Bow residents are divided over a possible data center, with debate centering on tax relief benefits versus environmental concerns. [1] Granite Shore Power, owners of closed Merrimack Station in Bow, filed request with Federal Energy Regulatory Commission to enter discussions with Eversource about making a connection to the power grid for a 350 megawatt project [5]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
Sam H., resident of Hopkinton, wrote that construction of hyperscale data center will be detriment to Bow and region because these facilities consume enormous amounts of electricity, provide few permanent jobs, require environmental costs and infrastructure, and risk higher rates(September 24, 2026) [5]
Beth H. stated that a data center at Merrimack Station would impact the region at large and downstream communities(September 23, 2026) concordmonitor.com (opens in a new tab)
Michael Vose, former chair of the N.H. House Science, Technology, & Energy Committee and sponsor of HB 672, argues that data centers should provide their own power under House Bill 672 rather than being subject to a state moratorium.(September 16, 2026) [4]
Governor Kelly Ayotte has proposed a statewide data center moratorium, citing insufficient state energy resources.(September 16, 2026) [4]
View all 12 statements on the record in New Hampshire →
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Bow Data Center.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | |||
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
Filing (source date; the content gives no date of its own)
Granite Shore Power, owners of closed Merrimack Station in Bow, filed request with Federal Energy Regulatory Commission to enter discussions with Eversource about making a connection to the power grid for a 350 megawatt project
(source date; the content gives no date of its own)
A preliminary study will examine the viability of a potential 350 megawatt interconnection associated with Granite Shore Power related to the rumored Bow data center.
(source date; the content gives no date of its own)
Data center would be located next to Merrimack Station power plant
(source date; the content gives no date of its own)
Eversource has been in communication with a developer interested in building a data center in Bow
(source date; the content gives no date of its own)
The project is proposed at the Merrimack Station, a coal fired power plant that ceased operations in September 2025
(source date; the content gives no date of its own)
Granite Shore Power is exploring a 350 megawatt data center project in Bow
(source date; the content gives no date of its own)
Granite Shore Power owns the 345 acre Merrimack Plant site
(source date; the content gives no date of its own)
Merrimack Station, a coal fired power plant, ceased operations in September 2025 and was due for retirement in 2028
Filing (source date; the content gives no date of its own)
Eversource and Granite Shore Power filed an application to the Federal Energy Regulatory Committee for a viability study for an up to 350 megawatt interconnection at the Merrimack Station coal plant
· reported (source date; the content gives no date of its own)
An unnamed town official in Bow confirmed there were high level discussions with a company about bringing a 350 megawatt data center to the town
· Citation
Cites the later report of the same claim by the same speaker (said again on September 5, 2026; the record's rules, October 10, 2026).
· Citation
Cites the later report of the same claim by the same speaker (said again on September 5, 2026; the record's rules, October 10, 2026).
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Tier after resolution (September 21, 2026). The source on file is mainepublic.org, the publisher's own page. The item reached the record through Google News: "data center" Maine, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of monitoring_sources. The speaker, the claim, the date and the url are unchanged.
Tier after resolution (September 21, 2026). The source on file is mainepublic.org, the publisher's own page. The item reached the record through Google News: "data center" Maine, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of monitoring_sources. The speaker, the claim, the date and the url are unchanged.
Tier after resolution (September 21, 2026). The source on file is mainepublic.org, the publisher's own page. The item reached the record through Google News: "data center" Maine, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of monitoring_sources. The speaker, the claim, the date and the url are unchanged.
Every correction on the record is on the corrections page.
Verified data center records in New Hampshire within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Bow Data Center (350 MW) Bow, Merrimack County | Less than 1 mi | Proposed | ||
| FirstLight Bedford Colocation Data Center (8 Commerce Drive) Bedford, Hillsborough County | ~18 mi | Running | FirstLight Fiber | |
| Nottingham Data Center (unnamed developer) Nottingham, Rockingham County | ~28 mi | Proposed | Thomas Moulton | |
| Liberty Mutual Data Center Portsmouth, Rockingham County | ~39 mi | Running | Liberty Mutual Insurance | |
| Dartmouth College Data Center Lebanon, Grafton County | ~47 mi | Running | Dartmouth College |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is reported, as reported September 2, 2026. The newest entry, reported September 24, 2026: Granite Shore Power, owners of closed Merrimack Station in Bow, filed request with Federal Energy Regulatory Commission to enter discussions with Eversource about making a connection to the power grid for a 350 megawatt project [5].
8 sources on file.
This site is in the NPCC New England (NEWE) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Bow Data Center. Last verified September 24, 2026. https://datacenterrecord.org/projects/bow-data-center-nh. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Bow Data Center
Data Center Record, "Bow Data Center", https://datacenterrecord.org/projects/bow-data-center-nh. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.