A blank rating cell means no person has set one for the city. A city without a record is listed, not linked.
What Cobb County has decided1 body, 5 decisions on the record
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
Marietta City Council approved a six month temporary moratorium on new data center applications.youtube.com (opens in a new tab)video · Aug 13, 2026 · 5 acts on this rowEvery act on the Marietta row
moratorium adopted
The city council imposed a 6 month moratorium on new data center requests.
Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
August 12, 2026Marietta, GAMarietta City Council 18 MW Data Center Rezoning and Six Month Moratorium VoteMarietta City Council3 clips
Marietta City Council voted 5 to 2 to approve an 18 megawatt, 11 acre data center with a 1 million dollar sound mitigation condition while simultaneously imposing a six month moratorium on any new data center applications.
Fox Business Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"Five back to approving 18 megawatt 11 acre data center. A move some are calling controversial. Now, just weeks ago city council impose a six month moratorium on new data center request. This project was already in the pipeline when the moratorium took effect. My next guest sits on that city council and voted yes for the data center."
Fox Business Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"One 18 megawatts, it has zero negative impact on the ratepayer it has a closed loop system and we are making sound better for the residents that are kind of f on the other it cited then is now because it's right and sigh 75 required over a million dollars in sound mitigation. This absolutely hurts no one could only help the citizens of Marietta were open for business"
Fox Business Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"Writing about with the latest ot meetings over this data center, people and I understand reticence from people in the rural south, to these data center projects. But, people have lost their minds. The one you just approved is not even an a.I. Data center. Please tell the audience is going to be used for law enforcement, medical and"
July 8, 2026Marietta, GAMarietta data center approved despite pushbackMarietta City Council3 clips
Marietta City Council members and residents debated a proposed pause on new data center applications and the creation of a Marietta Data Center Advisory Committee to rewrite municipal zoning standards.
11Alive Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"pollution a concern when it comes to these data centers. So, silencers going to be installed. They have to conduct independent testing and they have to stay away from the city's municipal water and waste water supply cuz of course there's concern from residents about what this could mean for my water bill. still though that was not enough for some people in the crowd. This is what happened inside Council Chambers right after that vote. Okay, so it was a 5-2 vote came after a"
11Alive Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"self storage property or at least part of it into an 18 megawatt data center. The property owner says it won't increase water consumption. It will include measures to minimize noise. Meanwhile, council members heard from people on both sides of the debate. It really doesn't generate anything positive for the community. It just extracts well from the community. It's going to make Marietta basically one of the"
Resident public commentResident Public Commenttranscribed from local broadcast report
"artificial intelligence. He says this data center is all about processing information quickly. So, that project has the green light, although they do have to abide by some of those conditions that I just laid out for you. By the way, if you're asking yourself, Marietta, Marietta, I know you were just talking about a data center moratorium in Marietta. Yes, we were. Just last month that same city council approved a"
Venue:Georgia Governor's Veto Statement on House Bill 1192
"Vetoed House Bill 1192, which would have suspended Georgia's state sales and use tax exemption for high tech data center equipment for two years, claiming that pausing the tax exemption would undermine Georgia's grid planning and business climate."
"Primary filings in Georgia Public Service Commission Docket 44280 and the 2025 and 2026 Integrated Resource Plan (Docket 56002) document that 80 percent of Georgia Power's projected multi gigawatt load growth comes from hyperscale data centers, requiring emergency fossil fuel and battery capacity additions and prompting the Commission to adopt Rule 515-3-4 imposing special contract and billing terms on any facility exceeding 100 megawatts."
12 miles awayFulton County: 28 data centers on the record.
20 miles awayDouglas County: 14 data centers on the record.
23 miles awayDeKalb County: 1 data center on the record.
25 miles awayBartow County: 5 data centers on the record.
Distances run between the centers the Census Bureau gives each place. Every Georgia county.
Disclosed figures
18 MW power
Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.
Power, water, jobs and tax
Figure
Disclosed total
Disclosed
Without a figure
Basis
Power
18 MW
1
2
1 the developer's figure
Water, stated per day
0
3
Water, stated per year
0
3
Permanent jobs
0
3
Tax each year
0
3
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
Use
Records
Power
Water
Jobs
Tax each year
No stated use
3
18 MW
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 3 tracked facilities in Cobb County are for.
How the facilities are cooled
No source on file states how any of the 3 tracked facilities in Cobb County are cooled.
FiguresOnly what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
LicenseData CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this pageData Center Record, "Data centers in Cobb County, Georgia", https://datacenterrecord.org/states/ga/cobb-county, updated October 26, 2026.CSV · JSON
Data Center Record, "Data center records in Cobb County, Georgia", https://datacenterrecord.org/states/ga/cobb-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.