Google revealed it is the developer behind Project Clydesdale, a 506 acre data center campus being built in Tulsa County, Oklahoma, with plans to fund removal of 2,000 acres of trees for water conservation and partnering with Beale Infrastructure. [4] Filings on the record specify 2 planned or operational buildings. [1] Google is the end user of Project Clydesdale, a 506 acre data center campus in unincorporated Tulsa County. [4]
U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.
Utility interconnection queue filings monitored.
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: 11600 E 116th St N, Project Clydesdale Site, Owasso, OK 74055.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Project Clydesdale (Google Tulsa County).
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 2 buildings | Site filing [1] datacenters.google | |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
On February 11, 2026, the Tulsa City Council voted unanimously to direct the Tulsa Metropolitan Area Planning Commission to overhaul the city's zoning code for data centers to address water consumption, noise, and neighborhood buffers.
"area, the city wants to ensure the industrial noise doesn't impact the quality of life for Tulsans. Fox 23's Page Or joins us live in studio. Page, the council isn't changing the zoning code, not yet anyway, but they are going to do a deep dive to see if they need to. That's right, Nathan. Last night's vote was an 8-0 approval to initiate a formal research phase into how these sites are categorized. Councilor Laura Bellis says"
"noise ordinances. An admission she says that these sites can be a real disturbance. What actually really brought this up to me was when I learned that they'd asked us to change our noise ordinance, which to me is a big flag of hey, this is something that can affect people who live nearby. When Tulsa first defined data centers 2 years ago, they were classified as low impact, meaning they wouldn't create"
"nuance into our zoning code, then we're going to be dealing with some real downstream effects that affect people's quality of life. While this vote only starts the clock on research, Bellis says it is a necessary step to ensure Tulsa isn't outrun by technology. At the council table, there was a general agreement that everyone knows much more today than they did 2 years ago. The first big data center that we had a couple years ago, we really didn't know enough. We"
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
The project will include approximately 1.5 miles of new water lines and infrastructure upgrades.
· Status: being built (source date; the content gives no date of its own)
Beale Infrastructure officially broke ground on Project Clydesdale in October 2025.
(source date; the content gives no date of its own)
Google is the end user of Project Clydesdale, a 506 acre data center campus in unincorporated Tulsa County.
(source date; the content gives no date of its own)
Located just west of Owasso
(source date; the content gives no date of its own)
Support for training more than 160 apprentices in electrical trades by 2030
(source date; the content gives no date of its own)
1.5 miles of new water lines and infrastructure upgrades for Washington County Rural Water District #3
(source date; the content gives no date of its own)
Construction of a new on site substation funded by Beale
(source date; the content gives no date of its own)
506 acre campus in unincorporated Tulsa County near Cherokee Industrial Park
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: ktul.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: ktul.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: ktul.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: ktul.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: ktul.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.
Every correction on the record is on the corrections page.
Verified data center records in Oklahoma within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Claremore Data Center Claremore, Rogers County | ~13 mi | Proposed | ||
| Meta AI-Optimized Data Center Tulsa Tulsa, Tulsa County | ~13 mi | Proposed | Meta | |
| TierPoint Tulsa Tulsa, Tulsa County | 13 mi | Running | TierPoint | 1 building |
| TierPoint Tulsa East (12151 East State Farm Boulevard) Tulsa, Tulsa County | 15 mi | Running | TierPoint | 1 building |
| Google Data Center Pryor Pryor, Mayes County | 29 mi | Proposed | ||
| Lambda Chouteau data center Chouteau, Mayes County | ~29 mi | Proposed | Lambda |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Google is the developer, datacenters.google (opens in a new tab). No construction contractor is named on the record yet.
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is being built, as reported August 19, 2026. The newest entry, reported August 19, 2026: The project will include approximately 1.5 miles of new water lines and infrastructure upgrades. [4]
Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
Official operator or facility campus page verified in 50 state website discovery pass.
8 sources on file.
This site is in the SPP South (SPSO) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Project Clydesdale (Google Tulsa County). Last verified November 6, 2026. https://datacenterrecord.org/projects/project-clydesdale-google-tulsa-county-ok. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Project Clydesdale (Google Tulsa County)
Data Center Record, "Project Clydesdale (Google Tulsa County)", https://datacenterrecord.org/projects/project-clydesdale-google-tulsa-county-ok. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.