Data centers in Floyd County, Georgia
Floyd County has 2 data centers on the record: 2 proposed. Floyd County decides new data centers one at a time, and a pause on new data centers is on the record. The latest decision on the record: Floyd County adopted ordinance governing data center development requiring zoning and addressing noise and utilities, reported September 8, 2026.
The 2 data centers in Floyd County
Every Floyd County record 2 records · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Microsoft Floyd County ATL80 Campus (DRI #4860) Floyd County | Proposed Waiting on permits Georgia DCA DRI #4860 regional review filing | Microsoft Corporation | 422 | Microsoft Corporation filed Georgia DCA DRI #4860 on October 20, 2026 for ATL80, a 3 building, 422 MW data center campus on 349.03 acres north of Huffaker Road in unincorporated Floyd County. apps.dca.ga.gov (opens in a new tab) primary source October 20, 2026 | the developer's figure | site | 1 | 2026-10-20 |
| Project Gracie Data Center Campus (Floyd County, DRI #4448) Floyd County | Proposed Waiting on permits Georgia DCA DRI #4448 regional review filing | Project Gracie Applicant | Georgia DCA DRI #4448 was filed in April 2025 for Project Gracie, a 7 building, 2,395,000 square foot data center campus in unincorporated Floyd County. apps.dca.ga.gov (opens in a new tab) primary source April 10, 2025 | site | 1 | 2025-04-10 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
The cities in Floyd County on the record (1)
| City | Census GEOID | Projects | Rules |
|---|---|---|---|
| Rome | 1366668 | 1 |
A city without a record is listed, not linked.
What Floyd County has decided 2 bodies, 4 decisions on the record
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| Floyd County | county | Floyd County ordinance limits data centers to Heavy Industrial zones and requires impact studies showing anticipated electricity, water, broadband requirements and construction phases. weisradio.com (opens in a new tab) local outlet Sep 7, 20264 acts on this rowEvery act on the Floyd County row
| 4 | 2026-09-08 | ||
| Rome | city | not rated | No dated act on this row yet. | 2026-09-17 |
Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
The rules across Georgia · Report missing data or a local act
What happened
-
Now waiting on permitsMicrosoft Floyd County ATL80 Campus (DRI #4860)
apps.dca.ga.gov (opens in a new tab) primary source -
OrdinanceFloyd County
thecentersquare.com (opens in a new tab) national outlet -
OrdinanceFloyd County
weisradio.com (opens in a new tab) local outlet -
MoratoriumFloyd County
Floyd County Commission enacted 80 day moratorium on new data center projects in late August 2026
thecentersquare.com (opens in a new tab) national outlet -
Moratorium adoptedFloyd County
weisradio.com (opens in a new tab) local outlet -
Now waiting on permitsProject Gracie Data Center Campus (Floyd County, DRI #4448)
apps.dca.ga.gov (opens in a new tab) primary source
Nearby places with records
Distances run between the centers the Census Bureau gives each place. Every Georgia county.
Disclosed figures
422 MW power, water from 1 record, 150 jobs
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 422 MW | 1 | 1 | 1 the developer's figure |
| Water, stated per day | 13,500 gallons a day | 1 | 1 | 1 the developer's figure |
| Permanent jobs | 150 jobs | 1 | 1 | 1 the developer's figure |
| Tax each year | $36,000,000 | 1 | 1 | 1 the developer's figure |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 2 | 422 MW | 13,500 gallons a day | 150 jobs | $36,000,000 |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 2 tracked facilities in Floyd County are for.
How the facilities are cooled
No source on file states how any of the 2 tracked facilities in Floyd County are cooled.
About this data
Report a correction · Send a tip about Floyd County · The rows here are part of the Georgia export.
Cite this page
Data Center Record, "Data center records in Floyd County, Georgia", https://datacenterrecord.org/states/ga/floyd-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Level
- county
- Census GEOID
- 13115
- Census geography
- County, Floyd County
- Rating
- Case by case