) national outlet
We invested over $2 million in due diligence testing on the site.
Wes Self, Representative, Western Hospitality Partners · October 6, 2026 · quoted · Sylacauga News (opens in a new tab) news outlet

Every Alabama statement, by speaker (103)

92 more on this page, one per speaker and claim; 103 statements in all

Dr. Charles Steele Jr., former president of the Southern Christian Leadership Conference, expressed opposition to the data center tax incentive, saying the proximity to a 1965 Selma march campsite makes it problematic

Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Yellowhammer News (opens in a new tab).

Mayor Dale Phillips said the city intends to move carefully and wants to vet every aspect before approving any data center proposal, and that there is nothing currently in the works.

WBMA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBMA (opens in a new tab).

Tuberville cosponsored the Senate version of the Ratepayer Protection Act, which would require states to consider standards making data centers drawing 100 MW or more pay the full cost of power plants, transmission lines and grid upgrades built to serve them

U.S. Senator Yellowhammer News (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Yellowhammer News (opens in a new tab).

Sen. Tommy Tuberville co sponsored the Ratepayer Protection Act requiring states to establish standards for utility commission decisions when connecting large electricity users of 100 megawatts or more to the grid.

U.S. Senator (R-Alabama) 1819 News (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: 1819 News (opens in a new tab).

Terri Michal, a vocal opponent of data centers, was previously removed from a Birmingham City Council meeting over public comment rules during disputes about data center projects

wvtm (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wvtm (opens in a new tab).

Joseph Baker, co organizer of the event, said AI and data center rollout is causing negative effects at facilities and surrounding areas

wvtm (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wvtm (opens in a new tab).

Representatives of the AI Data Center Revolt Tour visited Alabama to highlight the impact of data centers on rural communities

organizers of AI Data Center Revolt Tour wvtm (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wvtm (opens in a new tab).

Kathy Latham, Texas state director of Humans First, said rural America is under attack by big tech wanting land

Texas state director, Humans First wvtm (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wvtm (opens in a new tab).

Patmos founder John Johnson told neighbors at a community meeting that generators will have mufflers and the loudest equipment will stay inside, with the site quieter than the old Walmart.

WBRC (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBRC (opens in a new tab).

Fairfield Mayor Herman Carnes Jr. visited a Patmos data center campus in Kansas City and described it as a multi story tech campus with a data center on at least one floor, stating it was quieter than many imagine.

WBRC (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBRC (opens in a new tab).

Doug Jones accused Tuberville of ethical malpractice for accepting campaign funds from large tech companies currently building data centers in west Alabama.

Democratic gubernatorial candidate WVUA 23 (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WVUA 23 (opens in a new tab).

Mayor Tracie Threadford said the decision was made out of caution as the city prepares for potential future development

Mayor of Tarrant WBMA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBMA (opens in a new tab).

No potential data center developers have approached the city at this time

Tracie Threadford, Mayor of Tarrant WBMA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBMA (opens in a new tab).

Adam Kramer, Global Head of Data Centers at Panattoni Development Company, stated developers identify power access before purchasing land

Global Head of Data Centers, Panattoni Development Company WBMA (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBMA (opens in a new tab).

Nebius had a sound study conducted and built the facility to the worst condition scenario so noise should not exceed background noise

Leah Davis, Nebius spokesperson WBHM (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBHM (opens in a new tab).

Nebius spokesperson Leah Davis said the company followed every normal and legal procedure of any other economic development project that happens in the city of Birmingham

WBHM (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBHM (opens in a new tab).

Mayor Theangelo Perkins said no company has approached Harpersville about building a data center

Harpersville Mayor WVTM (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WVTM (opens in a new tab).

Former U.S. Sen. Doug Jones said voters concerned about data center projects should vote for him because his opponent would allow them without scrutiny.

former U.S. Senator WTVY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WTVY (opens in a new tab).

Residents questioned Huntsville leaders about Meta expansion raising concerns about water use, power, jobs, environmental impacts and transparency

Huntsville residents yahoo.com (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: yahoo.com (opens in a new tab).

Council member Michael Shirley requested that if the developer does not honor a 45 day wait period, the council should call a special meeting to consider a moratorium.

Council member, Westover www.yahoo.com (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: www.yahoo.com (opens in a new tab).

Doug Jones called for a one year moratorium on data center construction in Alabama

Democratic gubernatorial nominee Alabama Political Reporter (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Alabama Political Reporter (opens in a new tab).

Also reported by: Alabama Reflector (opens in a new tab) local outlet , Tuscaloosa Thread (opens in a new tab) local outlet , Alabama Daily News (opens in a new tab) local outlet , WVUA 23 (opens in a new tab) local outlet , Yellowhammer News (opens in a new tab) local outlet .

"Alabama is already requiring demonstrations to verify proposed demand, long term contracts, minimum building requirements, upfront reimbursement of direct costs, and even termination fees."
Cynthia Lee Almond, President of the Alabama Public Service Commission Alabama Political Reporter (opens in a new tab) local outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Primary source: Alabama Political Reporter (opens in a new tab).

Once operational, the Montgomery Data Center will be optimized for AI workloads

Meta alreporter.com (opens in a new tab) local outlet project record
Context & source notes

Montgomery Data Center energy use will be matched with 100 percent clean and renewable energy

Meta Meta Data Centers (opens in a new tab) primary source project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Meta Data Centers (opens in a new tab).

Also reported by: alreporter.com (opens in a new tab) local outlet , Meta Store (opens in a new tab) primary source .

Said again: September 24, 2025 ( alreporter.com (opens in a new tab) local outlet ), September 1, 2026 ( Meta Store (opens in a new tab) primary source ).

Meta's broader goal is to reach net zero emissions across its supply chain by 2030.

Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: esgdive.com (opens in a new tab).

Also reported by: Data Center Dynamics (opens in a new tab) query feed , Associated Construction Publications (opens in a new tab) news outlet .

Said again: September 12, 2025 ( Associated Construction Publications (opens in a new tab) news outlet ).

Meta data center will be the 20th of its kind in the United States

Kay Ivey, Governor of Alabama YouTube (opens in a new tab) video project record
· Kay Ivey · YouTube · April 1, 2024 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Meta requires shovel ready sites with infrastructure and deep talent pools for data centers

Brad Davis, Dir., Community and Economic Development, Meta YouTube (opens in a new tab) video project record
· Brad Davis · YouTube · April 1, 2024 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Meta seeks 100 percent renewable energy access for site selection

Brad Davis, Dir., Community and Economic Development, Meta YouTube (opens in a new tab) video project record
· Brad Davis · YouTube · April 1, 2024 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Meta data center project requires a tremendous amount of power

Ellen McNair, Secretary, Alabama Department of Commerce YouTube (opens in a new tab) video project record
· Ellen McNair · YouTube · April 1, 2024 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

On the November 3, 2026 ballot in Alabama: Governor (2), U.S. Senate (2), U.S. House, District 1 (2), U.S. House, District 2 (2), U.S. House, District 3 (2), U.S. House, District 4 (2), U.S. House, District 5 (2), U.S. House, District 6 (2), U.S. House, District 7 (2); 3 of 18 candidates with a statement on data centers on the record. Every candidate.

Already running in Alabama

1 site is serving load, 1 of them in Madison County.

See the 1 running site
  1. Meta Huntsville Data Center Huntsville, Madison County Running · Operational since 2021 (5 years)

Questions about Alabama data centers

How many data center projects are on the record in Alabama?

11 projects are on the record in Alabama: 8 reported, 2 being built, 1 running and 1 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

Where in Alabama are they?

Records are in 8 counties: Jefferson County (2), Montgomery County (2), Tuscaloosa County (2), Jackson County (1), Lowndes County (1), Madison County (1), Mobile County (1) and Shelby County (1). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in Alabama?

Not disclosed. None of the 11 records on file for Alabama states a power figure. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in Alabama say they will use?

Not disclosed. None of the 11 records on file for Alabama states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in Alabama?

6 developers are named on the record: Meta (2 records), DC Blox, Edged Energy, Google, Patmos and QTS Data Centers. 4 records name no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in Alabama have rules about data centers?

10 county and city rows are on the record, 6 of them rated: Westover is rated restrictive: Westover approved a 6 month moratorium on data centers, August 18, 2026, source (opens in a new tab), Anniston is rated restrictive: Anniston City Council adopted Resolution No. 26 R-97 on August 18, 2026, imposing a 12 month moratorium on data center permitting, development, expansion and licensing, source (opens in a new tab) and Chelsea is rated restrictive: Chelsea adopted a one year data center moratorium on July 21, 2026, source (opens in a new tab). The state's own row is rated case by case, with 9 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in Alabama, by county?

10 records are not yet running. Jefferson County: Patmos Fairfield Data Center (reported) and QTS Bessemer (being built); Montgomery County: DC Blox Montgomery data center (reported) and Montgomery Meta Investment (being built); Tuscaloosa County: Brookwood Proposed Data Center (reported) and Data Center near Tuscaloosa (reported); Jackson County: Google Bridgeport data center (reported); Lowndes County: Lowndes County Hyperscale Data Center (reported); Mobile County: Edged Energy Prichard Data Center (reported); and Shelby County: Westover Proposed Data Center (reported). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of Alabama itself decided?

1 state law is on the record: SB270 (signed, April 17, 2026, source (opens in a new tab)). The state's own scorecard row carries 9 dated acts, the newest October 6, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

nothing disclosed by 11 records

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power011
Water, stated per day011
Water, stated per year011
Permanent jobs011
Tax each year011

A blank cell means no record in Alabama disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power011
Water, stated per day011
Water, stated per year011
Permanent jobs011
Tax each year011

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 11 tracked facilities in Alabama are for. 1 site not yet verified is named apart and is not in that number.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use11

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

MethodFacilitiesShare of facilities
Closed loop liquid19%
No stated cooling type1091%

11 facilities in Alabama. 1 site not yet verified is named apart and is not counted here. A facility carries one cooling method; nothing here is estimated.

Sources read for Alabama

10 sources

10 sources are read for Alabama:

Newspapers
AL.com, TimesDaily
Public broadcaster
Alabama Public Radio
Economic development
Alabama Department of Commerce
Search feeds
6 news searches
Every feed, with its kind and tier

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Alabama", https://datacenterrecord.org/states/al, updated October 26, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in Alabama", https://datacenterrecord.org/states/al. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
AL
Rating of the state's own row
Case by case
Count by status
reported 8, being built 2, running 1, not yet verified 1
Located records
2 located, 9 at a centroid, 0 without coordinates

Researcher view · Alabama · 11 data center sites, 0 buildings where disclosed, 11 rule rows, 2 bills · basis and source tier on every row · verified October 26, 2026

Download CSV JSON GeoJSON