Crook County has 2 data centers on the record: 2 running. No county rule about data centers is on the record for Crook County itself; 1 body inside it has a scorecard row. The latest decision on the record: Prineville officials were in discussion with two additional companies about building data centers in the town where Facebook opened its first company built data center (Prineville), reported May 31, 2024.
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Meta Prineville Data Center Campus Prineville, Crook County | Running | Meta | Vitesse, LLC was a party to the Pacific Power data center tariff case (Docket UE 463) and did not oppose the settlement the Oregon PUC adopted on November 13, 2026. apps.puc.state.or.us (opens in a new tab) primary source November 13, 2026 | site | 1 | 2026-11-13 | ||
| Apple Prineville Data Center Campus Prineville, Crook County | Running | Apple | Facebook data center first phase was 150,000 square feet and opened in April datacenterknowledge.com (opens in a new tab) trade press reported May 31, 2024 | EPA registry | 1 | 2026-10-26 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
| City | Census GEOID | Projects | Rules |
|---|---|---|---|
| Prineville | 4159850 | 1 |
A city without a record is listed, not linked.
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| Prineville | city | not rated | Prineville officials were in discussion with two additional companies about building data centers in the town where Facebook opened its first company built data center. datacenterknowledge.com (opens in a new tab) trade press Reported May 31, 20241 act on this rowEvery act on the Prineville row
| 1 | 2024-05-31 |
Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
The rules across Oregon · Report missing data or a local act
Scorecard eventPrineville
Went liveApple Prineville Data Center Campus
Went liveMeta Prineville Data Center Campus
Altman previously publicly pointed out that the space data center initiative is not realistic.
Layoffs due to end of contract with client at Prineville location
Meta plans to rehire the majority of staff through a different firm as part of vendor partnership change
Prineville is home to both Facebook and Apple data centers with 15 year tax exemptions beginning to expire
View all 10 Oregon statements on the record →
Sam Altman said Musk is selling 'short term' space data centers to investors.
Provenance: Paraphrased; said in the source itself.
Primary source: 매일경제 (opens in a new tab).
Meta and Apple funded nearly the entire aquifer system
Provenance: Paraphrased; said in the source itself.
Primary source: KTVZ (opens in a new tab).
Data centers pay same water rates and system development charges as any other industrial developer
Provenance: Paraphrased; said in the source itself.
Primary source: KTVZ (opens in a new tab).
Regulations will likely aim to protect energy infrastructure and water supplies from being overburdened
Provenance: Paraphrased; said in the source itself.
Primary source: bendbulletin.com (opens in a new tab).
Greg LeRoy, executive director of Good Jobs First, stated that since Oregon has no sales tax, it is property taxes that are the big dollars attracting data centers
Provenance: Paraphrased; said in the source itself.
Primary source: bendbulletin.com (opens in a new tab).
Apple has committed to supporting 100 percent of its energy use in Prineville with renewable resources
Provenance: Paraphrased; said in the source itself.
Primary source: Data Center Knowledge (opens in a new tab).
Distances run between the centers the Census Bureau gives each place. Every Oregon county.
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 0 | 2 | ||
| Water, stated per day | 0 | 2 | ||
| Water, stated per year | 0 | 2 | ||
| Permanent jobs | 0 | 2 | ||
| Tax each year | 0 | 2 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 2 |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
No source on file states what any of the 2 tracked facilities in Crook County are for.
No source on file states how any of the 2 tracked facilities in Crook County are cooled.
Report a correction · Send a tip about Crook County · The rows here are part of the Oregon export.
Data Center Record, "Data center records in Crook County, Oregon", https://datacenterrecord.org/states/or/crook-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.