Marietta City Council 18 MW Data Center Rezoning and Six Month Moratorium Vote
Marietta City Council voted 5 to 2 to approve an 18 megawatt, 11 acre data center with a 1 million dollar sound mitigation condition while simultaneously imposing a six month moratorium on any new data center applications.
Privacy enhanced player · zero third party requests until clicked
Marietta City Council 18 MW Data Center Rezoning and Six Month Moratorium Vote
Marietta City Council · August 12, 2026
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
Clip 1 · 0:16Jason Waters, Council Member, Marietta City CouncilElected OfficialIn supporttranscribed from the official recording
ZoningMoratoriumPower & Grid
Marietta Council Member Jason Waters explains the council's 5 to 2 vote approving the 18 megawatt project already in the pipeline alongside a six month moratorium on new filings.
"FIVE BACK TO APPROVING 18 MEGAWATT 11 ACRE DATA CENTER. A MOVE SOME ARE CALLING CONTROVERSIAL. NOW, JUST WEEKS AGO CITY COUNCIL IMPOSE A SIX MONTH MORATORIUM ON NEW DATA CENTER REQUEST. THIS PROJECT WAS ALREADY IN THE PIPELINE WHEN THE MORATORIUM TOOK EFFECT. MY NEXT GUEST SITS ON THAT CITY COUNCIL AND VOTED YES FOR THE DATA CENTER."
Clip 2 · 3:00Jason Waters, Council Member, Marietta City CouncilElected OfficialIn supporttranscribed from the official recording
WaterNoiseMoratorium
Council Member Jason Waters details the facility's closed loop cooling system, acoustic mitigation requirements, and the need to update Marietta's zoning code during the six month moratorium.
"ONE 18 MEGAWATTS, IT HAS ZERO NEGATIVE IMPACT ON THE RATEPAYER IT HAS A CLOSED LOOP SYSTEM AND WE ARE MAKING SOUND BETTER FOR THE RESIDENTS THAT ARE KIND OF F ON THE OTHER IT CITED THEN IS NOW BECAUSE IT'S RIGHT AND SIGH 75 REQUIRED OVER A MILLION DOLLARS IN SOUND MITIGATION. THIS ABSOLUTELY HURTS NO ONE COULD ONLY HELP THE CITIZENS OF MARIETTA WERE OPEN FOR BUSINESS"
Clip 3 · 0:47Marietta City Council MemberElected OfficialOpposedtranscribed from the official recording
ZoningMoratoriumNoisePower & GridNDAs
Marietta City Council members deliberate on municipal siting standards, utility capacity, and the recorded ordinance action.
"WRITING ABOUT WITH THE LATEST OT MEETINGS OVER THIS DATA CENTER, PEOPLE AND I UNDERSTAND RETICENCE FROM PEOPLE IN THE RURAL SOUTH, TO THESE DATA CENTER PROJECTS. BUT, PEOPLE HAVE LOST THEIR MINDS. THE ONE YOU JUST APPROVED IS NOT EVEN AN A.I. DATA CENTER. PLEASE TELL THE AUDIENCE IS GOING TO BE USED FOR LAW ENFORCEMENT, MEDICAL AND"
Venue:Georgia Governor's Veto Statement on House Bill 1192
"Vetoed House Bill 1192, which would have suspended Georgia's state sales and use tax exemption for high tech data center equipment for two years, claiming that pausing the tax exemption would undermine Georgia's grid planning and business climate."
"Primary filings in Georgia Public Service Commission Docket 44280 and the 2025 and 2026 Integrated Resource Plan (Docket 56002) document that 80 percent of Georgia Power's projected multi gigawatt load growth comes from hyperscale data centers, requiring emergency fossil fuel and battery capacity additions and prompting the Commission to adopt Rule 515-3-4 imposing special contract and billing terms on any facility exceeding 100 megawatts."