● Proposed Campus Recorded January 1, 2019

Google Bridgeport data center

Street address 48809 Alabama Hwy 277, Bridgeport, AL 35740, Jackson County permit coordinates Exact, the point of the EPA's facility record [1] EPA ECHO detailed facility report: Google LLC

Overview, regulatory gates and specifications

Google's data center campus in Bridgeport, Jackson County, Alabama, operating since 2019 on a site of more than 600 acres. [1] The data center began operating in 2019 [3]

Verified Site & Permit Summary
Verified address
48809 Alabama Hwy 277, Bridgeport, AL 35740, Jackson County permit coordinates
Operator / developer
Google
Permit / registry ID
U.S. Environmental Protection Agency on file [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Google as stated by the source
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Bridgeport data center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    The data center began operating in 2019

    · Google · Reported June 19, 2026 · Privacy enhanced player · loads on click

    [3] youtube.com

  2. (source date; the content gives no date of its own)

    Less than a quarter of the campus property has been developed so far

    · Google · Reported June 19, 2026 · Privacy enhanced player · loads on click

    [3] youtube.com

  3. · Status: rumored (content date)

    Google's Bridgeport, Alabama data center began operating in 2019 (the video names the year only); corrects the entry dated June 19, 2026, which carried the video's upload date

    · Google · January 1, 2019 · Privacy enhanced player · loads on click

    [3] youtube.com

Every event in order

13 corrections to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: video is tier 5 (the editor, September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: video is tier 5 (the editor, September 23, 2026). The link did not change.

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: video is tier 5 (the editor, September 23, 2026). The link did not change.

  5. · Timeline entry

    The note "(Entry dated by the video's upload date; see the correction.)" appended by the date correction of September 8, 2026 belongs in this log, not in the event sentence; the date basis of the row already says the date is the source's. The sentence is restored to the event only (September 13, 2026).

  6. · Timeline entry

    The note "(Entry dated by the video's upload date; see the correction.)" appended by the date correction of September 8, 2026 belongs in this log, not in the event sentence; the date basis of the row already says the date is the source's. The sentence is restored to the event only (September 13, 2026).

  7. · Date basis

    Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.

  8. · Date basis

    Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.

  9. · Date basis

    Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.

  10. · Date basis

    Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.

  11. · Date basis

    Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.

  12. · Timeline entry

    Dated by the video's upload date (ABC News, June 19, 2026), which is the source date; the corrected entry dated January 1, 2019 carries the year the video gives.

  13. · Timeline entry

    Dated by the video's upload date (ABC News, June 19, 2026), which is the source date; the content says so far, no other date.

Every correction on the record is on the corrections page.

Nearest data centers in Alabama

Verified data center records in Alabama within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Meta Huntsville Data Center Huntsville, Madison County 52 mi Running Meta

Blank cell: not disclosed by any source on file.

Common questions about Google Bridgeport data center

Answered directly from the verified filings and local actions on this page.

Who is building Google Bridgeport data center?

Google is the developer. No construction contractor is named on the record yet.

How much power and water does Google Bridgeport data center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Google Bridgeport data center stand today?

It is reported, since January 1, 2019. The newest entry, reported June 19, 2026: The data center began operating in 2019 [3].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. EPA ECHO detailed facility report: Google LLC (opens in a new tab), U.S. Environmental Protection Agency
  2. Google: Data center locations (opens in a new tab), Google, September 14, 2026

Reporting

  1. Inside Google's AI data centers (opens in a new tab), YouTube, June 19, 2026, video

3 sources on file.

Regional grid context

This site is in the SERC South (SRSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Bridgeport data center", https://datacenterrecord.org/projects/google-bridgeport-data-center-al, last verified October 4, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Bridgeport data center", https://datacenterrecord.org/projects/google-bridgeport-data-center-al. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
34.930645, -85.731149
How the location is known
Location from an EPA facility record.
Location source
https://echo.epa.gov/detailed-facility-report?fid=110070571480
Coordinate source
https://echo.epa.gov/detailed-facility-report?fid=110070571480
Location source number
[1]
Location last verified
October 4, 2026
EPA registry id
110070571480
Published
September 8, 2026
Last verified
October 4, 2026
Not disclosed
Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google Bridgeport data center · 3 sources, 3 entries · basis and source tier on every row · verified October 4, 2026