Data Center Record.
Census GEOID: 40131 Location Precision: county centroid Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 4 reporting sources

● Proposed Campus Reported September 12, 2026

Claremore Data Center

Location Claremore, Rogers County, Oklahoma county centroid County level, the county seat

Overview, regulatory gates and specifications

A data center project in Claremore, Oklahoma advanced with major community commitments while also prompting community concerns addressed by the city. [1] Sequoyah Public Schools expected to receive $100 million in PILOT payments from Claremore data center project [3]

Verified Site & Permit Summary
Verified address
Claremore, Rogers County, Oklahoma county centroid
Operator / developer
Not disclosed in filing
Permit / registry ID
2 News Oklahoma KJRH Tulsa on file [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Not disclosed
Who leads it, Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

John Feary

City Manager · City of Claremore

DID Recorded statement at City of Claremore statement (August 28, 2026)
SAID We recognize the level of public interest surrounding this project and the importance of clearly communicating what has been finalized and what comes next. The agreements now in place establish substantial financial commitments, including payments to local public entities, infrastructure funding, community investment and financial protections for the City. (August 28, 2026) okcfox.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Not disclosed
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Claremore Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind it A land record, a zoning application or a company's own announcement.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Beale Infrastructure partnering with Sequoyah Public Schools on fitness focused playground project to be completed by end of year

    [3] kjrh.com

  2. (source date; the content gives no date of its own)

    Beale Infrastructure is the developer of the Claremore data center

    [3] kjrh.com

  3. · Status: rumored (source date; the content gives no date of its own)

    Sequoyah Public Schools expected to receive $100 million in PILOT payments from Claremore data center project

    [3] kjrh.com

Every event in order

9 corrections to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Oklahoma

Verified data center records in Oklahoma within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Project Clydesdale (Google Tulsa County) Owasso, Tulsa County ~13 mi Being built Google 2 buildings
Google Data Center Pryor Pryor, Mayes County ~16 mi Proposed Google
Lambda Chouteau data center Chouteau, Mayes County ~18 mi Proposed Lambda
TierPoint Tulsa East (12151 East State Farm Boulevard) Tulsa, Tulsa County ~20 mi Running TierPoint 1 building
Meta AI-Optimized Data Center Tulsa Tulsa, Tulsa County ~22 mi Proposed Meta
TierPoint Tulsa Tulsa, Tulsa County ~24 mi Running TierPoint 1 building

Blank cell: not disclosed by any source on file.

Comparisons

1 metric with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Tax each year

1 figure, 1 source
400,000,000 USD Reported

News On 6, Sep 8, 2026

Show each source's words
  • 400,000,000 USD, News On 6: Beale Infrastructure projected $400 million in electric revenue and sales tax over 30 years

Common questions about Claremore Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Claremore Data Center?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

Who will use Claremore Data Center?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Claremore Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Claremore Data Center stand today?
What is still unknown about Claremore Data Center?

Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is building it, who is constructing it, how much land, buildings, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Claremore addresses community concerns over data center project - 2 News Oklahoma KJRH Tulsa (opens in a new tab), 2 News Oklahoma KJRH Tulsa, September 3, 2026, local outlet
  2. Claremore data center project advances with major community commitments - News On 6 (opens in a new tab), News On 6, August 28, 2026, local outlet
  3. Sequoyah Public Schools set to receive largest share of Claremore data center PILOT payments - KJRH (opens in a new tab), KJRH, September 12, 2026, local outlet
  4. What to Know About Project Mustang in Claremore - News On 6 (opens in a new tab), News On 6, September 8, 2026, local outlet

4 sources on file.

Regional grid context

This site is in the SPP South (SPSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Claremore Data Center", https://datacenterrecord.org/projects/claremore-data-center-ok, last verified September 17, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Claremore Data Center", https://datacenterrecord.org/projects/claremore-data-center-ok. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
36.31528, -95.61278
How the location is known
Location is the county seat; exact site not disclosed.
Location source
County seat (Claremore), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Published
September 5, 2026
Last verified
September 17, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Claremore Data Center · 4 sources, 3 entries · basis and source tier on every row · verified September 17, 2026

Download CSV JSON