Data centers in Oregon

Oregon has 13 data center sites, 0 buildings where disclosed on the record: 10 running, 2 proposed and 1 stalled or cancelled. Most are in Washington County (5) and Crook County (2), and records are in 8 of 36 counties. The largest proposal is Hillsboro data center projects (7 in permitting) in Washington County, 36 MW (the developer's figure); it is reported, as reported May 28, 2026.

Oregon limits new data centers. From the state's own rule: Governor Kotek issued executive order pausing all state agency action on data center land requests on September 8, 2026.

5 sites the EPA's registry shows and no record has verified are on the map apart from the count. What not yet verified means.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Projects and campuses on the record

Facility and countyStageOperatorPower (MW)Latest entry
Oakline at Mill Creek Salem, Marion CountyProposed Waiting on permitsVerrusVerrus $5.1 billion data center project at Mill Creek Corporate Center prohibited from construction phase as long as moratorium is in effect salemreporter.com (opens in a new tab) local outlet reported September 22, 2026
Hillsboro data center projects (7 in permitting) Hillsboro, Washington CountyProposed36Flexential announced plans for Hillsboro 6 after purchasing additional property prnewswire.com (opens in a new tab) press release reported May 28, 2026
Aligned PDX-01 Hillsboro, Washington CountyRunningAligned Data Centers
Digital Realty Hillsboro Hillsboro, Washington CountyRunningDigital Realty
H5 Portland Portland, Multnomah CountyRunningH5 Data Centers
QTS Data Centers Hillsboro Hillsboro, Washington CountyRunningQTS Data Centers
STACK Infrastructure Hillsboro Hillsboro, Washington CountyRunningSTACK Infrastructure
Google The Dalles data center The Dalles, Wasco CountyRunningGoogleGoogle opened its first company owned data center in The Dalles in 2006. columbiacommunityconnection.com (opens in a new tab) local outlet reported September 16, 2026
Amazon Eastern Oregon Data Centers Boardman, Morrow CountyRunningAmazonAmazon data center project is proceeding in the Boardman area with Oregon Department of Environmental Quality opening public comment period for air quality permit opb.org (opens in a new tab) local outlet reported September 10, 2026
Amazon data centers in Lower Umatilla Basin Hermiston, Umatilla CountyRunningAmazonOPB reported that the Lower Umatilla Basin, which includes the towns of Boardman, Hermiston and Umatilla, has 14 large data centers, all owned by Amazon, and described one of them near Umatilla as a data center operated by Amazon. opb.org (opens in a new tab) local outlet reported July 22, 2026

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 13 Oregon projects.

Every Oregon record 13 records, and 5 sites not yet verified listed apart · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Crane Data CenterForest Grove, WashingtonNot yet verifiedEPA registry22026-10-20
Infomart Data Center, Cascadia 02Hillsboro, WashingtonNot yet verifiedEPA registry22026-10-20
NTT Global Data Centers Hi, LLCHillsboro, WashingtonNot yet verifiedNTT DATAEPA registry22026-10-20
T5 At Portland IV Data CenterHillsboro, WashingtonNot yet verifiedEPA registry22026-10-20
Sabey Umatilla Data CenterUmatilla, UmatillaNot yet verifiedSabey Data CentersEPA registry22026-10-03
Oakline at Mill CreekSalem, MarionProposedVerrussite12026-09-22
Aligned PDX-01Hillsboro, WashingtonRunningAligned Data Centerscentroid12026-09-17
Digital Realty HillsboroHillsboro, WashingtonRunningDigital Realtycentroid22026-09-17
H5 PortlandPortland, MultnomahRunningH5 Data Centerscentroid22026-09-17
QTS Data Centers HillsboroHillsboro, WashingtonRunningQTS Data Centerscentroid22026-09-17
STACK Infrastructure HillsboroHillsboro, WashingtonRunningSTACK Infrastructurecentroid22026-09-17
Google The Dalles data centerThe Dalles, WascoRunningGooglecentroid12026-09-17
Amazon Eastern Oregon Data CentersBoardman, MorrowRunningAmazoncentroid22026-09-17
Amazon data centers in Lower Umatilla BasinHermiston, UmatillaRunningAmazoncentroid12026-09-17
Hillsboro data center projects (7 in permitting)Hillsboro, WashingtonProposed36the developer's figurecentroid42026-09-25
Boxminer.io La Pine Industrial ParkLa Pine, DeschutesStalled or cancelledBoxminer.io20the developer's figurecentroid42026-09-17
Apple Prineville CampusPrineville, CrookRunningApple120third party estimateEPA registry22026-10-19
Meta Prineville CampusPrineville, CrookRunningMeta350third party estimatecentroid22026-10-19

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every Oregon county (36)

8 of 36 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRules
Washington County4106752
Crook County4101321
Deschutes County4101710
Marion County4104713
Morrow County4104910
Multnomah County4105111
Umatilla County4105910
Wasco County4106511
Clackamas County4100501
Lane County4103901

A county without a record is listed, not linked.

26 counties with no records yet
  • Baker County
  • Benton County
  • Clatsop County
  • Columbia County
  • Coos County
  • Curry County
  • Douglas County
  • Gilliam County
  • Grant County
  • Harney County
  • Hood River County
  • Jackson County
  • Jefferson County
  • Josephine County
  • Klamath County
  • Lake County
  • Lincoln County
  • Linn County
  • Malheur County
  • Polk County
  • Sherman County
  • Tillamook County
  • Union County
  • Wallowa County
  • Wheeler County
  • Yamhill County

The rules in Oregon 11 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
Oregonstaterestrictive until July 1, 20272027-07-01Governor Kotek issued executive order pausing all state agency action on data center land requests on September 8, 2026. wweek.com (opens in a new tab) local outlet Sep 8, 202634 acts on this row
Every act on the Oregon row
  1. moratorium

    Oregon Governor Tina Kotek directed the Department of Environmental Quality to pause issuing new air or water quality permits for data center projects until July 2027

    rtoinsider.com (opens in a new tab) trade press

    Also reported by 3 sources
  2. event

    Governor Kotek directed the environmental agency to stop processing applications from cities and counties seeking to renew or modify wastewater permits to accommodate data centers.

    opb.org (opens in a new tab) local outlet

  3. moratorium

    Kotek issued a roughly one year pause she recently ordered on approvals to develop data centers on state land or in state buildings.

    bankspost.com (opens in a new tab) news outlet

  4. moratorium adopted

    Oregon Gov. Tina Kotek ordered the Oregon Department of Environmental Quality to pause all air and water discharge permits for data centers until July 2027

    salemreporter.com (opens in a new tab) local outlet

  5. rate rule

    Pacific Power agreed to charge data center operators for all costs of energy infrastructure expansion needed to serve data centers

    salemreporter.com (opens in a new tab) local outlet

  6. event

    Governor Tina Kotek directed state agencies to hold off on unapproved requests for new data centers on state owned land until next year

    kptv.com (opens in a new tab) local outlet

    Also reported by 1 source
  7. moratorium

    Governor Kotek announced a roughly one year pause on approvals for data center requests on state land or in state buildings

    oregoncapitalchronicle.com (opens in a new tab) local outlet

  8. hearing

    A 45 day public comment period opened on the committee's preliminary findings, closing October 24, 2026

    katu.com (opens in a new tab) local outlet

  9. moratorium

    Governor Tina Kotek directed every state agency to immediately pause unapproved requests for data center projects involving state owned land through July 1 2027

    katu.com (opens in a new tab) local outlet

    Also reported by 1 source
  10. moratorium

    Oregon Governor Tina Kotek announced a pause on data center approvals

    thealaskastory.com (opens in a new tab) local outlet

  11. event

    The Data Center Advisory Committee released preliminary findings on September 10, 2026

    katu.com (opens in a new tab) local outlet

  12. moratorium

    Hundreds of Oregonians rallied at state Capitol on Tuesday demanding statewide moratorium on data centers

    katu.com (opens in a new tab) local outlet

  13. hearing

    House Interim Committee on Climate Energy and Environment held hearing on data center development

    katu.com (opens in a new tab) local outlet

  14. moratorium

    Governor directs pause on unapproved data center requests for state owned property through July 1 2027

    katu.com (opens in a new tab) local outlet

  15. event

    Governor Tina Kotek announces new directive on state land for data centers

    statesmanjournal.com (opens in a new tab) local outlet

    Also reported by 2 sources
  16. event

    Governor Kotek issued executive order pausing all state agency action on data center land requests on September 8, 2026

    wweek.com (opens in a new tab) local outlet

    Also reported by 11 sources
  17. moratorium

    Four state Democratic lawmakers announced they would propose legislation in 2027 to pause creation of new large data centers in Oregon for three years

    oregoncapitalchronicle.com (opens in a new tab) local outlet

  18. event

    Drazan voted against the POWER Act, a 2025 state law creating separate rate class for data centers

    oregoncapitalchronicle.com (opens in a new tab) local outlet

  19. event

    Poll found Oregonians want no more tax breaks for data centers

    oregonlive.com (opens in a new tab) local outlet

  20. rate rule

    The Oregon Public Utility Commission approved Portland General Electric's compliance filing under the POWER Act (Order No. 26-239), with rates effective July 8, 2026 that lower residential rates an average of 1.3 percent and raise data center customers' rates an average of 29 percent.

    apps.puc.state.or.us (opens in a new tab) primary source

    Also reported by 1 source
  21. rate rule

    Oregon Public Utility Commission approved PGE's large load tariff framework for data centers

    utilitydive.com (opens in a new tab) trade press

  22. event

    Oregon state regulators ruled that data centers must pay more for electricity

    oregonlive.com (opens in a new tab) local outlet

  23. moratorium adopted

    Oregon Connects registered as a nonprofit business in Oregon on March 4, 2026, just days before the Oregon Legislature passed a one year pause on the Standard Enterprise Zone tax incentive program for data centers

    opb.org (opens in a new tab) local outlet

  24. moratorium

    Oregon moves toward 1 year moratorium on some data center tax breaks

    oregonlive.com (opens in a new tab) local outlet

  25. event

    Oregon lawmakers considered adding Hillsboro industrial land and providing larger tax breaks for data centers

    oregonlive.com (opens in a new tab) local outlet

  26. event

    Oregon governor formed a new committee to advise on data center growth

    oregoncapitalchronicle.com (opens in a new tab) local outlet

  27. event

    Gov. Tina Kotek announced new Data Center Advisory Committee in January 2026 with seven members

    redmondspokesman.com (opens in a new tab) news outlet

  28. event

    Kotek convened the Oregon Data Center Advisory Committee in January to develop policy recommendations to address growth in data centers

    bondbuyer.com (opens in a new tab) news outlet

    Also reported by 2 sources
  29. event

    Oregon House of Representatives passed bill in June 2025 to ensure data centers and cryptocurrency operations cover fair share of costs for new power plants and transmission lines

    datacenterdynamics.com (opens in a new tab) trade press

  30. rate rule

    POWER Act was passed in 2025 creating new rate class for large energy users

    opb.org (opens in a new tab) local outlet

  31. event

    Oregon POWER Act enacted in 2025 to treat large data centers as a distinct class of electricity customer

    yahoo.com (opens in a new tab) national outlet

  32. event

    In 2025, Kotek signed the Protecting Oregonians With Energy Responsibility (POWER) Act

    kptv.com (opens in a new tab) local outlet

    Also reported by 2 sources
  33. statement

    Oregon schools and districts lost $275 million to property tax abatements in 2024, which is more than double the $125 million lost in 2019, according to a Good Jobs First report showing data center tax exemptions as the primary driver

    bendbulletin.com (opens in a new tab) local outlet

  34. event

    Tina Kotek voted in 2012 to pass a bill ensuring tech companies operating data centers in enterprise zones are taxed only on physical assets under five and ten year property tax breaks

    oregoncapitalchronicle.com (opens in a new tab) local outlet

Last verified October 14, 2026.

342026-10-14
Clackamas Countycountynot ratedClackamas County Board of Commissioners voted unanimously to start the formal process for a moratorium on data center applications. yahoo.com (opens in a new tab) national outlet Reported Aug 192 acts on this row
Every act on the Clackamas County row
  1. moratorium

    Clackamas County Board of Commissioners voted unanimously to start the formal process for a moratorium on data center applications

    yahoo.com (opens in a new tab) national outlet

  2. moratorium

    The Legislature enacted a one year pause on new enterprise zone tax exemptions for urban and suburban data centers

    katu.com (opens in a new tab) local outlet

Last verified September 14, 2026.

22026-09-14
Eugenecitynot ratedThe City of Eugene stopped a data center from moving into the former Hynix site, citing local land regulation rules. kval.com (opens in a new tab) local outlet Reported Sep 152 acts on this row
Every act on the Eugene row
  1. event

    The City of Eugene stopped a data center from moving into the former Hynix site, citing local land regulation rules.

    kval.com (opens in a new tab) local outlet

  2. hearing

    72 people gave public comment at the Eugene City Council meeting raising concerns about energy and water use, noise, and jobs from data centers.

    kval.com (opens in a new tab) local outlet

Last verified September 15, 2026.

22026-09-15
Hillsborocityrestrictive until November 24, 20262026-11-24Hillsboro, Oregon also approved its own pause at a last minute July 27 meeting. yahoo.com (opens in a new tab) national outlet Jul 27, 20267 acts on this row
Every act on the Hillsboro row
  1. moratorium adopted

    Hillsboro City Council enacted a 120 day moratorium on new data center developments.

    kptv.com (opens in a new tab) local outlet

  2. moratorium

    Hillsboro put 120 day moratorium on data center projects at end of July 2026

    datacenterdynamics.com (opens in a new tab) trade press

  3. moratorium adopted

    Hillsboro City Council voted for a moratorium on all new data center construction.

    klcc.org (opens in a new tab) local outlet

  4. moratorium adopted

    Hillsboro City Council unanimously adopted 120 day moratorium on data center and battery energy storage land use applications on July 28 2026

    opb.org (opens in a new tab) local outlet

    Also reported by 2 sources
  5. moratorium adopted

    Hillsboro, Oregon also approved its own pause at a last minute July 27 meeting

    yahoo.com (opens in a new tab) national outlet

  6. moratorium adopted

    Hillsboro enacted a 120 day moratorium on new data center and battery storage applications in late July 2026

    kptv.com (opens in a new tab) local outlet

  7. litigation

    A legal challenge has been filed to stop Hillsboro, Oregon data center deals

    hillsboroherald.com (opens in a new tab) news outlet

Last verified September 23, 2026.

72026-09-23
Marion Countycountynot ratedSpecial meeting vote to initiate a data center moratorium. salemreporter.com (opens in a new tab) local outlet Aug 3, 20261 act on this row
Every act on the Marion County row
  1. moratorium

    Salem City Council voted unanimously at a special meeting to initiate a moratorium on new data center applications, with a 45 day state notice and a public hearing still required before it takes effect.

    salemreporter.com (opens in a new tab) local outlet

Last verified September 23, 2026.

12026-09-23
Portlandcitynot ratedThe resolution instructs city staff to alert council if an outside company requests a preliminary meeting or permit for a facility drawing 20 megawatts or more. kptv.com (opens in a new tab) local outlet Reported Sep 142 acts on this row
Every act on the Portland row
  1. event

    The resolution instructs city staff to alert council if an outside company requests a preliminary meeting or permit for a facility drawing 20 megawatts or more.

    kptv.com (opens in a new tab) local outlet

  2. rate rule

    Oregon regulators approved a 30 percent electricity rate hike for data centers near Portland

    oregonlive.com (opens in a new tab) local outlet

Last verified September 14, 2026.

22026-09-14
Prinevillecitynot ratedPrineville officials were in discussion with two additional companies about building data centers in the town where Facebook opened its first company built data center. datacenterknowledge.com (opens in a new tab) trade press Reported May 31, 20241 act on this row
Every act on the Prineville row
  1. event

    Prineville officials were in discussion with two additional companies about building data centers in the town where Facebook opened its first company built data center

    datacenterknowledge.com (opens in a new tab) trade press

Last verified May 31, 2024.

12024-05-31
Salemcityrestrictive until January 19, 20272027-01-19Salem and Woodburn have adopted moratoriums on data centers. katu.com (opens in a new tab) local outlet Aug 24, 202616 acts on this row
Every act on the Salem row
  1. moratorium

    Salem city council voted to accept 120 day moratorium on all new data center projects with option to extend by additional six months before year end

    salemreporter.com (opens in a new tab) local outlet

  2. moratorium adopted

    Salem City Council voted to approve a four month moratorium on development and construction of data centers across the city effective through January 19, 2027

    kptv.com (opens in a new tab) local outlet

  3. moratorium adopted

    Salem city council approved 120 day moratorium on all new data center projects using more than two megawatts of power, effective immediately

    salemreporter.com (opens in a new tab) local outlet

  4. hearing

    Salem held first of three town halls to gather community input on data centers, with city council to consider formal proposal in December 2026

    kptv.com (opens in a new tab) local outlet

  5. event

    Salem city councilors voted 8-1 on a motion to consider new regulations around the city's use of non disclosure agreements related to data center developments

    salemreporter.com (opens in a new tab) local outlet

  6. event

    Salem's Data Center Task Force held a town hall on September 15, 2026, at Broadway Commons to gather community input on data center policy.

    salemreporter.com (opens in a new tab) local outlet

  7. event

    Task force was formed in response to community outcry over a $5.1 billion data center project proposed in Salem

    salemreporter.com (opens in a new tab) local outlet

  8. event

    Salem Data Center Task Force holds first of three town halls to address data center policies at Broadway Commons

    salemreporter.com (opens in a new tab) local outlet

  9. moratorium

    A Salem City Council special meeting considered a temporary citywide data center moratorium.

    democratherald.com (opens in a new tab) local outlet

  10. event

    Oregon Governor Kotek halted the sale of land for a data center in Salem at the Mill Creek Corporate Center, approximately 32 acres of state land

    bondbuyer.com (opens in a new tab) news outlet

    Also reported by 1 source
  11. ordinance

    Salem City Council adopted resolution to update zoning code and land use regulations to protect water, environment and electricity

    statesmanjournal.com (opens in a new tab) local outlet

  12. moratorium

    Salem City Council voted to move forward with temporary moratorium on AI data centers

    statesmanjournal.com (opens in a new tab) local outlet

  13. moratorium

    Salem City Council voted unanimously to pursue a moratorium in early August 2026.

    salemreporter.com (opens in a new tab) local outlet

  14. event

    Kotek directed the state to stop the sale of state owned land in southeast Salem for a data center project on July 30

    statesmanjournal.com (opens in a new tab) local outlet

  15. event

    Salem City Council formed Data Center Task Force on July 27, 2026

    statesmanjournal.com (opens in a new tab) local outlet

    Also reported by 1 source
  16. event

    Kotek intervened to stop a data center proposed on state owned Department of Corrections land in Salem in March.

    democratherald.com (opens in a new tab) local outlet

Last verified September 23, 2026.

162026-09-23
Wasco Countycountynot ratedWasco County commissioners unanimously approved placing 15 million dollars into Community Endowment and Resiliency Fund. columbiacommunityconnection.com (opens in a new tab) local outlet Reported Sep 231 act on this row
Every act on the Wasco County row
  1. event

    Wasco County commissioners unanimously approved placing 15 million dollars into Community Endowment and Resiliency Fund

    columbiacommunityconnection.com (opens in a new tab) local outlet

Last verified September 23, 2026.

12026-09-23
Washington Countycountynot ratedWashington County Commissioner Nafisa Fai announced her intention to bring forward a proposal that would temporarily pause new data center and AI computing facility development and permitting countywide. katu.com (opens in a new tab) local outlet Reported Aug 241 act on this row
Every act on the Washington County row
  1. moratorium

    Washington County Commissioner Nafisa Fai announced her intention to bring forward a proposal that would temporarily pause new data center and AI computing facility development and permitting countywide

    katu.com (opens in a new tab) local outlet

Last verified September 23, 2026.

12026-09-23
Woodburncityrestrictive until January 13, 20272027-01-13Woodburn City Council unanimously approved 120 day moratorium on data center development on September 15, 2026. opb.org (opens in a new tab) local outlet Sep 15, 20262 acts on this row
Every act on the Woodburn row
  1. moratorium

    The moratorium temporarily pauses approval, review, and acceptance of development proposals and permits for new data centers including data storage, processing, and information technology centers

    koin.com (opens in a new tab) local outlet

    Also reported by 1 source
  2. moratorium adopted

    Woodburn City Council unanimously approved 120 day moratorium on data center development on September 15, 2026

    opb.org (opens in a new tab) local outlet

    Also reported by 3 sources

Last verified September 16, 2026.

22026-09-16

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

Oregon laws and the full scorecard

Bills and laws in Oregon

2 signed into law, 4 bills tracked

4 bills tracked in the Oregon legislature, 2 of them signed into law, grouped by where each stands. A row opens its own page; the Oregon laws page has what each law requires.

Signed into law 2

  • Relating to economic development; and prescribing an effective date.

    HB 4084 Signed

    What it says and where it is from

    The Act would set up a Joint Permitting Council to run a fast track permit program. The Act would direct certain state agencies to publish a list of certain permits that can be issued by the agencies. The Act would adjust certain requirements of the enterprise zone program and restrict the use of the program for data centers. The Act would adjust the tax credit for a taxpayer that creates new jobs. (Flesch Readability Score: 67.5). [Digest: The Act would set up a Joint Permitting Council to run a fast track permit program.] [The Act would direct certain state agencies to publish a list of certain permits that can be issued by the agencies.] [The Act would adjust certain requirements of the enterprise zone program.] [The Act would give money to OBDD. (Flesch Readability Score: 71.3).] Establishes the Joint Permitting Council. Directs the council to administer a fast track permitting program. Directs certain state agencies to publish a catalog of permits related to economic development projects issued by the agencies within 120 days after the effective date of the Act. Updates certain requirements and thresholds for the enterprise zone program. Restricts the use of the program for data centers. [Appropriates moneys to the Oregon Business Development Department for deposit in the Industrial Site Loan Fund.] Modifies provisions establishing a personal income or corporate excise tax credit for a taxpayer that creates new jobs. Takes effect on the 91st day following adjournment sine die. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Relating to central assessment; and prescribing an effective date.

    SB 611 Signed

    What it says and where it is from

    Grants property tax exemption to property of centrally assessed company in amount of positive value obtained by subtracting from real market value of company's real property and tangible and intangible personal property included in unit subject to central assessment, reduced by amount of certain elective exemptions, amount equal to historical or original cost of company's real property and tangible personal property included in unit subject to central assessment, without reduction for certain el ective exemptions, multiplied by 130 percent. Provides amount of exemption may not exceed amount equal to 95 percent of real market value of company's real property and tangible and intangible personal property included in unit subject to central assessment. Grants property tax exemption to property of centrally assessed company if company completes and] builds, maintains and operates communication infrastructure project that meets certain service standards. Requires submission of application to Public Utility Commission with fee to be distributed equally to commission for costs of reviewing application and Department of Revenue for costs of appraising project property. Provides for exemption in amount of positive value obtained by subtracting from Oregon allocated real market value of company's real property and tangible and intangible personal property included in unit subject to central assessment, reduced by Oregon allocated amount of certain elective exemptions, amount equal to greater of $250 million or real market value of company's real and tangible personal property located in Oregon, without reduction for certain elective exemptions. Provides exemption granted for lesser of 20 consecutive property tax years or period during which company] owner maintains and operates communication infrastructure project. Provides, for company eligible for both property tax exemptions, Department of Revenue shall compute property taxes on property under both exemptions and impose taxes that result in least amount of] appraise company's property using provisions of exemption that result in lowest taxable value. Requires Public Utility Commission to report on property tax exemptions] communication infrastructure project exemption to interim committees of Legislative Assembly related to revenue no later than February 1 of each year. Allows company that owns, leases or uses licenses granted by Federal Communications Commission, franchises used in business of communication or satellites used to provide communication services directly to retail customers and licenses granted by Federal Communications Commission related to use of satellites, to elect one of above types of property for property tax exemption. Provides value of property shall equal cost of property carried in accounting records of owner, less accrued depreciation reserve. Provides that value of franchises allocated to Oregon shall be subtracted from assessed value of company's property.] Removes, for purposes of exclusion from central assessment, requirement that data center company have tax abatement agreement with sponsors of enterprise zone. Clarifies that statute applies only to company in business of communication. Raises maximum allowable percentage of cost of property other than data center property and changes base to cost of property used in business of communication. Specifies certain noncommunication related property excluded from determination of maximum allowable percentage. Provides that company is not subject to central assessment solely because company manufactures or sells property used by any person in communication. Provides for local assessment of data center property used or held for future use by company whose property is not centrally assessed or by company Takes effect on 91st day following adjournment sine die. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

Failed or died 2

  • Relating to data centers.

    H.B. 3698 Died at adjournment

    What it says and where it is from

    This Act tells data centers to report how much water and electricity they use each quarter. The Act tells the EQC to adopt emissions rules for generators used at data centers. (Flesch Readability Score: 60.1). Directs data centers to report water and electricity used to the Water Resources Department and the State Department of Energy. Requires the State Department of Energy to publish summaries of reported information on a website. Directs the Environmental Quality Commission to adopt emissions standards for standby generators used at data centers. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Relating to data center power usage.

    S.B. 553 Died at adjournment

    What it says and where it is from

    Tells ODOE to study data center power usage and give a report on its findings. (Flesch Readability Score: 61.8). Requires the State Department of Energy to study data center power usage. Directs the department to submit findings to the interim committees of the Legislative Assembly related to energy not later than September 15, 2026. Sunsets on January 2, 2027. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

4 bills tracked, 2 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
HB 4084 2026 Legislative Measures Signed 2026-04-06 Relating to economic development; and prescribing an effective date.
H.B. 3698 2025 Legislative Measures Died at adjournment 2025-06-27 Relating to data centers.
S.B. 553 2025 Legislative Measures Died at adjournment 2025-06-27 Relating to data center power usage.
SB 611 2015 Legislative Measures Signed 2015-04-07 Relating to central assessment; and prescribing an effective date.

4 bills tracked in Oregon; 2026 Legislative Measures, legislature adjourned; last checked October 26, 2026. The last check found no bill not already tracked; the 4 tracked bills stand. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. Oregon's members: 6 yea, 0 nay. How each member voted

MemberPartyPosition
BentzRYea
BonamiciDYea
BynumDYea
DexterDYea
Hoyle (OR)DYea
SalinasDYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. Oregon's members: 0 yea, 2 nay. How each member voted

MemberPartyPosition
Merkley (D-OR)DNay
Wyden (D-OR)DNay

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What happened

The full Oregon timeline, year by year

What was said

My concern has been with utility costs and water. Clackamas County has a reasonable footprint in farming and nurseries which are dependent on water. There are some responsible concerns to make sure we have the appropriate guardrails in place that make sure our industries that are here today are
Paul Savas, Commissioner, Clackamas County Board of Commissioners · October 23, 2026 · quoted · Oregon City News (opens in a new tab) news outlet
Nelson Abramson spent 20 years at Google including on its data center team, then ran infrastructure at X
Nelson Abramson, Verrus (implied leadership) · August 19, 2026 · paraphrased · Salem Reporter (opens in a new tab) local outlet

Every Oregon statement, by speaker (94)

92 more on this page, one per speaker and claim; 94 statements in all
"We have to be vigilant as we prepare for the future. We are definitely flying into the great unknown, we don't know where these centers could be located or how. The technology is advancing so quickly that we are not keeping up with any kind of policy sidebars"
Martha Schrader, Commissioner, Clackamas County Board of Commissioners Clackamas County Board of Commissioners meeting Oregon City News (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Clackamas County Board of Commissioners meeting.

Primary source: Oregon City News (opens in a new tab).

"The thing that you just can't do, though, is move the goalposts mid game. If we're going to go through this land use process and in the end, this is all a land use process. You can't change the rules in the middle of it"
David Stockdale, City Manager, City of Umatilla Nonstop Local News interview Nonstop Local News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Nonstop Local News interview.

Primary source: Nonstop Local News (opens in a new tab).

"This is about far more than data centers. It is about the families whose livelihoods depend on these jobs, the local businesses that rely on a strong and stable economy, and the residents who trust us to make responsible, long-term decisions for our community's future."
David Stockdale, City Manager, City of Umatilla Nonstop Local News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Primary source: Nonstop Local News (opens in a new tab).

"How do you apply the same permitting rules with the basis of environmental studies, and understanding and the data that should back whether a permit is approved"
Joanna Lyons-Antley, City Attorney, Umatilla City Umatilla City Council meeting Elkhorn Media Group (opens in a new tab) news outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Umatilla City Council meeting.

Primary source: Elkhorn Media Group (opens in a new tab).

Filip calls for a ban on AI data centers, arguing that their consumption of energy and water and their environmental impacts warrant stronger restrictions.

Pacific Green, Progressive candidate for U.S. House (District 4), Oregon kboo.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: kboo.com (opens in a new tab).

Scott Hege believes decisions about data center development, including tax breaks and community investments, should be made locally rather than at the state level.

Wasco County Commissioner OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Hank Sanders called for a statewide moratorium of unspecified time on data centers.

candidate for Oregon House 52nd District OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Val Hoyle, Democratic incumbent U.S. Rep. from Oregon's 4th Congressional District, co sponsored or voted for several bills to regulate AI and address data center impacts, including the Ratepayer Protection Act and Bernie Sanders' Ban Artificial Super Intelligence Act

U.S. Representative OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Also reported by: NPR for Oregonians (opens in a new tab) local outlet .

Republican candidate Monique DeSpain said she promised not to accept money from the AI industry and stated communities must have the power to reject a data center if they determine it isn't right for them

Republican candidate, Oregon 4th Congressional District NPR for Oregonians (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NPR for Oregonians (opens in a new tab).

Committee consensus found need for more responsible oversight of data center industry and centralized information repository about Oregon data centers' type, water and energy use, and tax breaks.

Oregon Data Center Advisory Committee polkio.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: polkio.com (opens in a new tab).

Justin Filip, the Pacific Green candidate, said neither major party candidates' views go far enough to protect their constituents from the impacts of AI and data centers.

Pacific Green, Progressive candidate for U.S. House (District 4), Oregon klcc.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: klcc.org (opens in a new tab).

Monique DeSpain, Republican challenger in Oregon's 4th Congressional District, argues communities must have power to reject data centers and calls for radical transparency in data center decisions

retired Air Force colonel and JAG officer OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Amazon data centers in Eastern Oregon use outside air for cooling for 93% of the year, using water cooling for only 7% of the year

About Amazon (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: About Amazon (opens in a new tab).

Oregon Data Center Advisory Committee held seven fact finding meetings over nine months and released preliminary learnings and questions report.

polkio.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: polkio.com (opens in a new tab).

Town hall focused on hearing input on data center water usage, noise, job creation and electricity consumption

Salem city officials KPTV (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KPTV (opens in a new tab).

Hillsboro pushing back against expansion and Clackamas County commissioners starting conversations about data center development

unnamed Oregon city and county officials KMTR (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KMTR (opens in a new tab).

Woodburn City Manager says water impact from data centers could exceed city's water supply capacity

Scott Derickson OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Amazon data centers have drawn criticism for water and energy use and environmental impacts

local advocates opb.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: opb.org (opens in a new tab).

Environmental Protection Network identified more than 30 federal actions increasing pollution related health risks, including narrowing environmental reviews, ending citizen led pollution lawsuits, and changing public participation requirements

New Orleans CityBusiness (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: New Orleans CityBusiness (opens in a new tab).

Amazon representative said Amazon data center uses less water than local agriculture industry

Courtney Lee, senior manager for state and local policy, Amazon Web Services OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Amazon representative said company runs diesel generators about 12 hours per year for testing and maintenance

Courtney Lee, senior manager for state and local policy, Amazon Web Services OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Jim Doherty, former Morrow County Commissioner, said opposition to data centers is a unifying moment between rural and urban Oregon

OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

David Sykes, chair of the Morrow County Board of Commissioners, said decisions over data centers on private property are up to local government

Chair, Morrow County Board of Commissioners OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Data centre moratorium debate is playing out across Oregon and the nation as campaign issue

OPB OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Many data centers across Oregon rely on diesel generators to provide backup power which could release massive amounts of diesel pollution into nearby communities

OPB opb.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: opb.org (opens in a new tab).

The AI boom has rapidly increased the demand for data center infrastructure

OPB journalists opb.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: opb.org (opens in a new tab).

Michael Franz, co director of the Wesleyan Media Project, said data centers give both political parties talking points they want to use.

co-director, Wesleyan Media Project OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

The Democratic Party of Oregon responded saying Christine Drazan had opportunity after opportunity to stand up against data centers and every time chose not to

Nathan Soltz, Democratic Party of Oregon chair Willamette Week (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Willamette Week (opens in a new tab).

Olivia Davis, spokeswoman for the Democratic Governors Association, said data centers are creating deep concerns around affordability and utility costs.

spokeswoman, Democratic Governors Association OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

A Republican Party operative said the most popular Republican position is that data centers could be acceptable as long as they pay for their own energy.

Republican Party operative (unnamed) OPB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Chavez DeRemer says she will focus on investments in energy and data center infrastructure to support AI industry

former U.S. labor secretary OregonLive.com (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OregonLive.com (opens in a new tab).

Chris Carpenter, IBEW Local 48 political director, told Hillsboro City Council his members had serious concerns with the city's plans for a temporary data center moratorium.

Willamette Week (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Willamette Week (opens in a new tab).

Commissioner Diana Helm said a data center could come into the county and that officials are trying to put a pause on anything happening until they have done their research

Clackamas County Commissioner The Cool Down (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Cool Down (opens in a new tab).

Lori Chavez DeRemer accepted newly created role as senior adviser for labor and national infrastructure at Think Big to advocate for data center industry

former U.S. labor secretary OregonLive.com (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OregonLive.com (opens in a new tab).

Oregon Governor Tina Kotek is backing efforts by local governments to halt data center development, saying more needs to be done to prevent Oregonians from footing the bill.

RTO Insider (opens in a new tab) trade press
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: RTO Insider (opens in a new tab).

Meta plans to rehire the majority of staff through a different firm as part of vendor partnership change

Meta spokesperson OPB (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: OPB (opens in a new tab).

Data centers pay same water rates and system development charges as any other industrial developer

Casey Kaiser, assistant city manager KTVZ (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KTVZ (opens in a new tab).

On the November 3, 2026 ballot in Oregon: Governor (3), U.S. Senate (4), U.S. House, District 1 (2), U.S. House, District 2 (2), U.S. House, District 3 (2), U.S. House, District 4 (3), U.S. House, District 5 (3), U.S. House, District 6 (2); 6 of 21 candidates with a statement on data centers on the record. Every candidate.

Already running in Oregon

10 sites are serving load, 4 of them in Washington County.

See the 10 running sites
  1. Aligned PDX-01 Hillsboro, Washington County Running · Operational since 2024 (2 years)
  2. Amazon data centers in Lower Umatilla Basin Hermiston, Umatilla County Running · Operational since 2011 (15 years)
  3. Amazon Eastern Oregon Data Centers Boardman, Morrow County Running · Operational since 2011 (15 years)
  4. Apple Prineville Campus Prineville, Crook County Running 120 MW · Operational since 2012 (14 years)
  5. Digital Realty Hillsboro Hillsboro, Washington County Running · Operational since 2018 (8 years)
  6. Google The Dalles data center The Dalles, Wasco County Running · Operational since 2006 (20 years)
  7. H5 Portland Portland, Multnomah County Running
  8. Meta Prineville Campus Prineville, Crook County Running 350 MW · Operational since 2011 (15 years)
  9. QTS Data Centers Hillsboro Hillsboro, Washington County Running · Operational since 2020 (6 years)
  10. STACK Infrastructure Hillsboro Hillsboro, Washington County Running

Questions about Oregon data centers

How many data center projects are on the record in Oregon?

13 projects are on the record in Oregon: 1 reported, 1 waiting on permits, 10 running, 1 cancelled and 5 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

Where in Oregon are they?

Records are in 8 counties: Washington County (5), Crook County (2), Deschutes County (1), Marion County (1), Morrow County (1), Multnomah County (1), Umatilla County (1) and Wasco County (1). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in Oregon?

526 MW is disclosed across 4 of 13 records: Meta Prineville Campus (350 MW, third party estimate, source (opens in a new tab)), Apple Prineville Campus (120 MW, third party estimate, source (opens in a new tab)) and Hillsboro data center projects (7 in permitting) (36 MW, the developer's figure, source (opens in a new tab)) and 1 more under Disclosed figures. The other 9 records have not disclosed capacity. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in Oregon say they will use?

Not disclosed. None of the 13 records on file for Oregon states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in Oregon?

13 developers are named on the record: Amazon (2 records), Aligned Data Centers, Apple, Boxminer.io, Digital Realty, Google, H5 Data Centers, Meta, NTT DATA, QTS Data Centers, Sabey Data Centers, STACK Infrastructure and Verrus. Each name opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in Oregon have rules about data centers?

10 county and city rows are on the record, 3 of them rated: Hillsboro is rated restrictive: Hillsboro, Oregon also approved its own pause at a last minute July 27 meeting, source (opens in a new tab), Salem is rated restrictive: Salem and Woodburn have adopted moratoriums on data centers, August 24, 2026, source (opens in a new tab) and Woodburn is rated restrictive: Woodburn City Council unanimously approved 120 day moratorium on data center development on September 15, 2026, source (opens in a new tab). The state's own row is rated restrictive, with 34 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in Oregon, by county?

2 records are not yet running. Marion County: Oakline at Mill Creek (waiting on permits); and Washington County: Hillsboro data center projects (7 in permitting) (reported). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of Oregon itself decided?

2 state laws are on the record: HB 4084 (signed, April 6, 2026, source (opens in a new tab)) and SB 611 (signed, April 7, 2015, source (opens in a new tab)). The state's own scorecard row carries 34 dated acts, the newest October 14, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

526 MW power

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power526 MW492 third party estimate, 2 the developer's figure
Water, stated per day013
Water, stated per year013
Permanent jobs013
Tax each year013

A blank cell means no record in Oregon disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power526 MW492 third party estimate, 2 the developer's figure
Water, stated per day013
Water, stated per year013
Permanent jobs013
Tax each year013

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 13 tracked facilities in Oregon are for. 5 sites not yet verified are named apart and are not in that number.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use13526 MW

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

No source on file states how any of the 13 tracked facilities in Oregon are cooled. 5 sites not yet verified are named apart and are not in that number.

Sources read for Oregon

16 sources

16 sources are read for Oregon:

Newspapers
Salem Reporter, Statesman Journal (via Google News), The Oregonian
Public broadcaster
OPB
Economic development
Business Oregon
Search feeds
11 news searches
Every feed, with its kind and tier

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Oregon", https://datacenterrecord.org/states/or, updated October 25, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in Oregon", https://datacenterrecord.org/states/or. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
OR
Rating of the state's own row
Restrictive
Count by status
reported 1, waiting on permits 1, running 10, cancelled 1, not yet verified 5
Located records
2 located, 11 at a centroid, 0 without coordinates

Researcher view · Oregon · 13 data center sites, 0 buildings where disclosed, 11 rule rows, 4 bills · basis and source tier on every row · verified October 25, 2026

Download CSV JSON GeoJSON