Marietta resident
Susan Clark requested moratorium on data centers in Marietta pending further study
The Marietta city council voted 5-2 to approve a new data center. It is reported, as reported July 7, 2026.
How much power it needs, how much water it would use and who would use it have not been disclosed.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
Each figure as its source gave it. The number in brackets is its place in the source list.
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | Not disclosed | |||
| How much water it would use | Not disclosed | |||
| How loud it would be | Not disclosed | |||
| Jobs once it runs | Not disclosed | |||
| Tax it would pay each year | Not disclosed |
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Not disclosed | |||
| Who is constructing it | Not disclosed | |||
| How much land | Not disclosed | |||
| Where its power comes from | Not disclosed | |||
| Grid connection | Not disclosed | |||
| How it is cooled | Not disclosed |
How much power it needs, also reported: 18 MW, 2026 (YouTube: The data center project near Interstate 75 and Delk Road will have a capacity of 18 megawatts.); 12 MW, 2026 (95.5 WSB: Data center facility is 12 megawatts) .
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
The record adds each the day a source gives it. Why these documents.
Acts of Cobb County and Marietta about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Marietta | The city council required 1 million dollars in sound mitigation for the data center project. | youtube.com | |
| Marietta | The city council imposed a 6 month moratorium on new data center requests. | youtube.com | |
| Marietta | Marietta City Council voted 5-2 approving an 18 megawatt, 11 acre data center. | youtube.com | |
| Marietta | Developers must install silencers and conduct independent testing for the data center. | youtube.com | |
| Marietta | Marietta City Council approved a six month temporary moratorium on new data center applications. | youtube.com | |
| Marietta | Marietta City Council approved rezoning for an 18 megawatt data center on a 5-2 vote after hours of debate. | youtube.com |
| Date | Who | Decision | Source |
|---|---|---|---|
| Marietta | Marietta city council voted 5-2 to approve a new data center | fox5atlanta.com | |
| Marietta | Marietta City Council expected to consider rezoning matter at July 8 meeting | wsbradio.com | |
| Marietta | Marietta Planning Commission voted 4-3 in favor of rezoning 10 acres for data center project | wsbradio.com |
(source date; the content gives no date of its own)
The data center utilizes a closed loop cooling system. [4]
· Status: rumored (source date; the content gives no date of its own)
Self storage facility targeted for 18 MW data center in Marietta [1]
The full Marietta Data Center timeline, in order
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
Every correction on the record is on the corrections page.
Georgia Digital Infrastructure Alliance announced a six figure statewide advertising campaign on data center development benefits
Parks Huff, attorney for developer, stated facility is needed and location is ideal for data center due to infrastructure proximity
Every statement about data centers in Georgia, by speaker
Marietta resident
Susan Clark requested moratorium on data centers in Marietta pending further study
Where in Cobb County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.
Tap a pin for the data center, the parcel for its record
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
Not disclosed. No source on file gives its capacity, its acreage or a count of buildings. What the record holds instead is under Disclosed.
Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is reported, as reported July 7, 2026. The newest entry, reported August 21, 2026: The data center utilizes a closed loop cooling system. [4]
Marietta: The city council required 1 million dollars in sound mitigation for the data center project. (reported August 21, 2026, source); and Marietta: The city council imposed a 6 month moratorium on new data center requests. (reported August 21, 2026, source). 9 events are on the county's rows; a rule about the area is not a decision about this record.
Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is building it, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
4 sources on file.
Data Center Record, "Marietta Data Center", https://datacenterrecord.org/projects/marietta-data-center-ga, last verified September 17, 2026.
Data Center Record, "Marietta Data Center", https://datacenterrecord.org/projects/marietta-data-center-ga. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.