Census GEOID: 13073 Location Precision: assessor parcel Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 3 primary and 7 reporting sources

● Being Built Reported August 31, 2026 · 12 Buildings

Google Columbia County Data Center (White Oak Technology Park)

Street address 1955 Appling Harlem Rd, Appling, GA 30802, Columbia County assessor parcel Exact, on the parcel [3] apps.dca.ga.gov

Overview, regulatory gates and specifications

Google lists a data center at Columbia County, Georgia and says it is being built. [6] Filings on the record specify 12 planned or operational buildings. [3] Georgia Power wants to upgrade two reactors at Plant Vogtle near Augusta and two at Plant Hatch west of Savannah to put roughly 100 megawatts total of emission free electricity on the power grid. [7]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
$118,050,880/yr stated
4. Utility Grid Queue
96 MW from nuclear uprates
5. Air & Water Permits
Georgia DCA DRI #4443 (White
What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Electric utility territory: 96 MW from nuclear uprates.

Cooling & Water [3]
6,598,000 gal/day
the developer's figure

Equivalent to ~21,993 U.S. households (U.S. EPA 300 gal/day household baseline).

Stated annual local tax revenue: $118,050,880.

Site & Buildings [3]
12 buildings
permit

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 1955 Appling Harlem Rd, Appling, GA 30802.

Taxes & Permanent Jobs [3]
$118,050,880/yr
the developer's figure

Permanent operational headcount not yet disclosed on the record.

Stated annual local tax revenue: $118,050,880.

Key specifications on the record

Power capacity
Not disclosed
Water usage
6,598,000 gallons a day (withdrawal) developer figure Equivalent to the daily water use of about 22,000 average U.S. households based on the U.S. Environmental Protection Agency baseline of 300 gallons per day per home. What at most 22,000 American families use at home, at the EPA's more than 300 gallons a family a day (the EPA gives no year for it).
[3] apps.dca.ga.gov
Land area
Not disclosed
Buildings
12 buildings permitted
[3] apps.dca.ga.gov
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Google as stated by the source
[10] wfxg.com
Tax each year
$118,050,880 the developer's figure
[3] apps.dca.ga.gov
Where its power comes from
96 MW from nuclear uprates as stated by the source
[6] augustachronicle.com
State air permit registration
Georgia DCA DRI #4443 state air permit register
State permit status
Georgia DCA DRI #4443 (White Oak Technology Park) review completed the state's permit register, as of April 8, 2025, last verified November 11, 2026
[2] apps.dca.ga.gov
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs
The math behind the comparison
  1. Google Columbia County Data Center (White Oak Technology Park), water: 6,598,000 gallons a day.
  2. Water used at home each day by the average American family, more than: 300 gallons a day.
  3. 6,598,000 ÷ 300 = 21,993.33 (gallons a day over gallons a day).

Sources:

The two count different water: the data center figure is water withdrawn from its source, and the EPA's is water used at home, which the EPA does not split into water consumed and water returned.

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Dr. Christopher Kadlec

Georgia Southern University applied cyber education director

DID Recorded statement at WRDW (September 23, 2026)
SAID Dr. Christopher Kadlec warned that emergency backup power systems present environmental considerations, particularly diesel powered generators during severe weather in south Georgia. (September 23, 2026) wrdw.com (opens in a new tab)

Georgia Power

Public Record Speaker

DID Recorded statement at ajc.com (September 22, 2026) [7]
SAID Google agreed to pay a premium for new electricity from planned upgrades as part of a new program Georgia Power submitted to state regulators on Monday. (September 22, 2026) [7]

Jen Ryan

Google representative

DID Recorded statement at AOL.com (September 10, 2026)
SAID Jen Ryan stated that Google worked with Columbia County leadership to exceed decibel standards and buffers for the data center. (September 10, 2026) aol.com (opens in a new tab)

Doug Duncan

Columbia County Commissioner

DID Recorded statement at AOL.com (September 10, 2026)
SAID Columbia County Commissioner Doug Duncan stated that Google was an opponent during negotiations but understood the county's vision. (September 10, 2026) aol.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet
UTILITIES
Electric utility: 96 MW from nuclear uprates

View all 12 statements on the record in Georgia →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Columbia County Data Center (White Oak Technology Park).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 12 buildings permit [3] apps.dca.ga.gov
Cooling & Water System 6,598,000 gal/day the developer's figure [3] apps.dca.ga.gov
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue $118,050,880/yr the developer's figure [3] apps.dca.ga.gov

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.

Hearings and statements on the record

February 3, 2026 Appling, GA Columbia County Board of Commissioners Data Center Rezoning Vote Columbia County Board of Commissioners 3 clips

On February 3, 2026, the Columbia County Board of Commissioners approved rezoning for two major data center campuses, Pumpkin Technology Campus in Harlem and White Oak Technology Park in Appling, over resident objections regarding rural character and power transmission lines.

  1. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Harlem and white oak technology park in Appling. That's step one, a spokesperson for Columbia County tells me. Zoning approval is the first of several steps the developers must take before they break ground. The second step, the developers must submit site or building plans to the county for approval. The plans must show they can meet certain conditions, like reducing the noise limit. The developers will also need to submit an application for land disturbance if they plan on grading the"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "On grading the property. Finally, they must provide the county with a letter from georgia power showing the power company can sufficiently meet the power needs of the proposed data centers. Back in december, georgia's public service commission approved a historic request by georgia power to acquire ten gigawatts of new energy capacity to fuel the needs of data centers. To put that in perspective, that's enough energy to power"
  3. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Data centers. To put that in perspective, that's enough energy to power roughly 9 million homes. According to data center map. Georgia ranks fifth in the nation for data centers. Zooming to georgia in augusta is second only to atlanta, so state lawmakers proposed a bill just last month that would pause construction of new data centers throughout georgia until march of 2027. The pause would halt construction of data centers that do not"
January 28, 2026 Harlem, GA Columbia County residents discuss proposed data centers at town hall Columbia County Board of Commissioners 3 clips

WRDW News 12 report on Columbia County Board of Commissioners and community proceedings in Harlem, GA: Columbia County residents discuss proposed data centers at town hall (January 28, 2026).

  1. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "County data centers could be. Georgia's growth in the data center sector has outpaced the nation last year, according to commercial real estate firm CBRE. With the metro Atlanta leading the US in data center expansion last year, surpassing northern Virginia. The Bird Farm, Pumpkin Center, and White Oak data centers are the ones possibly coming to Columbia County as a planning commission recommended them for"
  2. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "gathered at Harlem Middle School ahead of the full commission meeting. Ethan Hunter is live at Harlem Middle School. Ethan, the county didn't get a chance to respond. However, you've done digging and you heard from neighbors tonight. What do they have to say? Yeah, this was not a Columbia County school event, but there were about 100 neighbors from around this area in Harlem Middle School right behind me."
  3. Resident public comment Resident Public Comment transcribed from local broadcast report
    "on the other side from where the Pumpkin Center data center could be coming. A lot of the people that I talked to tonight, some of those that would be most affected by these projects. These trees greet those coming into Harlem and Appling off I-20, but that could be changing. This land, one of three sites that could become data centers in Columbia County. We thought we built a family property to be passed on"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Georgia Power wants to upgrade two reactors at Plant Vogtle near Augusta and two at Plant Hatch west of Savannah to put roughly 100 megawatts total of emission free electricity on the power grid.

    [7] ajc.com

  2. (source date; the content gives no date of its own)

    Agreement mandates 65 decibel noise ceiling and 500 foot buffer zone from residential areas.

    [9] constructionreviewonline.com

  3. (source date; the content gives no date of its own)

    First payments expected late 2026 or early 2027 depending on construction milestones.

    [9] constructionreviewonline.com

  4. (source date; the content gives no date of its own)

    Two major sites: White Oak and Pumpkin Center area in Columbia County.

    [9] constructionreviewonline.com

  5. · Status: being built (source date; the content gives no date of its own)

    Economic Development Authority approved memorandum of understanding for Google Data Center in Columbia County, Georgia.

    [9] constructionreviewonline.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google Columbia County data center at Columbia County, Georgia on its own page of data center locations, read September 14, 2026.

    [1] datacenters.google

6 corrections to this record

Every correction, with its reason
  1. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 10, 2026; the record's rules, October 10, 2026).

  2. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 10, 2026; the record's rules, October 10, 2026).

Every correction on the record is on the corrections page.

Nearest data centers in Georgia

Verified data center records in Georgia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Project Squash Data Center Campus (Columbia County, DRI #4735) Columbia County 1 mi Proposed The Whiting-Turner Contracting Company 200 MW
Project JGK Data Center Campus (Columbia County, DRI #4736) Columbia County 3 mi Proposed Turner Construction Company 1.4 GW
Project Azelea Data Center Campus (McDuffie County, DRI #4602) McDuffie County 6 mi Proposed Project Azelea Applicant 400 MW
Project Eisenhower Data Center Campus (Augusta, DRI #4171) Augusta, Richmond County 12 mi Proposed Eagle South, LLC 6 buildings
Nixon Technology Center (Augusta, DRI #4853) Richmond County 21 mi Proposed 3 G Investments, LLC 600 MW
QTS Augusta Data Center Campus Augusta, Richmond County 22 mi Being built QTS Data Centers 8 buildings

Blank cell: not disclosed by any source on file.

Common questions about Google Columbia County Data Center (White Oak Technology Park)

Answered directly from the verified filings and local actions on this page.

Who is building Google Columbia County Data Center (White Oak Technology Park)?

Google is the developer, wfxg.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Google Columbia County Data Center (White Oak Technology Park) say it needs?

Power: not disclosed by any source on file. Water: 6,598,000 gallons a day (withdrawal) (the developer's figure, apps.dca.ga.gov (opens in a new tab)).

Where does Google Columbia County Data Center (White Oak Technology Park) stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Google: Data center locations (opens in a new tab), Google, September 14, 2026
  2. Georgia DCA DRI #4443 Application Summary (White Oak Technology Park, Columbia County) (opens in a new tab), Georgia Department of Community Affairs, April 8, 2025
  3. Georgia Department of Community Affairs: DRI Filing #4443 (White Oak Technology Park, Columbia County) (opens in a new tab), Georgia Department of Community Affairs

Reporting

  1. Columbia County pitches Google project as path to property tax relief - The Augusta Chronicle (opens in a new tab), The Augusta Chronicle, August 28, 2026, local outlet
  2. Columbia County Observer: Google finally joins the conversation - The Augusta Press (opens in a new tab), The Augusta Press, September 14, 2026, news outlet
  3. Georgia Power, Google to upgrade Plant Vogtle? What's happening - The Augusta Chronicle (opens in a new tab), The Augusta Chronicle, September 22, 2026, local outlet
  4. Georgia Power nuclear reactors to get huge face lift, paid partly by Google - ajc.com (opens in a new tab), ajc.com, September 22, 2026, local outlet
  5. Google data center could generate billions, add jobs, and new households - WRDW (opens in a new tab), WRDW, September 23, 2026, local outlet
  6. $17bn Google Data Center in Columbia County Advances as Firm Finalizes Agreement with Officials - Construction Review (opens in a new tab), Construction Review, August 31, 2026, news outlet
  7. What Google’s Data Center could mean for Columbia County’s Economy - WFXG FOX54 (opens in a new tab), WFXG FOX54, September 23, 2026, local outlet

10 sources on file.

Regional grid context

This site is in the SERC South (SRSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Columbia County Data Center (White Oak Technology Park)", https://datacenterrecord.org/projects/google-columbia-county-data-center-ga, last verified September 22, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Columbia County Data Center (White Oak Technology Park)", https://datacenterrecord.org/projects/google-columbia-county-data-center-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
33.5042, -82.3215
How the location is known
Location from the county parcel record.
Location source
https://apps.dca.ga.gov/DRI/AdditionalForm.aspx?driid=4443
Coordinate source
Georgia DCA DRI Filing #4443 (White Oak Technology Park, Columbia County) and Google Locations
Location last verified
September 16, 2026
How water was disclosed
the developer's figure
Published
September 14, 2026
Last verified
September 22, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google Columbia County Data Center (White Oak Technology Park) · 10 sources, 6 entries · basis and source tier on every row · verified September 22, 2026

Download CSV JSON