Data Center Record.
Census GEOID: 41067 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 5 primary sources

● Running First recorded September 14, 2026 · 3 Buildings

STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03)

Street address 6230 NE Century Blvd, Hillsboro, OR 97124, Washington County verified address Exact, at the address [3] STACK Infrastructure: STACK POR01

Overview, regulatory gates and specifications

STACK Infrastructure lists 3 data centers at Hillsboro, Oregon among the sites it operates. [1] Filings on the record specify disclosed capacity of 84 MW (the developer's figure), 3 planned or operational buildings. [3] STACK Infrastructure lists STACK POR01, STACK POR02, STACK POR03 at Hillsboro, Oregon on its own page of data center locations, read September 14, 2026. [3]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
62 generators permitted
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [3]
84 MW
the developer's figure

Equivalent to ~69,720 U.S. homes (U.S. EIA 830 homes/MW baseline) · 4.0% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [3]
3 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 6230 NE Century Blvd, Hillsboro, OR 97124.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
84 MW developer figure Equivalent to the continuous electricity demand of about 69,700 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 0.8 percent of New York City's summer peak demand in 2024.
[3] stackinfra.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
3 buildings operator page
[3] stackinfra.com
Backup generators
62 generators (180.7 MW) permitted
[4] deqonline.deq.state.or.us
Capital investment
Not disclosed
Commissioned
Operational since 2020 (6 years)
Who leads it
STACK Infrastructure as stated by the source
Permitted legal entity
SI POR03, LLC what a permit allows
[4] deqonline.deq.state.or.us [3] stackinfra.com
State air permit registration
34-0245, 34-0245-ST-01 state air permit register
[4] deqonline.deq.state.or.us
Official project website
stackinfra.com (opens in a new tab) verified October 28, 2026
stackinfra.com (opens in a new tab)
Archived promotional websites
stackinfra.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03), capacity: 84 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 84 ÷ 10,245 = 0.0082 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: STACK Infrastructure · Applicant / Shell LLC: SI POR03, LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 84 MW 84 MW the developer's figure [3] stackinfra.com
Site Footprint (Acres)
Data Hall Buildings 3 buildings 3 operator page [3] stackinfra.com
Cooling & Water System
Backup Diesel / Gas Generators 62 units (180.7 MW) what a permit allows [4] deqonline.deq.state.or.us
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

2025 to 2026 hearings
July 27, 2026 Hillsboro, OR Hillsboro City Council Special Meeting on Data Center Moratorium Hillsboro City Council 3 clips

Hillsboro City Council convened a special meeting to consider a temporary municipal land use moratorium on new data center and battery energy storage permits while staff updates the Hillsboro Community Development Code.

  1. Hillsboro City Planning Staff Board & Planning Staff transcribed from the official recording
    "in order to then have that hearing. So the state needs 45 days notice. Today is day 46. We did this on purpose because when the governor instituted an a moratorium on enterprise zones, she left time between the time she said we were going to have a moratorum and by the and then when the moratorum was enacted and"
  2. Hillsboro City Planning Staff Board & Planning Staff transcribed from the official recording
    "facilities while drafting potential updates to Hillsboro Community Development Code and to define where to define where and how these facilities operate. The moratorium we will consider today is different, very different and separate from the state's temporary moratorium on enterprise zone agreements. And that's what I was alluding to earlier when I was speaking. That legislation on enterprise zones"
  3. Hillsboro City Council Member Elected Official transcribed from the official recording
    "so welcome to the city council special meeting. and I wanted to explain why we're here today. And I want to explain why we're here today and why it was a special meeting on a Monday at 9:00 a.m. So we were briefed in executive session on legal implications on doing a moratorum. And in that session we learned one of"
2019 to 2024 hearings
March 7, 2023 Hillsboro, OR March 7. 2023: Hillsboro City Council Meeting Hillsboro City Council 1 clip

Hillsboro City Council meeting and Enterprise Zone record on property tax abatements and semiconductor and hyperscale data center industrial zoning (March 7, 2023).

  1. Hillsboro Economic Development and Planning Staff Municipal / Agency Staff transcribed from the official recording
    "In the North Hillsboro Industrial Renewal Area and Enterprise Zone, data center investments have driven significant assessed value growth, while requiring coordinated planning with Portland General Electric and Joint Water Commission supply."
Said and filed

Said and filed

Statements and filings, side by side

Column A · Dated Statement
Hillsboro Economic Development and Enterprise Zone Sponsors Hillsboro Enterprise Zone Program Officials
Venue: Hillsboro City Council Enterprise Zone Abatement Proceedings
"Hillsboro Enterprise Zone three to five year property tax abatements attract premier hyperscale data center investment into the Silicon Forest industrial corridor while strengthening our local tax base and utility infrastructure."
City of Hillsboro Oregon
Column B · Subsequent Recorded Position
Hillsboro City Council Ordinance No. 6525 (9 to 0 Vote Enacting 180 Day Emergency Data Center Moratorium)
Hillsboro City Council Ordinance No. 6525 · March 3, 2026 Unanimous Vote
Agency or Venue: Hillsboro City Council
"On March 3, 2026, the Hillsboro City Council voted 9 to 0 to enact a 180 day emergency moratorium on new data centers after city planners documented that hyperscale facilities consumed rampant electricity and industrial land needed for high employment semiconductor manufacturing while generating minimal permanent jobs."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    STACK Infrastructure lists STACK POR01, STACK POR02, STACK POR03 at Hillsboro, Oregon on its own page of data center locations, read September 14, 2026.

    [3] stackinfra.com

1 correction to this record

Every correction, with its reason

Every correction on the record is on the corrections page.

Nearest data centers in Oregon

Verified data center records in Oregon within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Infomart Portland (Cascadia Hillsboro Campus) Hillsboro, Washington County Less than 1 mi Running STACK Infrastructure 24 MW
Digital Realty Hillsboro Campus (PDX10 / PDX11 / PDX12) Hillsboro, Washington County Less than 1 mi Running Digital Realty 54 MW
Flexential Hillsboro 1 (PDX01 Brookwood) Hillsboro, Washington County Less than 1 mi Running Flexential 3.6 MW
NTT Global Data Centers Hillsboro Campus (HI1 / HI2 / HI3) Hillsboro, Washington County Less than 1 mi Running NTT Global Data Centers 126 MW
EdgeConneX Portland (POR01 / POR02 Hillsboro) Hillsboro, Washington County Less than 1 mi Running EdgeConneX 30 MW
Aligned PDX-01 Hillsboro, Washington County Less than 1 mi Running Aligned Data Centers 72 MW

Blank cell: not disclosed by any source on file.

Common questions about STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03)

Answered directly from the verified filings and local actions on this page.

Who is building STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03)?

STACK Infrastructure is the developer. No construction contractor is named on the record yet.

How much power and water does STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03) say it needs?

Power: 84 MW (the developer's figure, stackinfra.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. US EPA ECHO Detailed Facility Report: Hillsboro Data Center LLC / STACK Infrastructure (FRS 110070108174) (opens in a new tab), US Environmental Protection Agency
  2. STACK Infrastructure: Americas locations (opens in a new tab), STACK Infrastructure, September 14, 2026
  3. STACK Infrastructure: STACK POR01 (opens in a new tab), STACK Infrastructure, September 14, 2026
  4. Oregon DEQ Standard ACDP (OAR 340-216) 34-0245-ST-01 (SI POR03, LLC - STACK Infrastructure, SI POR03) (opens in a new tab), Oregon Department of Environmental Quality, June 30, 2023
  5. Oregon DEQ Permit Review Report 34-0245-ST-01 (SI POR03, LLC - STACK Infrastructure, SI POR03) (opens in a new tab), Oregon Department of Environmental Quality, June 30, 2023

5 sources on file.

Regional grid context

This site is in the Northwest Power Pool (NWPP) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03)", https://datacenterrecord.org/projects/stack-infrastructure-hillsboro-or, last verified October 26, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03)", https://datacenterrecord.org/projects/stack-infrastructure-hillsboro-or. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
45.547403, -122.897906
How the location is known
Location from the site's street address.
Location source
https://www.stackinfra.com/locations/americas/portland/
Coordinate source
STACK Infrastructure Portland Hillsboro campus specification
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
84 MW, the developer's figure
Published
September 14, 2026
Last verified
October 26, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · STACK Infrastructure Hillsboro Campus (POR01 / POR02 / POR03) · 5 sources, 1 entry · basis and source tier on every row · verified October 26, 2026

Download CSV JSON