Data Center Record.
● 3 Facilities on Record 1 local rule row · 1.6 GW disclosed

Data centers in Columbia County, Georgia

Columbia County has 3 data centers on the record: 1 being built and 2 proposed. Columbia County has a scorecard row with no rating yet.

The 3 data centers in Columbia County

Every Columbia County record 3 records · blank cell: not disclosed · sort by any column

Facility and county Stage Operator Power (MW) Latest entry Basis Located Tier Verified
Google Columbia County Data Center (White Oak Technology Park) Appling, Columbia County Being built Georgia DCA DRI #4443 (White Oak Technology Park) review completed Google Georgia Power wants to upgrade two reactors at Plant Vogtle near Augusta and two at Plant Hatch west of Savannah to put roughly 100 megawatts total of emission free electricity on the power grid. ajc.com (opens in a new tab) local outlet reported September 22, 2026 site 1 2026-09-22
Project JGK Data Center Campus (Columbia County, DRI #4736) Columbia County Proposed Waiting on permits Georgia DCA DRI #4736 regional review filing Turner Construction Company 1,400 Turner Construction Company filed Georgia DCA DRI #4736 on May 5, 2026 for Project JGK, a 2,862 acre, 1,400 MW hyperscale data center development off Catalyst Drive and Morris Callaway Road in unincorporated Columbia County. apps.dca.ga.gov (opens in a new tab) primary source May 5, 2026 the developer's figure site 1 2026-05-05
Project Squash Data Center Campus (Columbia County, DRI #4735) Columbia County Proposed Waiting on permits Georgia DCA DRI #4735 regional review filing The Whiting-Turner Contracting Company 200 The Whiting-Turner Contracting Company filed Georgia DCA DRI #4735 on May 5, 2026 for Project Squash, a 200 MW data center campus on 325 acres at 6423 Wrightsboro Road near Harlem in unincorporated Columbia County. apps.dca.ga.gov (opens in a new tab) primary source May 5, 2026 the developer's figure site 1 2026-05-05

Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.

What Columbia County has decided 1 body, 0 decisions on the record

What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source. No dated decision is on the record yet.

BodyLevelRatingIn force untilLatest actActsVerified
Columbia Countycountynot ratedNo dated act on this row yet.2026-08-26

A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.

February 3, 2026 Appling, GA Columbia County Board of Commissioners Data Center Rezoning Vote Columbia County Board of Commissioners 3 clips

On February 3, 2026, the Columbia County Board of Commissioners approved rezoning for two major data center campuses, Pumpkin Technology Campus in Harlem and White Oak Technology Park in Appling, over resident objections regarding rural character and power transmission lines.

  1. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Harlem and white oak technology park in Appling. That's step one, a spokesperson for Columbia County tells me. Zoning approval is the first of several steps the developers must take before they break ground. The second step, the developers must submit site or building plans to the county for approval. The plans must show they can meet certain conditions, like reducing the noise limit. The developers will also need to submit an application for land disturbance if they plan on grading the"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "On grading the property. Finally, they must provide the county with a letter from georgia power showing the power company can sufficiently meet the power needs of the proposed data centers. Back in december, georgia's public service commission approved a historic request by georgia power to acquire ten gigawatts of new energy capacity to fuel the needs of data centers. To put that in perspective, that's enough energy to power"
  3. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Data centers. To put that in perspective, that's enough energy to power roughly 9 million homes. According to data center map. Georgia ranks fifth in the nation for data centers. Zooming to georgia in augusta is second only to atlanta, so state lawmakers proposed a bill just last month that would pause construction of new data centers throughout georgia until march of 2027. The pause would halt construction of data centers that do not"
January 28, 2026 Harlem, GA Columbia County residents discuss proposed data centers at town hall Columbia County Board of Commissioners 3 clips

WRDW News 12 report on Columbia County Board of Commissioners and community proceedings in Harlem, GA: Columbia County residents discuss proposed data centers at town hall (January 28, 2026).

  1. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "County data centers could be. Georgia's growth in the data center sector has outpaced the nation last year, according to commercial real estate firm CBRE. With the metro Atlanta leading the US in data center expansion last year, surpassing northern Virginia. The Bird Farm, Pumpkin Center, and White Oak data centers are the ones possibly coming to Columbia County as a planning commission recommended them for"
  2. WRDW News 12 Broadcast Report Broadcast Report transcribed from local broadcast report
    "gathered at Harlem Middle School ahead of the full commission meeting. Ethan Hunter is live at Harlem Middle School. Ethan, the county didn't get a chance to respond. However, you've done digging and you heard from neighbors tonight. What do they have to say? Yeah, this was not a Columbia County school event, but there were about 100 neighbors from around this area in Harlem Middle School right behind me."
  3. Resident public comment Resident Public Comment transcribed from local broadcast report
    "on the other side from where the Pumpkin Center data center could be coming. A lot of the people that I talked to tonight, some of those that would be most affected by these projects. These trees greet those coming into Harlem and Appling off I-20, but that could be changing. This land, one of three sites that could become data centers in Columbia County. We thought we built a family property to be passed on"

The rules across Georgia · Report missing data or a local act

What was said

Dr. Christopher Kadlec warned that emergency backup power systems present environmental considerations, particularly diesel powered generators during severe weather in south Georgia.
Dr. Christopher Kadlec, Georgia Southern University applied cyber education director · September 23, 2026 · paraphrased · WRDW (opens in a new tab) local outlet
Google agreed to pay a premium for new electricity from planned upgrades as part of a new program Georgia Power submitted to state regulators on Monday.
Georgia Power · September 22, 2026 · paraphrased · ajc.com (opens in a new tab) local outlet
Jen Ryan stated that Google worked with Columbia County leadership to exceed decibel standards and buffers for the data center.
Jen Ryan, Google representative · September 10, 2026 · paraphrased · AOL.com (opens in a new tab) national outlet
Columbia County Commissioner Doug Duncan stated that Google was an opponent during negotiations but understood the county's vision.
Doug Duncan, Columbia County Commissioner · September 10, 2026 · paraphrased · AOL.com (opens in a new tab) national outlet

View all 12 Georgia statements on the record →

8 more on this page, one per speaker and claim; 12 statements in all

Dr. Christopher Kadlec, Georgia Southern University applied cyber education director, explained that data centers are attracted to Georgia because of infrastructure, power, and Plant Vogtle nuclear generation.

WRDW (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRDW (opens in a new tab).

Jen Ryan said the data center will follow certain standards when it comes to noise, lighting, and water usage.

Google representative Yahoo (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Yahoo (opens in a new tab).

Scott Johnson, Columbia County Manager, said the goal is to find innovative ways to grow the economy, protect residents, and reduce the burden of property taxes through the partnership

WJBF (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WJBF (opens in a new tab).

Doug Duncan, Columbia County Chairman, said the county is building a partnership that has the potential to generate billions of dollars in revenue for Columbia County and provide meaningful property tax relief for homeowners

WJBF (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WJBF (opens in a new tab).

Nearby places with records

14 miles away McDuffie County: 1 data center on the record.
17 miles away Richmond County: 3 data centers on the record.
66 miles away Putnam County: 1 data center on the record.
80 miles away Candler County: 1 data center on the record.

Distances run between the centers the Census Bureau gives each place. Every Georgia county.

Disclosed figures

1.6 GW power, water from 3 records, 80 jobs

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedWithout a figureBasis
Power1.6 GW212 the developer's figure
Water, stated per day6,894,000 gallons a day303 the developer's figure
Permanent jobs80 jobs212 the developer's figure
Tax each year$203,050,880303 the developer's figure

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
No stated use31.6 GW6,894,000 gallons a day80 jobs$203,050,880

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 3 tracked facilities in Columbia County are for.

How the facilities are cooled

No source on file states how any of the 3 tracked facilities in Columbia County are cooled.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Columbia County, Georgia", https://datacenterrecord.org/states/ga/columbia-county, updated September 22, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Data center records in Columbia County, Georgia", https://datacenterrecord.org/states/ga/columbia-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Level
county
Census GEOID
13073
Census geography
County, Columbia County
Rating
Not rated