Data Center Record.

Reported Built from one source

Westover Proposed Data Center

A proposed data center in Westover prompted a town hall and a 6 month moratorium approved by the city. It is reported, as reported August 17, 2026.

How much power it needs, how much water it would use and who would use it have not been disclosed.

Last verified · 3 sources, 0 primary · A skeleton record: built from one source, not yet reviewed in depth by a person. · How to read this page

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Land
448 acres
third party estimate [1]
Power it would draw
Not disclosed
Water
Not disclosed
Who leads it
Not disclosed
Who would use it
Not disclosed
Jobs once it runs
Not disclosed
Tax each year
Not disclosed
Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs Not disclosed
How much water it would use Not disclosed
How loud it would be Not disclosed
Jobs once it runs Not disclosed
Tax it would pay each year Not disclosed

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Not disclosed
Who is constructing it Not disclosed
How much land 448 acres third party estimate [1] yahoo.com September 25, 2026
Where its power comes from Not disclosed
Grid connection Not disclosed
How it is cooled Not disclosed

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water useA state water right filing or a water supply agreement.
  • Who would use itA lease announcement or a tenant named in a filing.
  • Power the campus would drawA utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind itA land record, a zoning application or a company's own announcement.
  • Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Shelby County and Westover about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Harpersville Harpersville adopted six month moratorium on data center development in August abc3340.com
Chelsea Chelsea adopted a one year moratorium on new data center applications abc3340.com
Harpersville Harpersville city council approved six month pause on data center projects in August 2026, followed by first of six public information sessions wvtm13.com
Chelsea Chelsea adopted a one year data center moratorium on July 21, 2026. yahoo.com

What happened

  1. · Status: rumored (source date; the content gives no date of its own)

    The proposed data center project is awaiting engineering confirmation from Alabama Power regarding sufficient incremental electricity capacity and from Shelby County water authority regarding water capacity. [1]

The full Westover Proposed Data Center timeline, in order

4 corrections to this record

Every correction, with its reason
  1. · the speaker role of a statements row

    Speaker read again from the statement's source line, "Council member Michael Shirley, Westover": the title in front of the name (Council member) is the role, not part of the name. The old and new text.

  2. · the speaker of a statements row

    Speaker read again from the statement's source line, "Council member Michael Shirley, Westover": the title in front of the name (Council member) is the role, not part of the name. The old and new text.

  3. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  4. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

Every correction on the record is on the corrections page.

What was said

Council member Michael Shirley requested that if the developer does not honor a 45 day wait period, the council should call a special meeting to consider a moratorium.
Michael Shirley, Council member, Westover · August 17, 2026 · paraphrased · www.yahoo.com national outlet

Every statement about data centers in Alabama, by speaker

The site

Where in Shelby County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.

  • This record: Proposed, ringed
  • data center
  • Dashed edge: the exact site is not in the public record
  • Smaller pins: 9 other published records in Alabama
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

Where
Westover, Shelby County, Alabama
How exactly it is located
County level, the county seat
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
Nearest records are not computed for a record placed at a county seat.

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Westover Proposed Data Center?

The record has one measure of its size: 448 acres (third party estimate, source). Its power capacity is not disclosed.

Who is building Westover Proposed Data Center?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

How much power and water does Westover Proposed Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

What has Westover or Shelby County decided about it?

Harpersville: Harpersville adopted six month moratorium on data center development in August (reported September 8, 2026, source); and Chelsea: Chelsea adopted a one year moratorium on new data center applications (reported September 8, 2026, source). 4 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. In Alabama, Westover delays data center moratorium vote, calls for town hall, www.yahoo.com, August 17, 2026, local outlet
  2. City of Westover hosting town hall on proposed data center Thursday night - WBRC 6 News, WBRC 6 News, August 20, 2026, local outlet
  3. Westover approves 6-month moratorium on data centers - WBRC 6 News, WBRC 6 News, August 18, 2026, local outlet

3 sources on file.

Cite this record

Data Center Record, "Westover Proposed Data Center", https://datacenterrecord.org/projects/westover-proposed-data-center-al, last verified September 25, 2026.

Last verified , first recorded . Every correction is logged on the corrections page and under What happened.

Cite this page

Data Center Record, "Westover Proposed Data Center", https://datacenterrecord.org/projects/westover-proposed-data-center-al. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Slug
westover-proposed-data-center-al
Status value
rumored
Stage
Proposed
Tier
skeleton
Tags
skeleton
Place id
us/al/shelby-county/westover
Coordinates
33.18355, -86.60936
Location precision
county
Location source
County seat (Columbiana), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location source number
Not disclosed
Location last verified
September 16, 2026
EPA registry id
Not disclosed
Use type values
not_disclosed
Tenancy value
not_disclosed
Cooling type value
not_disclosed
Capacity basis
not_disclosed
Water basis
not_disclosed, gallons_per_day
Acreage basis
third_party_estimate
Interconnection value
not_disclosed
Capacity, if disclosed
Not disclosed
Rating of the county's rows
Not disclosed
Published
2026-09-05
Last verified
2026-09-25