Every act on the record for Alabama, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.

The record by year

On the record as of October 27, 2026.

An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.

21 acts on the line for Alabama, from 61 dated lines in the records' histories and the scorecard. 15 more acts are dated only by the article that reported them and sit under their month. 1 line reports an act already listed. 24 lines are background, plans or statements. 6 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).

Narrow the acts
Kind
Topic
Developer

Each count is the number of lines on this page the chip keeps. Topics are matched from the words of each line and are a finding aid, not a fact about the event.

2026 11 acts on the line from 12 reports; 14 reported, dated only by the article; 17 lines of background, plans and statements

October 2026 2 acts on the line

  1. Ordinance Alabama

    Alabama Public Service Commission approved new transparency requirements for large data centers expected to draw 150 megawatts or more of electricity on a single contiguous property

    streamlinefeed.co.ke (opens in a new tab), international outlet

  2. Approval Alabama

    Alabama Public Service Commission approved rules requiring the commission to vote on each new data center project exceeding the 150 megawatt threshold within 90 days, with automatic approval if no vote occurs

    streamlinefeed.co.ke (opens in a new tab), international outlet

September 2026 No acts on the line; 9 reported; 7 lines of background, plans and statements

Reported in September 2026, dated only by the article that carried them: 9 acts
  1. Rate rule Alabama

    Alabama Power to the People Act takes effect in October, requires Alabama Public Service Commission to determine that any large data center contract with Alabama Power recovers full cost of serving that customer before approval

    yellowhammernews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Moratorium adopted Tarrant, Alabama

    City of Tarrant approved a 12 month moratorium on data centers

    abc3340.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Moratorium adopted Chelsea, Alabama

    Chelsea adopted a one year moratorium on new data center applications

    abc3340.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Moratorium Homewood, Alabama

    Homewood temporarily paused new data center applications

    abc3340.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. Munford, Alabama

    Public interest meeting on proposed data center scheduled for Sept. 10 at 6 p.m. at Munford Recreation Center Gym

    annistonstar.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  6. Moratorium Talladega County, Alabama

    Talladega County Commission and elected officials seeking one year moratorium on data center development

    annistonstar.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  7. Anniston, Alabama

    Anniston Planning Commission directed to study zoning, property sizes, residential separation, utility capacity, stormwater, transportation effects, backup generators, emergency response, noise, lighting and screening within six months.

    weisradio.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  8. Statement Brookwood, Alabama

    Brookwood City Council heard citizens concerns about a proposed data center.

    reutersconnect.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  9. Hearing Talladega County, Alabama

    Alabama leaders held a meeting in Talladega County to address questions about data centers

    wbrc.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for September 2026, not acts of their own: 7 lines of background, plans and statements
  1. Alabama

    Alabama's Power to the People Act requires the Alabama Public Service Commission to determine that any large data center contract with Alabama Power recovers the full cost of serving that customer before approval

    yellowhammernews.com (opens in a new tab) (a description, not an act)

  2. QTS Bessemer, Bessemer, Alabama

    Nebius AI data center project planned in Oxmoor Valley near Birmingham

    alreporter.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. QTS Bessemer, Bessemer, Alabama

    Project Marvel data center campus planned to cover roughly 1,600 acres in Bessemer area

    alreporter.com (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Tarrant, Alabama

    Tarrant City Council scheduled first reading of Ordinance No. 1177 establishing temporary moratorium on data center business license applications

    abc3340.com (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Tarrant, Alabama

    Ordinance would direct city to study feasibility of data centers and what standards should be established

    abc3340.com (opens in a new tab) (a plan or a schedule, not an act yet)

  6. Brookwood Proposed Data Center, Brookwood, Alabama

    Brookwood has a possible data center project near Brookwood Middle School

    abc3340.com (opens in a new tab) (a description, not an act)

  7. Alabama

    EPA proposal could restrict public access to information on data center plans

    apnews.com (opens in a new tab) (a plan or a schedule, not an act yet)

August 2026 6 acts on the line from 7 reports; 4 reported; 5 lines of background, plans and statements

  1. reported Brookwood Proposed Data Center, Brookwood, Alabama

    Brookwood data center proposal is 2 million square foot facility on Brookwood Parkway near Brookwood Middle School

    tuscaloosanews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Moratorium adopted Anniston, Alabama

    Anniston City Council adopted Resolution No. 26 R-97 on August 18, 2026, imposing a 12 month moratorium on data center permitting, development, expansion and licensing.

    weisradio.com (opens in a new tab), local outlet

    1 more report of this
    1. Aug 18 City of Anniston adopted Resolution No. 26 R-97 on August 18, 2026 establishing a 12 month temporary moratorium on permitting, development and licensing of data centers. wbrc.com (opens in a new tab)
  3. reported Westover Proposed Data Center, Westover, Alabama

    The proposed data center project is awaiting engineering confirmation from Alabama Power regarding sufficient incremental electricity capacity and from Shelby County water authority regarding water capacity.

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  4. Moratorium Westover, Alabama

    Westover city council postponed a vote on a proposed six month moratorium on data centers at a special meeting on August 6, 2026.

    yahoo.com (opens in a new tab), national outlet

  5. Moratorium adopted Harpersville, Alabama

    Harpersville adopted six month moratorium on data center development in August

    abc3340.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 8, 2026)

  6. Moratorium adopted Harpersville, Alabama

    Harpersville city council approved six month pause on data center projects in August 2026, followed by first of six public information sessions

    wvtm13.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 1, 2026)

Reported in August 2026, dated only by the article that carried them: 4 acts
  1. Alabama

    County commissions passed a resolution saying they do not want specific power to regulate data centers

    aldailynews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Anniston, Alabama

    Anniston Planning Commission directed to study data center issues and present recommendations within six months including appropriate locations, minimum lot sizes, electrical demand, water consumption, cooling systems, stormwater impacts, backup generators, noise and lighting standards, and neighborhood compatibility.

    wbrc.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Hearing Alabama

    A state senator held a hearing on a proposed Alabama data center

    thebatavian.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Moratorium adopted Westover, Alabama

    Westover approved a 6 month moratorium on data centers

    wbrc.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for August 2026, not acts of their own: 5 lines of background, plans and statements
  1. Brookwood Proposed Data Center, Brookwood, Alabama

    Applied Digital owns 1,300 acres in Brookwood

    tuscaloosathread.com (opens in a new tab) (a description, not an act)

  2. Alabama

    New Alabama law setting rules for hyperscale data centers effective October 1st

    tuscaloosathread.com (opens in a new tab) (no act in the sentence)

  3. Montgomery Meta Investment, Montgomery, Alabama

    Meta data center in Toney area expanding to 2.5 million square feet

    yahoo.com (opens in a new tab) (no act in the sentence)

  4. Westover, Alabama

    Mayor Bobby Pardue scheduled a public town hall on August 20, 2026 to discuss the proposed data center and allow residents to raise concerns directly.

    yahoo.com (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Alabama

    Bitcoin mining data center permitted despite county and town moratoriums due to state zoning law gap

    tomshardware.com (opens in a new tab) (no act in the sentence)

July 2026 1 act on the line; 1 reported

  1. Moratorium adopted Chelsea, Alabama

    Chelsea adopted a one year data center moratorium on July 21, 2026.

    yahoo.com (opens in a new tab), national outlet

Reported in July 2026, dated only by the article that carried it: 1 act
  1. Alabama

    Alabama Power made a data center contract publicly available with redacted sections

    wbrc.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

June 2026 No acts on the line; 1 line of background, plans and statements

Also on the record for June 2026, not acts of their own: 1 line of background, plans and statements
  1. Google Bridgeport data center, Bridgeport, Alabama

    Less than a quarter of the campus property has been developed so far

    youtube.com (opens in a new tab) (a description, not an act)

February 2026 1 act on the line; 4 lines of background, plans and statements

  1. Approval Alabama

    The Alabama Public Service Commission issued an approval order for Alabama Power to build solar facilities to power Meta data center

    fox10tv.com (opens in a new tab), local outlet

Also on the record for February 2026, not acts of their own: 4 lines of background, plans and statements
  1. Baldwin County, Alabama

    Hundreds of residents packed a Baldwin County town hall on February 9, 2026 to oppose the solar farm approved to power the Meta data center in Montgomery

    fox10tv.com (opens in a new tab) (a description, not an act)

  2. Montgomery Meta Investment, Montgomery, Alabama

    Silicon Ranch will begin building sometime in 2027 with the solar farm's lifespan expected to be at least 25 years

    fox10tv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Montgomery Meta Investment, Montgomery, Alabama

    Construction planned to begin by end of 2026, taking 12-18 months

    mynbc15.com (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Montgomery Meta Investment, Montgomery, Alabama

    Silicon Ranch planning solar farm on 4,500 acres in Baldwin County to power Meta data center

    mynbc15.com (opens in a new tab) (a plan or a schedule, not an act yet)

2026, no month given 1 act

  1. Moratorium Alabama

    Several Alabama cities placed moratoriums on new data center projects in 2026, including Fort Payne, Cullman, Birmingham, Leeds, and Homewood

    yellowhammernews.com (opens in a new tab), local outlet (the year its own sentence names; filed under Sep 7, 2026)

2025 4 acts on the line; 1 reported, dated only by the article; 4 lines of background, plans and statements

December 2025 No acts on the line; 1 reported

Reported in December 2025, dated only by the article that carried it: 1 act
  1. Approval Alabama

    Alabama Public Service Commission approved two year electric rate freeze and two solar projects for Meta data center

    insideclimatenews.org (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)

September 2025 2 acts on the line; 4 lines of background, plans and statements

  1. Montgomery Meta Investment, Montgomery, Alabama

    Meta announced plans to invest in two new buildings at its Montgomery Data Center

    alreporter.com (opens in a new tab), local outlet

  2. Expansion being built Montgomery Meta Investment, Montgomery, Alabama

    Montgomery Data Center campus is expanding with two new buildings

    datacenters.atmeta.com (opens in a new tab), primary source

Also on the record for September 2025, not acts of their own: 4 lines of background, plans and statements
  1. Montgomery Meta Investment, Montgomery, Alabama

    Meta has donated to STEM programs at Montgomery Public Schools and launched district wide robotics program

    wsfa.com (opens in a new tab) (a description, not an act)

  2. Montgomery Meta Investment, Montgomery, Alabama

    Mass timber provider Binderholz is partnering on the project alongside Hensel Phelps.

    acppubs.com (opens in a new tab) (a description, not an act)

  3. Montgomery Meta Investment, Montgomery, Alabama

    The administrative facility utilizes mass timber construction as a renewable, lower carbon alternative to traditional steel and concrete.

    acppubs.com (opens in a new tab) (no act in the sentence)

  4. Montgomery Meta Investment, Montgomery, Alabama

    Hensel Phelps is providing general contractor services for a new administrative facility at Meta's Montgomery, Alabama data center campus.

    acppubs.com (opens in a new tab) (a description, not an act)

August 2025 1 act on the line

  1. Expansion approved Montgomery Meta Investment, Montgomery, Alabama

    Meta will construct additional mass timber buildings at Cheyenne, Wyoming and Montgomery, Alabama data center campuses.

    esgdive.com (opens in a new tab), trade press

2025, no month given 1 act

  1. Montgomery Meta Investment, Montgomery, Alabama

    Meta announced in 2025 that its investment in the Montgomery campus increased to more than $1.5 billion

    yellowhammernews.com (opens in a new tab), local outlet (the year its own sentence names; filed under Aug 11, 2026)

2024 4 acts on the line; 3 lines of background, plans and statements

May 2024 2 acts on the line

  1. being built Montgomery Meta Investment, Montgomery, Alabama

    Meta plans 800 million dollar data center in Montgomery

    wsfa.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Montgomery Meta Investment, Montgomery, Alabama

    Meta project began in May 2024

    wsfa.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 23, 2025)

April 2024 2 acts on the line; 3 lines of background, plans and statements

  1. approved Montgomery Meta Investment, Montgomery, Alabama

    The facility will be Meta's 20th data center in the United States and its second in Alabama after Huntsville, as reported by AI Business

    youtube.com (opens in a new tab), video

  2. Montgomery Meta Investment, Montgomery, Alabama

    Meta first announced an $800 million investment to begin construction of the data center in April 2024

    alreporter.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 24, 2025)

Also on the record for April 2024, not acts of their own: 3 lines of background, plans and statements
  1. Montgomery Meta Investment, Montgomery, Alabama

    The facility will feature mass timber in the construction of its administration building

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  2. Montgomery Meta Investment, Montgomery, Alabama

    The facility will be powered by 100 percent renewable energy

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Montgomery Meta Investment, Montgomery, Alabama

    The facility will be Meta's 24th global data center

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

2019 2 acts on the line

2019, no month given 2 acts

  1. reported Google Bridgeport data center, Bridgeport, Alabama

    Google's Bridgeport, Alabama data center began operating in 2019 (the video names the year only); corrects the entry dated June 19, 2026, which carried the video's upload date

    youtube.com (opens in a new tab), video (the year its own sentence names; filed under Jan 1, 2019)

  2. Google Bridgeport data center, Bridgeport, Alabama

    The data center began operating in 2019

    youtube.com (opens in a new tab), video (the year its own sentence names; filed under Jun 19, 2026)