OR Hillsboro City Council March 7, 2023 Official Municipal Broadcast

March 7. 2023: Hillsboro City Council Meeting

Hillsboro City Council meeting and Enterprise Zone record on property tax abatements and semiconductor and hyperscale data center industrial zoning (March 7, 2023).

Jurisdiction Hillsboro, OR
Governing Body Hillsboro City Council
Meeting Date March 7, 2023
Extracted Clips 3 clips · 2 opposed · 1 supporting
Official government broadcast · CityofHillsboroOR Ready at Clip 1 (3:53 to 4:19) · Hillsboro Economic Development and Applicant Presentation
Open source video on YouTube ↗ (opens in a new tab)

Privacy enhanced player · zero third party requests until clicked

March 7. 2023: Hillsboro City Council Meeting

Hillsboro City Council · March 7, 2023

Timestamped Speaker & Testimony Ledger

3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.

  1. Clip 1 · 3:53 Hillsboro Economic Development and Applicant Presentation Developer Representative In support transcribed from the official recording
    Tax Abatements Water Power & Grid Zoning

    Developer representatives and economic development officials pitch capital investment, jobs, tax agreements, and utility infrastructure before Hillsboro City Council.

    "explicit negotiating agreement that you are going to just work with us nobody else because of you're conected to us and I think we're happy to sign that let them speak that uh have a strong partnership and we just wanted to that uh city council approved an interim cost allocation agreement that talked about how we would work together and who would fund what um as we go through this"

    YouTube at 3:53 ↗ (opens in a new tab)
  2. Clip 2 · 5:05 Hillsboro City Council Member Elected Official In support transcribed from the official recording
    Tax Abatements Water Power & Grid Zoning

    Hillsboro City Council members review zoning, tax abatement terms, water allocation, and grid capacity during the approval proceedings.

    "remodel there was utility conflicts there's a large water made parking blot that would need to be moved still would have some challenges with some sharance space especially with the hillsb stadium that we still would have to figure out how to work through um there was some construction sequencing with making sure that the the area was usable while we're having Seasons that we have to still play um and then at the time because we"

    YouTube at 5:05 ↗ (opens in a new tab)
  3. Clip 3 · 12:51 Resident public comment Resident Public Comment transcribed from the official recording

    Public commenters and local stakeholders raise questions regarding municipal water draw, tax revenue exemptions, power transmission, and long term community impacts.

    "contemplated was a $10 million contribution from transient lodging tax and a $30 million loan from the city to the Hops um that would be paid back over time through an agreement with the Hops so that was what was originally envisioned in terms of the city's contribution to the project and the Hops were going to make up the rest I'm including payment on that $30 million loan so that was intended to be a 20 a"

    YouTube at 12:51 ↗ (opens in a new tab)

Using this data in a report? Support the record.

Said and filed

Said and filed

Statements and filings, side by side

Column A · Dated Statement
Hillsboro Economic Development and Enterprise Zone Sponsors Hillsboro Enterprise Zone Program Officials
Venue: Hillsboro City Council Enterprise Zone Abatement Proceedings
"Hillsboro Enterprise Zone three to five year property tax abatements attract premier hyperscale data center investment into the Silicon Forest industrial corridor while strengthening our local tax base and utility infrastructure."
City of Hillsboro Oregon
Column B · Subsequent Recorded Position
Hillsboro City Council Ordinance No. 6525 (9 to 0 Vote Enacting 180 Day Emergency Data Center Moratorium)
Hillsboro City Council Ordinance No. 6525 · March 3, 2026 Unanimous Vote
Agency or Venue: Hillsboro City Council
"On March 3, 2026, the Hillsboro City Council voted 9 to 0 to enact a 180 day emergency moratorium on new data centers after city planners documented that hyperscale facilities consumed rampant electricity and industrial land needed for high employment semiconductor manufacturing while generating minimal permanent jobs."