Data Center Record.
States / Georgia

Georgia, year by year.

Every act on the record for Georgia, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.

The record by year

On the record as of October 27, 2026.

An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.

50 acts on the line for Georgia, from 158 dated lines in the records' histories and the scorecard. 33 more acts are dated only by the article that reported them and sit under their month. 5 lines report an act already listed. 70 lines are background, plans or statements. 10 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).

Narrow the acts
Kind
Topic
Developer

Each count is the number of lines on this page the chip keeps. Topics are matched from the words of each line and are a finding aid, not a fact about the event.

2026 41 acts on the line from 46 reports; 32 reported, dated only by the article; 70 lines of background, plans and statements

September 2026 9 acts on the line from 11 reports; 20 reported; 24 lines of background, plans and statements

  1. Moratorium adopted Lovejoy, Georgia

    The City of Lovejoy on Monday passed an ordinance banning data center construction within city limits.

    atlantanewsfirst.com (opens in a new tab), local outlet (the weekday its sentence names, the last before the report; filed under Sep 29, 2026)

  2. Moratorium Lovejoy, Georgia

    Lovejoy city council updated zoning code to explicitly prohibit data centers.

    ajc.com (opens in a new tab), local outlet

  3. Litigation Georgia

    Southern Environmental Law Center filed lawsuit alleging OpenAI data center deal violated Georgia sunshine laws on public access to government meetings and records (alleged in the filing, not a finding)

    ajc.com (opens in a new tab), local outlet

  4. Hearing Georgia

    Georgia Public Service Commission held a town hall meeting in Savannah on September 16, 2026, to discuss the proposed OpenAI data center in Effingham County

    wjcl.com (opens in a new tab), local outlet (the day its own sentence names)

    2 more reports of this
    1. Reported September 16 Georgia PSC held a meeting in Savannah to hear public concerns about OpenAI data center in Effingham County and its power bill impacts. wabe.org (opens in a new tab)
    2. Reported September 18 Georgia Public Service Commission held meeting in Savannah and presented recent actions on data centers, including approval of Georgia Power contract with OpenAI and new protections for regular customers grist.org (opens in a new tab)
  5. Ordinance Byron, Georgia

    Byron City Council voted to approve comprehensive data center ordinance during Monday council meeting setting tighter guidelines for data center operations

    wgxa.tv (opens in a new tab), local outlet

  6. proposed OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI is planning a large data center in Effingham County, Georgia, for which Georgia Power received approval for a 3.2 GW power deal, and which faces a citizen led zoning lawsuit and questions about water and electric bill impacts.

    psc.ga.gov (opens in a new tab), primary source

  7. Lawsuit Effingham County, Georgia

    Three Effingham County residents filed a lawsuit September 2 challenging Ordinance 2026-352, which county commissioners gave final approval August 4

    effinghamherald.net (opens in a new tab), local outlet

  8. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    The Development Authority and OpenAI began their conversations in October

    youtube.com (opens in a new tab), video

  9. Moratorium rejected Bulloch County, Georgia

    In September 2026, the Bulloch County Commission rejected a proposed data center ban by a 4-3 vote.

    statesboroherald.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 1, 2026)

Reported in September 2026, dated only by the article that carried them: 20 acts
  1. Moratorium Georgia

    State Rep. Ruwa Romman introduced a bill proposing a statewide moratorium on new data centers through March, citing concerns over environmental and economic impact

    benzinga.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  2. Georgia

    Georgia General Assembly adjourned without delivering on push to regulate data centers

    ajc.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Georgia

    Georgia Chamber launched the Georgia Digital Infrastructure Alliance for responsible digital infrastructure investment

    wabe.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Georgia

    Georgia Chamber launched the Data Center Ready Community Initiative as a checklist for whether a new data center is right for a community's economic development

    wabe.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. Georgia

    During her tenure on the Public Service Commission, Pridemore voted on major expansions of Georgia Power's system driven substantially by data center demand, including DC BLOX expansion in Conyers with 216 megawatts of power committed by Georgia Power

    georgiarecorder.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  6. Effingham County, Georgia

    OpenAI announced plans for a new data center in Effingham County

    gpb.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  7. Georgia

    Georgia introduced HB 1059 to forbid local governments from permitting data centers until December 2028.

    mashable.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  8. Effingham County, Georgia

    Effingham County Commission delayed the site review for the OpenAI data center

    gpb.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  9. Moratorium extended Byron, Georgia

    Byron City Council voted to extend moratorium on data centers

    wgxa.tv (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  10. Moratorium adopted Chatham County, Georgia

    Chatham County Commissioners passed a moratorium on large scale data centers of at least 10 megawatts lasting approximately five months

    wgtjradio.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  11. Moratorium Georgia

    Georgia Tech Data Center Ordinance Hub recorded 39 moratoriums enacted from September 2025 to July 2026, with nine expired by July 2026

    therealdeal.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)

  12. Ordinance Augusta, Georgia

    Augusta released final draft of data center ordinance with redline version showing all revisions

    wfxg.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  13. Denial DeKalb County, Georgia

    DeKalb County Zoning Board of Appeals denied Shadowbox Studios data center application

    youtube.com (opens in a new tab), video (dated only by the report that carried it, so under the month of the report)

  14. Ordinance Floyd County, Georgia

    Floyd County adopted ordinance governing data center development requiring zoning and addressing noise and utilities

    thecentersquare.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  15. Ordinance Candler County, Georgia

    Candler County Commissioners voted 4-0 to table discussion of data center projects and zoning ordinances

    thegeorgiavirtue.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  16. Moratorium adopted Walker County, Georgia

    Walker County commissioners enacted a data center moratorium.

    local3news.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  17. Filing Georgia

    A complaint of illegal data center zoning was filed

    gpb.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  18. Ordinance Effingham County, Georgia

    Ordinance 2026-352 changed county zoning rules to allow data centers on property already zoned for industrial use

    effinghamherald.net (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  19. Litigation Effingham County, Georgia

    Plaintiffs allege the county failed to follow state law and its own zoning rules by not holding required public hearings before approving the ordinance

    effinghamherald.net (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  20. Moratorium adopted Savannah, Georgia

    Savannah City Council approved a 155 day moratorium on large scale data centers

    savannahnow.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for September 2026, not acts of their own: 24 lines of background, plans and statements
  1. Georgia

    Georgia Department of Community Affairs decertified Social Circle for one year over data center land dispute and annexation approval without Newton County agreement

    atlantanewsfirst.com (opens in a new tab) (no act in the sentence)

  2. Georgia

    The upgrade plan is subject to approval by the Georgia Public Service Commission per Docket 44280 and Docket 56002.

    augustachronicle.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Google Columbia County Data Center (White Oak Technology Park), Appling, Georgia

    Georgia Power wants to upgrade two reactors at Plant Vogtle near Augusta and two at Plant Hatch west of Savannah to put roughly 100 megawatts total of emission free electricity on the power grid.

    ajc.com (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Statesboro, Georgia

    City Council's decision violated city ordinances, state law, and constitutional protections

    thegeorgiavirtue.com (opens in a new tab) (no act in the sentence)

  5. Effingham County, Georgia

    Effingham County residents have banded together to protest a new data center.

    gpb.org (opens in a new tab) (a description, not an act)

  6. Georgia

    Georgia law prohibits public officials from registering as a lobbyist or engaging in lobbying for one year after leaving office

    georgiarecorder.com (opens in a new tab) (a description, not an act)

  7. Rome, Georgia

    Rome city commissioners debate data center moratorium

    northwestgeorgianews.com (opens in a new tab) (no act in the sentence)

  8. Byron, Georgia

    Data center operations shall not produce continuous sound exceeding average of 75 decibels measured in dBA and 85 decibels measured in dBC over any 30 minute period between 8 a.m. and 6 p.m.

    wgxa.tv (opens in a new tab) (a plan or a schedule, not an act yet)

  9. Byron, Georgia

    Closed loop cooling systems shall be required and utilized for data centers

    wgxa.tv (opens in a new tab) (a plan or a schedule, not an act yet)

  10. Byron, Georgia

    Data centers shall comply with applicable emissions standards under Clean Air Act and EPA management

    wgxa.tv (opens in a new tab) (a plan or a schedule, not an act yet)

  11. Byron, Georgia

    Complete perimeter monitoring on 24 hour per day, 7 days per week basis from third party sound monitoring source required

    wgxa.tv (opens in a new tab) (no act in the sentence)

  12. Georgia

    Federal officials considering limiting transparency requirements on data center projects

    wabe.org (opens in a new tab) (a plan or a schedule, not an act yet)

  13. Decatur County, Georgia

    Decatur County moratorium does not have an expiration date

    therealdeal.com (opens in a new tab) (a description, not an act)

  14. Georgia

    Georgia Senate Bill 410 would end tax exemption for data center equipment while preserving benefits already granted.

    newsweek.com (opens in a new tab) (a plan or a schedule, not an act yet)

  15. Augusta, Georgia

    Augusta Commission planned to vote on data center ordinance on September 15, 2026

    wfxg.com (opens in a new tab) (a plan or a schedule, not an act yet)

  16. DeKalb County, Georgia

    DeKalb County has a data center moratorium affecting the application

    youtube.com (opens in a new tab) (a description, not an act)

  17. Floyd County, Georgia

    Floyd County ordinance limits data centers to Heavy Industrial zones and requires impact studies showing anticipated electricity, water, broadband requirements and construction phases.

    weisradio.com (opens in a new tab) (a description, not an act)

  18. Floyd County, Georgia

    Floyd County ordinance requires facilities expected to consume more than 10 megawatts of electricity to submit an energy and sustainability plan.

    weisradio.com (opens in a new tab) (a description, not an act)

  19. Floyd County, Georgia

    Floyd County ordinance gives preference to closed loop cooling systems and prohibits use of private wells, septic systems, direct surface water withdrawals and direct aquifer connections.

    weisradio.com (opens in a new tab) (a description, not an act)

  20. Effingham County, Georgia

    The county's zoning ordinance requires two public hearings before action can be taken on a zoning change, one before the Planning Board and another before the County Commission

    effinghamherald.net (opens in a new tab) (a description, not an act)

  21. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    The free meal program is scheduled to begin on Tuesday, September 8, 2026

    wtoc.com (opens in a new tab) (a plan or a schedule, not an act yet)

  22. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Campus is 1,400 acres

    youtube.com (opens in a new tab) (a description, not an act)

  23. Savannah, Georgia

    The moratorium defines large scale data centers as those with an electrical capacity of 10 megawatts or more

    savannahnow.com (opens in a new tab) (a description, not an act)

  24. Savannah, Georgia

    The moratorium prohibits warehouses and industrial properties at 200,000 square feet or more from conversion to data centers

    savannahnow.com (opens in a new tab) (a description, not an act)

August 2026 13 acts on the line from 15 reports; 11 reported; 27 lines of background, plans and statements

  1. Approval being built Google Columbia County Data Center (White Oak Technology Park), Appling, Georgia

    Economic Development Authority approved memorandum of understanding for Google Data Center in Columbia County, Georgia.

    constructionreviewonline.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)

  2. waiting on permits OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI announced a $20 billion data center in Effingham County

    ajc.com (opens in a new tab), local outlet

  3. Georgia

    Georgia Power received approval from the Georgia PSC for a 3.2 GW contract to serve an OpenAI data center.

    rtoinsider.com (opens in a new tab), trade press

    2 more reports of this
    1. Reported August 27 Georgia Public Service Commission approved Georgia Power's contract to supply electricity to OpenAI's Effingham County data center fox5atlanta.com (opens in a new tab)
    2. Reported September 16 Georgia PSC approved Georgia Power's contract with OpenAI as the largest single customer contract since 2024. wabe.org (opens in a new tab)
  4. Approval approved OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Georgia Public Service Commission approved power contract between Georgia Power and OpenAI for Project Camellia data center in Effingham County

    wsbtv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. Ordinance Floyd County, Georgia

    Floyd County Commission approved a comprehensive data center ordinance on August 25, 2026, establishing regulations for future projects in unincorporated areas.

    weisradio.com (opens in a new tab), local outlet

  6. waiting on permits OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project Camellia covers approximately 1,400 acres and could require up to 3.2 gigawatts of power

    effinghamherald.net (opens in a new tab), local outlet

  7. stalled OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI's $20B data center project in Georgia has been delayed, with Georgia Power extending the deadline for the PSC to consider its contract with OpenAI.

    psc.ga.gov (opens in a new tab), primary source

  8. being built QTS Blakely Data Center Campus, Blakely, Georgia

    QTS announces community investment in Blakely and Early County

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  9. Approval Marietta Cobb Parkway Data Center, Marietta, Georgia

    The Marietta city council voted 5 2 to approve a new data center.

    mariettaga.gov (opens in a new tab), primary source

  10. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Georgia Power entered into a 25 year agreement with OpenAI to provide 3.2 gigawatts of electricity

    effinghamherald.net (opens in a new tab), local outlet

  11. waiting on permits OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project Camellia has cleared initial hurdles through the county's development authority

    wtoc.com (opens in a new tab), local outlet

  12. Rate rule Georgia

    PSC members reviewed and approved the large load contract for Georgia Power to serve electricity to the future OpenAI data center in Effingham County in August

    statesboroherald.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Aug 1, 2026)

  13. Moratorium Floyd County, Georgia

    Floyd County Commission enacted 80 day moratorium on new data center projects in late August 2026

    thecentersquare.com (opens in a new tab), national outlet (the month its own sentence names; no day is given; filed under Sep 8, 2026)

Reported in August 2026, dated only by the article that carried them: 11 acts
  1. Hearing Augusta, Georgia

    Augusta leaders hosted meeting on data center ordinance

    wrdw.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Ordinance Atlanta, Georgia

    Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks

    theatlantavoice.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  3. Statement Georgia

    Georgia Public Service Commission staff declined to object to Georgia Power's electricity contract for OpenAI's data center filed July 27, 2026

    wjcl.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Filing OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Georgia Power agreed to provide public information on data center portfolio performance twice yearly and issue summary within 10 days of contract filing.

    wjcl.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Georgia PSC staff declined to object to Georgia Power electricity contract for OpenAI data center in Effingham County.

    wjcl.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  6. Approval Marietta, Georgia

    Marietta City Council voted 5-2 approving an 18 megawatt, 11 acre data center.

    youtube.com (opens in a new tab), video (dated only by the report that carried it, so under the month of the report)

  7. Moratorium adopted Marietta, Georgia

    The city council imposed a 6 month moratorium on new data center requests.

    youtube.com (opens in a new tab), video (dated only by the report that carried it, so under the month of the report)

  8. Georgia

    Georgia Environmental Protection Division ordered workers to stop construction on a data center and power facility due to work beginning without proper permits

    wsbtv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  9. Approval Marietta, Georgia

    Marietta City Council approved rezoning for an 18 megawatt data center on a 5-2 vote after hours of debate.

    youtube.com (opens in a new tab), video (dated only by the report that carried it, so under the month of the report)

  10. Moratorium adopted Marietta, Georgia

    Marietta City Council approved a six month temporary moratorium on new data center applications.

    youtube.com (opens in a new tab), video (dated only by the report that carried it, so under the month of the report)

  11. Approval Marietta, Georgia

    Marietta city council voted 5-2 to approve a new data center

    fox5atlanta.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for August 2026, not acts of their own: 27 lines of background, plans and statements
  1. Google Columbia County Data Center (White Oak Technology Park), Appling, Georgia

    Agreement mandates 65 decibel noise ceiling and 500 foot buffer zone from residential areas.

    constructionreviewonline.com (opens in a new tab) (a description, not an act)

  2. Google Columbia County Data Center (White Oak Technology Park), Appling, Georgia

    First payments expected late 2026 or early 2027 depending on construction milestones.

    constructionreviewonline.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Google Columbia County Data Center (White Oak Technology Park), Appling, Georgia

    Two major sites: White Oak and Pumpkin Center area in Columbia County.

    constructionreviewonline.com (opens in a new tab) (no act in the sentence)

  4. Georgia

    Georgia Power's contract to serve OpenAI's Effingham County data center was approved by the Georgia Public Service Commission

    wjcl.com (opens in a new tab) (a description, not an act)

  5. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    An annual publicly available audit conducted by an independent firm will monitor OpenAI's adherence to community and operational commitments for Project Camellia as development progresses

    wsbtv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  6. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI Project Camellia data center facility will use a closed loop water system that recirculates water to minimize ongoing water consumption

    wsbtv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  7. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI pledged 80 million dollars in local community benefits over the lifespan of the project to support schools, public safety, health care and infrastructure

    wsbtv.com (opens in a new tab) (a statement; who said what is on the statements pages)

  8. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI Project Camellia data center agreement includes providing up to 1,000 megawatts of flexible demand response

    wsbtv.com (opens in a new tab) (a description, not an act)

  9. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI Project Camellia data center will be built in phases from 2028 to 2032 and is expected to need approximately 3,200 megawatts of power once completed

    wsbtv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  10. Columbia County, Georgia

    Economic Development Authority of Columbia County is working with Google on a Memorandum of Understanding for a data center partnership

    yahoo.com (opens in a new tab) (a description, not an act)

  11. Byron, Georgia

    Byron data center ordinance requires 500 feet distance from residential property, 1000 feet from schools, places of worship, hospitals

    wgxa.tv (opens in a new tab) (a description, not an act)

  12. Byron, Georgia

    Byron data center ordinance limits noise to 75 decibels over 30 minutes from 6 a.m. to 8 p.m.

    wgxa.tv (opens in a new tab) (a description, not an act)

  13. Byron, Georgia

    Byron city council to vote on data center ordinances on Sept. 14

    wgxa.tv (opens in a new tab) (no act in the sentence)

  14. QTS Blakely Data Center Campus, Blakely, Georgia

    Data center campus will use closed loop cooling system that consumes no water for cooling once operational

    constructionowners.com (opens in a new tab) (a plan or a schedule, not an act yet)

  15. QTS Blakely Data Center Campus, Blakely, Georgia

    QTS will make $7.5 million annual payments for three years beginning in December 2026 before construction starts

    constructionowners.com (opens in a new tab) (a plan or a schedule, not an act yet)

  16. QTS Blakely Data Center Campus, Blakely, Georgia

    QTS Data Centers will invest at least $28.75 million in community betterment fund for Blakely and Early County Georgia data center development

    constructionowners.com (opens in a new tab) (a plan or a schedule, not an act yet)

  17. Marietta, Georgia

    The city council required 1 million dollars in sound mitigation for the data center project.

    youtube.com (opens in a new tab) (no act in the sentence)

  18. Marietta Cobb Parkway Data Center, Marietta, Georgia

    The data center utilizes a closed loop cooling system.

    youtube.com (opens in a new tab) (no act in the sentence)

  19. Wayne County, Georgia

    Wayne County is tightening data center rules ahead of tech expansion

    wtoc.com (opens in a new tab) (a description, not an act)

  20. Marietta, Georgia

    Developers must install silencers and conduct independent testing for the data center.

    youtube.com (opens in a new tab) (a description, not an act)

  21. Georgia

    An EPA plan could reduce public scrutiny of Georgia data center air permits

    axios.com (opens in a new tab) (a plan or a schedule, not an act yet)

  22. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Site will operate a closed loop cooling system to continuously recycle the same water instead of relying on evaporative methods

    wtoc.com (opens in a new tab) (a plan or a schedule, not an act yet)

  23. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Agreement mandates that developers draw only from treated surface rivers rather than underground groundwater

    wtoc.com (opens in a new tab) (a description, not an act)

  24. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI data center planned for Effingham County

    gpb.org (opens in a new tab) (a plan or a schedule, not an act yet)

  25. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project planned for phased development between 2028 and 2032

    savannahnow.com (opens in a new tab) (a plan or a schedule, not an act yet)

  26. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    1,440 acre data center campus with four buildings and combined footprint of 720,000 square feet

    savannahnow.com (opens in a new tab) (no act in the sentence)

  27. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI planned $20 billion data center campus with 4.4 million square feet in Effingham County

    ajc.com (opens in a new tab) (a plan or a schedule, not an act yet)

July 2026 14 acts on the line from 15 reports; 1 reported; 19 lines of background, plans and statements

  1. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Agreement gave Broe and OmniTRAX authority as sole and exclusive agent, attorney in fact and master developer of nearly 2,600 acres of ECIDA owned land

    effinghamherald.net (opens in a new tab), local outlet

  2. proposed OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project Camellia is a planned 1,400 acre data center campus at the Savannah Gateway Industrial Hub

    effinghamherald.net (opens in a new tab), local outlet

  3. Filing OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Contract was filed on July 27, 2026.

    wjcl.com (opens in a new tab), local outlet (the day its own sentence names; filed under Aug 26, 2026)

  4. waiting on permits OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project Camellia must undergo Georgia Developments of Regional Impact process before construction can begin

    thecurrentga.org (opens in a new tab), local outlet

  5. approved OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Nearly 1,000 people attended an open house on July 23, 2026 about the $20 billion OpenAI data center project in Effingham County

    thecurrentga.org (opens in a new tab), local outlet

  6. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Under a 25 year agreement, OpenAI agreed to cut up to 1,000 megawatts during peak demand to help grid reliability

    youtube.com (opens in a new tab), video

  7. Filing OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    DRI form submitted July 23, 2026 by Effingham County Senior Planner Kimberly Barlett with blank spaces for water usage, energy supply, and environmental impacts

    thecurrentga.org (opens in a new tab), local outlet (the day its own sentence names; filed under Jul 25, 2026)

  8. approved OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI data center will comprise four buildings at Savannah Gateway Industrial Hub

    thecurrentga.org (opens in a new tab), local outlet

  9. proposed OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI announced plans for a new project in Effingham County, Georgia, about 45 minutes outside of Savannah

    prnewswire.com (opens in a new tab), press release

    1 more report of this
    1. Jul 23 OpenAI data center project in Effingham County announced without any public comment or vote thecurrentga.org (opens in a new tab)
  10. proposed OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI proposes a $20 billion data center campus in Effingham County

    youtube.com (opens in a new tab), video

  11. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project announced July 22 followed by public information open house July 23

    effinghamherald.net (opens in a new tab), local outlet (the day its own sentence names; filed under Jul 28, 2026)

  12. Approval approved OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Effingham County Industrial Development Authority approved incentive package for OpenAI data center on July 21, 2026

    savannahnow.com (opens in a new tab), local outlet (the day its own sentence names; filed under Aug 3, 2026)

  13. approved Marietta Cobb Parkway Data Center, Marietta, Georgia

    Self storage facility targeted for 18 MW data center in Marietta

    datacenterdynamics.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)

  14. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI announced the project in July with a proposed $20 billion data center campus

    effinghamherald.net (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Aug 24, 2026)

Reported in July 2026, dated only by the article that carried it: 1 act
  1. Approval Marietta, Georgia

    Marietta Planning Commission voted 4-3 in favor of rezoning 10 acres for data center project

    wsbradio.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for July 2026, not acts of their own: 19 lines of background, plans and statements
  1. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project has multi year five phase timeline with first phase targeted to begin construction by late 2028 and entire project completed by end of 2034

    wtoc.com (opens in a new tab) (a description, not an act)

  2. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    County records show the Special Payment in Lieu of Taxes agreement gives OpenAI a 37.5 percent annual property tax reduction, assessing the property at 25 percent of fair market value instead of the standard 40 percent, locked at the 2026 millage rate for 15 years

    wtoc.com (opens in a new tab) (a description, not an act)

  3. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Savannah Gateway property has been zoned industrial since 2006

    effinghamherald.net (opens in a new tab) (a description, not an act)

  4. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    County must wait until DRI process complete before initiating engineering reviews, fire and stormwater plans, or noise level evaluations

    thecurrentga.org (opens in a new tab) (a description, not an act)

  5. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Georgia Coastal Regional Commission must evaluate project in no more than 30 days

    thecurrentga.org (opens in a new tab) (a description, not an act)

  6. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Effingham County Industrial Development Authority was initially approached about the data center around fall 2025

    thecurrentga.org (opens in a new tab) (no act in the sentence)

  7. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI promises $80 million in community benefits including sports fields and free training for school students

    thecurrentga.org (opens in a new tab) (a statement; who said what is on the statements pages)

  8. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI will receive short term tax abatements during construction and become the county's largest taxpayer after opening in 2028

    thecurrentga.org (opens in a new tab) (a plan or a schedule, not an act yet)

  9. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    OpenAI data center project covers 2,600 acres at Savannah Gateway Industrial Hub

    thecurrentga.org (opens in a new tab) (a description, not an act)

  10. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Site is next to a high school and less than a mile from a park

    youtube.com (opens in a new tab) (a description, not an act)

  11. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Project Camellia covers about 1,400 acres inside Savannah Gateway Industrial Hub with four buildings and $20 billion price tag

    youtube.com (opens in a new tab) (a description, not an act)

  12. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    The site is located just outside of Rincon in Effingham County

    thecurrentga.org (opens in a new tab) (a description, not an act)

  13. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Data center is scheduled to open in phases starting in 2028

    thecurrentga.org (opens in a new tab) (a plan or a schedule, not an act yet)

  14. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    25 year agreement with Georgia Power

    prnewswire.com (opens in a new tab) (no act in the sentence)

  15. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Site is located at Savannah Gateway Industrial Hub, approximately 12 miles northwest of the Port of Savannah

    youtube.com (opens in a new tab) (a description, not an act)

  16. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Construction is expected to begin in 2028 and finish by 2032, with operations planned from 2028; project discussions began in November 2023, dates also on WTOC and the county video

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  17. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    Campus will cover more than 1,400 acres on McCall Road in Effingham County

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  18. Marietta, Georgia

    Marietta City Council expected to consider rezoning matter at July 8 meeting

    wsbradio.com (opens in a new tab) (a plan or a schedule, not an act yet)

  19. Atlanta, Georgia

    Communities placing moratoriums on data center development citing concerns about power and water usage, traffic, environmental impacts and noise

    wsbradio.com (opens in a new tab) (no act in the sentence)

June 2026 4 acts on the line

  1. Filing waiting on permits DataBank Cartersville Campus (Project Indo), Cartersville, Georgia

    DataBank filed a Development of Regional Impact application for Project Indo in Cartersville, Georgia, a 200 MW campus across 69 acres totaling 1.1 million sq ft valued at approximately $2.4 billion, with first phase targeted for 2032.

    datacenterdynamics.com (opens in a new tab), trade press

  2. Moratorium adopted Floyd County, Georgia

    Floyd County approved 80 day moratorium on June 9, 2026, to allow time to draft specific requirements for data centers.

    weisradio.com (opens in a new tab), local outlet

  3. Statesboro, Georgia

    city amended its Unified Development Code on June 2, 2026, to allow data centers in an O office/business zoning district and prohibited hyperscale data centers within city limits

    thegeorgiavirtue.com (opens in a new tab), local outlet

  4. Ordinance Statesboro, Georgia

    The City of Statesboro adopted a data center ordinance in June 2026 and later rezoned land on Burkhalter Road where a data center could possibly be built.

    statesboroherald.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jun 1, 2026)

April 2026 1 act on the line

  1. being built Google LaGrange Data Center Campus, LaGrange, Georgia

    Google announces new data center coming to LaGrange, Georgia.

    wsav.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

2025 3 acts on the line

November 2025 1 act on the line

  1. proposed Bolingbroke Technology Campus (Forsyth), Forsyth, Georgia

    Trammell Crow Company proposes a $21 billion, 1,632 acre data center campus along I 75 in Forsyth, Georgia, comprising up to 12 million square feet across 21 data center warehouses.

    ajc.com (opens in a new tab), local outlet

January 2025 1 act on the line

  1. proposed Amazon Web Services Butts County Campus, Jackson, Georgia

    Amazon Web Services plans to spend at least $11 billion on new data center capacity in Butts County (and Douglas County) in metro Atlanta.

    ajc.com (opens in a new tab), local outlet

2025, no month given 1 act

  1. Georgia

    Georgia PSC adopted rules in 2025 for new customers with electricity demand of at least 100 megawatts.

    wjcl.com (opens in a new tab), local outlet (the year its own sentence names; filed under Aug 26, 2026)

2024 4 acts on the line

July 2024 1 act on the line

  1. proposed ATL03 Red Oak Data Center Campus (Union City), Union City, Georgia

    Burr Computer Environments filed a Developments of Regional Impact application for a 2.1 million square foot data center campus designated ATL11 in Union City, Fulton County, with construction set to start in 2026.

    datacenterdynamics.com (opens in a new tab), trade press

June 2024 1 act on the line

  1. proposed T5 Data Centers Fairburn Campus, Fairburn, Georgia

    T5 Data Centers is planning a data center campus in Fairburn, Georgia.

    apps.dca.ga.gov (opens in a new tab), primary source

March 2024 1 act on the line

  1. Groundbreaking being built Microsoft Palmetto Data Center (CCO06), Palmetto, Georgia

    Microsoft acquired nearly 21 acres adjacent to its existing Palmetto data center campus in south Fulton County for $6 million to support ongoing data center construction, and later purchased additional land near Atlanta.

    ajc.com (opens in a new tab), local outlet

February 2024 1 act on the line

  1. Filing waiting on permits DC BLOX Conyers Data Center Campus (ATL East), Conyers, Georgia

    Strategic Real Estate Partners filed state paperwork for a three warehouse, 837,500 square foot data center campus on 53 acres near Conyers in Rockdale County, east of Atlanta.

    ajc.com (opens in a new tab), local outlet

2023 0 acts on the line; 1 reported, dated only by the article

November 2023 No acts on the line; 1 reported

Reported in November 2023, dated only by the article that carried it: 1 act
  1. Acquisition DataBank Atlanta Campus (ATL1 / ATL2 / ATL3 / ATL4), Atlanta, Georgia

    DataBank acquires nearly 100 acres near Atlanta for new data center campus

    costar.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

2016 1 act on the line

February 2016 1 act on the line

  1. OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    In February 2016, ECIDA board voted 7 1 to partner with OmniTRAX in collaboration with Broe Real Estate Group as master developer

    effinghamherald.net (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jul 28, 2026)

2006 1 act on the line

2006, no month given 1 act

  1. Acquisition OpenAI Effingham County Data Center Campus (Project Camellia), Rincon, Georgia

    ECIDA purchased the property near Rincon in 2006 from International Paper for about $31 million

    effinghamherald.net (opens in a new tab), local outlet (the year its own sentence names; filed under Jul 28, 2026)

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data