Data Center Record.

Data centers in Pennsylvania

Pennsylvania has 79 data center sites, 22 buildings where disclosed on the record: 18 running, 3 being built, 57 proposed and 1 stalled or cancelled. The counties with the most are Lackawanna County (12) and Luzerne County (12), and records are in 27 of 67 counties. The largest proposal is Homer City Energy Campus Redevelopment in Indiana County, 4.5 GW (the developer's figure); it is being built since September 4, 2026.

Pennsylvania decides case by case. From the state's own rule: PUC established model large load tariff in May 2026 to ensure customers requiring 50 megawatts or more bear the costs they add to electric system, May 1, 2026.

State register coverage: Pennsylvania's air permit, parcel, utility, water, and operator registers name 79 facilities; 79 are on the record (22 buildings where disclosed), and 0 sit not yet verified.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Nuclear power restart: Crane Clean Energy Center (Three Mile Island Unit 1) in Dauphin County is undergoing a 835 MW commercial restart contracted for data centers. View nuclear infrastructure record →

Projects and campuses on the record

Facility and countyStageOperatorPower (MW)Latest entry
Amazon Web Services data center, Center Township Center Township, Indiana CountyProposed Proposed, no permit applications receivedAmazon Web Services
Archbald I LLC and Archbald II LLC Data Centers Archbald, Lackawanna CountyProposed Proposed, no permit applications receivedArchbald I LLC / Archbald II LLC
Avison Young data center, Wilkes-Barre Wilkes-Barre, Luzerne CountyProposed Proposed, no permit applications receivedAvison Young
Breaker Street Data Center Jessup, Lackawanna CountyProposed Proposed, no permit applications receivedBreaker Street Associates LLC
Brewster Land Company LLC data center, Dorrance Township Dorrance Township, Luzerne CountyProposed Proposed, no permit applications receivedBrewster Land Company LLC
Corscale Dauphin data center Swatara Township, Dauphin CountyProposed Proposed, no permit applications receivedCorscale
Dickson City Data Center Dickson City, Lackawanna CountyProposed Proposed, no permit applications receivedDickson City Development LLC
Emaus Ave Warehouse Allentown, Lehigh CountyProposed Proposed, no permit applications receivedQuantm LLC
Fezzik Energy data center, Midland Midland, Beaver CountyProposed Proposed, no permit applications receivedFezzik Energy
Frackville Data New Castle Township, Schuylkill CountyProposed Proposed, no permit applications receivedKRNL Data Centers
Gouldsboro Data Center Project / Project Gold Clifton Township, Lackawanna CountyProposed Proposed, no permit applications receivedQuantm Group LLC / 1778 Rich Pike LLC
Hendricks data center, Penn Forest Township Penn Forest Township, Carbon CountyProposed Proposed, no permit applications receivedHendricks
KSR data center, Plains Township Plains Township, Luzerne CountyProposed Proposed, no permit applications receivedKSR
LBT Investment Group LLC data center, Sugarloaf Township Sugarloaf Township, Luzerne CountyProposed Proposed, no permit applications receivedLBT Investment Group LLC
Linde Data Center / Forest City Energy Center LLC Clinton Township, Wayne CountyProposed Proposed, no permit applications received
Londonderry Data Center Londonderry Township, Dauphin CountyProposed Proposed, no permit applications receivedLondonderry Data Center Developer
Mount Carmel Township Data Center Mount Carmel Township, Northumberland CountyProposed Proposed, no permit applications received
Nescopeck / Valley View Wood Data Center Nescopeck Township, Luzerne CountyProposed Proposed, no permit applications received
Outrigger Data Center Mifflin Township, Columbia CountyProposed Proposed, no permit applications received
Pocono Manor Investors data center, Tobyhanna Township Tobyhanna Township, Monroe CountyProposed Proposed, no permit applications receivedPocono Manor Investors
Project Green Mountain Archbald, Lackawanna CountyProposed Proposed, no permit applications receivedGreen Mountain 6 LLC
Project Hummingbird Monongahela Township, Greene CountyProposed Proposed, no permit applications receivedInternational Electric Power
Project Scott Archbald, Lackawanna CountyProposed Proposed, no permit applications receivedPatrinely and Provident Real Estate
Spring Mountain Quakake Tunnel Packer Township, Carbon CountyProposed Proposed, no permit applications receivedNorthPoint Development
Sunnyside Road Data Center Jessup, Lackawanna CountyProposed Proposed, no permit applications receivedSunnyside Road Associates LLC
Verdantas and Prologis data center, Allen Township Allen Township, Northampton CountyProposed Proposed, no permit applications receivedVerdantas / Prologis
West Hazleton Data Center West Hazleton, Luzerne CountyProposed Proposed, no permit applications receivedOne Trinity Real Estate
Zediker Station Data Center South Strabane Township, Washington CountyProposed Proposed, no permit applications receivedCNX
Lancaster AI Hub West Lancaster, Lancaster CountyProposed Waiting on permits Permits under reviewChirisa Technology Parks (CoreWeave)100The Pennsylvania DEP received the project's first permit application on September 25, 2026; its tracker lists the project as permits under review (3 permits: 2 pending, 1 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source September 25, 2026
Aligned PIT-01 (Project Phoenix) Shippingport, Beaver CountyBeing built Permits under reviewAligned Data Centers2,000Shippingport Industrial Park site is adjacent to Shippingport Power Station, a former coal power plant being redeveloped into natural gas energy campus datacenterdynamics.com (opens in a new tab) trade press reported September 17, 2026
Newport Ridge Data Center Newport Township, Luzerne CountyProposed Proposed, no permit applications receivedNewport Ridge LLCNewport Township issued zoning permits for 15 closed loop data center buildings powered by three natural gas generation facilities, with seven sited in the mixed use zone and eight in the industrial zone. citizensvoice.com (opens in a new tab) news outlet September 14, 2026
Smithfield Gateway Project Smithfield Township, Monroe CountyProposed Proposed, no permit applications receivedDEPG Moiser Assoc. LP / DEPG of Shawnee II Assoc. LPRevised documents submitted include traffic statements, acoustical evaluations of sound emissions, and emergency response plans. lehighvalleylive.com (opens in a new tab) local outlet reported September 7, 2026
Homer City Energy Campus Redevelopment Homer City, Indiana CountyBeing built Proposed, no permit applications receivedHomer City Redevelopment LLC4,500The Homer City plant redevelopment is now being built by 1,800 contractors and tradespeople. post-gazette.com (opens in a new tab) local outlet September 4, 2026
Scranton Materials Data Center Ransom Township, Lackawanna CountyProposed Proposed, no permit applications receivedMudiita Land Venture LLCMudiita Land Venture LLC purchased 528.6 acres in Ransom Township near Old Forge for a planned hyperscale data center campus, on land also eyed for a pumped storage hydroelectric project. thetimes-tribune.com (opens in a new tab) local outlet September 4, 2026
PAX-1 Data Center Middlesex Township, Cumberland CountyProposed Waiting on permits Permits under reviewPAX-1 Developer LLCMiddlesex Township supervisors approved PAX-1 data center development matters. cumberlink.com (opens in a new tab) news outlet September 3, 2026
Amazon Luzerne Data Center (Susquehanna Campus) Salem Township, Luzerne CountyBeing built Phase 1: DEP review complete; Phase 2: permits under reviewAmazon Web ServicesAmazon's data center project in Salem Township is in construction. thecentersquare.com (opens in a new tab) national outlet reported September 1, 2026
Lower Mount Bethel Technology Center Lower Mount Bethel Township, Northampton CountyProposed Proposed, no permit applications receivedPeron DevelopmentTownship authority over data center plans in Northampton County is described as uncertain. lehighvalleylive.com (opens in a new tab) local outlet August 31, 2026
Wildcat Ridge Data Center Campus Archbald, Lackawanna CountyProposed Proposed, no permit applications receivedPine Line IncPPL completed a land deal in Archbald to pave the way for massive data center power plants. thetimes-tribune.com (opens in a new tab) local outlet August 30, 2026
River Pointe Data Center Upper Mount Bethel Township, Northampton CountyProposed Proposed, no permit applications receivedSlate Belt Holdings LLC (Talen Energy)The proposed data center campus would consist of 23 data center pads, each with a footprint of 201,000 square feet lehighvalleylive.com (opens in a new tab) local outlet reported August 26, 2026
4-3 Salem Township Data Center Salem Township, Luzerne CountyProposed Proposed, no permit applications received4-3 Glen Brook Group3,500A proposed third data center campus in Salem Township encompassing 279 properties and 4,466 acres is undergoing a zoning hearing process that a Luzerne County judge ordered to be redone after residents were locked out of the July 23, 2026 meeting. citizensvoice.com (opens in a new tab) news outlet August 25, 2026
Pittsburgh International Race Complex Data Center (Switch) Big Beaver, Beaver CountyProposed Waiting on permits Permits under reviewWampum I LLC (Switch)Switch filed for local approval to build a three building data center campus on the 384 acre former Pittsburgh International Race Complex site in Big Beaver Borough, Beaver County. post-gazette.com (opens in a new tab) local outlet August 22, 2026
Falls Township Data Center (Keystone Trade Center) Falls Township, Bucks CountyProposed Waiting on permits Phase 1: DEP review complete; Phase 2: permits under reviewAmazon Web ServicesAmazon has been confirmed as the end user in a contentious Pennsylvania data center project. buckscountycouriertimes.com (opens in a new tab) news outlet August 20, 2026
Kline Township Data Center Development Kline Township, Schuylkill CountyProposed Waiting on permits Permits under reviewAmazon Web ServicesAn unnamed technology company is discussing plans for an AI factory data center in Schuylkill County, Pennsylvania amid resident concerns. republicanherald.com (opens in a new tab) news outlet August 15, 2026
Starpointe Data Center Hanover Township, Washington CountyProposed Waiting on permits Permits under reviewPrime Data CentersA controversial data center proposed in a rural Washington County community drew hundreds of residents to a township meeting and was the subject of a public hearing. observer-reporter.com (opens in a new tab) news outlet August 7, 2026
900 Conshohocken Rd. Data Center Plymouth Township, Montgomery CountyProposed Proposed, no permit applications receivedMLP VenturesBrian O'Neill is seeking approval for a 2 million square foot data center facility at 900 Conshohocken Road in Plymouth Township 6abc.com (opens in a new tab) local outlet August 6, 2026
Highridge Data Project Nebius Butler Township, Schuylkill CountyProposed Waiting on permits Permits under reviewNorthPoint DevelopmentA proposed 600 acre data center in Butler Township prompted a special municipal hearing. republicanherald.com (opens in a new tab) news outlet July 29, 2026
QTS Salem Township Salem Township, Luzerne CountyProposed Waiting on permits Permits under reviewQTS Data CentersQTS acquired approximately 1,700 acres for $580 million in Salem Township and received Salem Township approval of road vacations and a final master plan for the data center campus. citizensvoice.com (opens in a new tab) news outlet July 12, 2026
1205 Commonwealth Dr. Data Center (Pennhurst) East Vincent Township, Chester CountyProposed Proposed, no permit applications receivedPennhurst Holdings LLCEast Vincent Township supervisors unanimously rejected a proposed 1.9 million square foot data center at the Pennhurst State School and Hospital property; developer Pennhurst Holdings LLC appealed to the Chester County Court of Common Pleas. thecooldown.com (opens in a new tab) national outlet May 27, 2026
Hunlock Data Center Hunlock Township, Luzerne CountyProposed Proposed, no permit applications receivedCastleton Commodities / UGI Development CompanyCastleton Commodities International LLC expressed interest in building a small data center near Hunlock Creek Energy Center in Luzerne County. thetimes-tribune.com (opens in a new tab) local outlet May 14, 2026
Project Gravity Archbald, Lackawanna CountyProposed Waiting on permits Permits under reviewArchbald 25 Developer LLCProject Gravity is a proposed seven building AI data center complex in Archbald Borough, Lackawanna County, that was removed from Pennsylvania's fast track permitting program due to lack of transparency. paenvironmentdaily.blogspot.com (opens in a new tab) local outlet May 3, 2026
Sharon Data Center Project Sharon, Mercer CountyProposed Waiting on permits Permits under reviewKeel InfrastructureThe Pennsylvania DEP received the project's first permit application on April 28, 2026; its tracker lists the project as permits under review (2 permits: 1 pending, 1 received). gis.dep.pa.gov (opens in a new tab) primary source April 28, 2026
Triboro Industrial Park Data Center Throop, Lackawanna CountyProposed Waiting on permits Permits under reviewTriboro Industrial Park Developer LLCThe Pennsylvania DEP received the project's first permit application on April 28, 2026; its tracker lists the project as permits under review (6 permits: 1 issued, 1 pending, 4 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source April 28, 2026
Project Boson / Highway Auto Data Center Archbald, Lackawanna CountyProposed Waiting on permits Permits under reviewKriger Construction CompanyThe Pennsylvania DEP received the project's first permit application on March 2, 2026; its tracker lists the project as permits under review (6 permits: 1 pending, 1 returned, 4 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source March 2, 2026
Carbon Node East / Panther Creek Nesquehoning, Carbon CountyProposed Waiting on permits Permits under reviewKeel Infrastructure / Bitfarms (Stronghold)The Pennsylvania DEP received the project's first permit application on February 25, 2026; its tracker lists the project as permits under review (5 permits: 3 pending, 2 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source February 25, 2026
Project Atlas South Whitehall Township, Lehigh CountyProposed Waiting on permits Permits under reviewEdged US / CDE AcquisitionsThe Pennsylvania DEP received the project's first permit application on January 28, 2026; its tracker lists the project as permits under review (6 permits: 3 pending, 1 received, 2 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source January 28, 2026
Springdale Data Center Springdale, Allegheny CountyProposed Waiting on permits Permits under reviewAllegheny DC Property Co. LLCThe Pennsylvania DEP received the project's first permit application on December 8, 2025; its tracker lists the project as permits under review (5 permits: 3 issued, 2 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source December 8, 2025
Project Hazelnut Hazle Township, Luzerne CountyProposed Waiting on permits Permits under reviewNorthPoint DevelopmentNorthPoint Development sought approval for 15 data center buildings on land north of Humboldt Industrial Park in Hazle Township standardspeaker.com (opens in a new tab) news outlet November 14, 2025
Lancaster AI Hub East Lancaster, Lancaster CountyProposed Waiting on permits Phase 1: permits under review; Phase 2: proposed, no permit applications receivedChirisa Technology Parks (CoreWeave)200The Pennsylvania DEP received the project's first permit application on May 14, 2025; its tracker lists the project as permits under review (5 permits: 2 issued, 1 pending, 2 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source May 14, 2025
Wyalusing Energy Center Wyalusing Township, Bradford CountyProposed Waiting on permits Permits under reviewKlondike Digital InfrastructureThe Pennsylvania DEP received the project's first permit application on December 27, 2024; its tracker lists the project as permits under review (5 permits: 1 issued, 4 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source December 27, 2024
Project Forge Data Center East Whiteland Township, Chester CountyProposed Waiting on permits Permits under reviewSentinel Green Fig LLC150The Pennsylvania DEP received the project's first permit application on November 1, 2024; its tracker lists the project as permits under review (3 permits: 2 issued, 1 not yet submitted). gis.dep.pa.gov (opens in a new tab) primary source November 1, 2024
365 Data Centers Philadelphia (PH2) Philadelphia, Philadelphia CountyRunning365 Data Centers2.4
Comcast XSDC Data Center North Fayette Township, Allegheny CountyRunningComcast Corporation
DataBank Philadelphia (PHL1) Philadelphia, Philadelphia CountyRunningDataBank3.1
DataBank Pittsburgh (PIT2) North Fayette Township, Allegheny CountyRunningDataBank4
DataBank Pittsburgh Downtown (PIT1) Pittsburgh, Allegheny CountyRunningDataBank4.5
Digital Realty 833 Chestnut Street Philadelphia Data Center Philadelphia, Philadelphia CountyRunningDigital Realty10
Equinix PH1 Philadelphia Philadelphia, Philadelphia CountyRunningEquinix4.8
Flexential Philadelphia Collegeville (PHL01) Upper Providence Township, Montgomery CountyRunningFlexential3.6
H5 Data Centers Philadelphia Philadelphia, Philadelphia CountyRunningH5 Data Centers
H5 Data Centers Pittsburgh Pittsburgh, Allegheny CountyRunningH5 Data Centers
Iron Mountain Western Pennsylvania Data Center (WPA-1) Cherry Township, Butler CountyRunningIron Mountain Data Centers21
TierPoint Allentown TekPark Data Center Upper Macungie Township, Lehigh CountyRunningTierPoint
TierPoint Bethlehem Data Center Bethlehem, Northampton CountyRunningTierPoint
TierPoint Lehigh Valley Data Center Bethlehem, Northampton CountyRunningTierPoint
TierPoint Philadelphia Navy Yard Data Center Philadelphia, Philadelphia CountyRunningTierPoint
TierPoint Valley Forge Data Center Lower Providence Township, Montgomery CountyRunningTierPoint
United Fiber & Data York Data Center York, York CountyRunningUnited Fiber & Data
MLP Ventures King of Prussia Data Center Campus King of Prussia, Montgomery CountyStalled or cancelled In court Proposed, no permit applications receivedMLP VenturesDeveloper withdrew applications for seven proposed data centers in King of Prussia, canceling scheduled zoning hearing. 6abc.com (opens in a new tab) query feed October 20, 2026
TECfusions Keystone Connect AI Data Center New Kensington, Westmoreland CountyRunning DEP review completeTECfusions3,000TECfusions' Building J is live and providing computing power to a tenant, with township permits for work inside the building and a land development plan for its electrical and mechanical upgrades approved on August 5, 2026. keystonenewsroom.com (opens in a new tab) local outlet reported September 8, 2026

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 79 Pennsylvania projects.

Every Pennsylvania record 79 records · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
365 Data Centers Philadelphia (PH2)Philadelphia, PhiladelphiaRunning365 Data Centers2.4the developer's figuresite22026-10-23
Amazon Web Services data center, Center TownshipCenter Township, IndianaProposedAmazon Web Servicessite22026-10-23
Archbald I LLC and Archbald II LLC Data CentersArchbald, LackawannaProposedArchbald I LLC / Archbald II LLCsite22026-10-23
Avison Young data center, Wilkes-BarreWilkes-Barre, LuzerneProposedAvison Youngsite22026-10-23
Breaker Street Data CenterJessup, LackawannaProposedBreaker Street Associates LLCsite22026-10-23
Brewster Land Company LLC data center, Dorrance TownshipDorrance Township, LuzerneProposedBrewster Land Company LLCsite22026-10-23
Comcast XSDC Data CenterNorth Fayette Township, AlleghenyRunningComcast CorporationEPA registry22026-10-23
Corscale Dauphin data centerSwatara Township, DauphinProposedCorscalesite22026-10-23
DataBank Philadelphia (PHL1)Philadelphia, PhiladelphiaRunningDataBank3.1the developer's figuresite22026-10-23
DataBank Pittsburgh (PIT2)North Fayette Township, AlleghenyRunningDataBank4the developer's figuresite22026-10-23
DataBank Pittsburgh Downtown (PIT1)Pittsburgh, AlleghenyRunningDataBank4.5the developer's figureEPA registry12026-10-23
Dickson City Data CenterDickson City, LackawannaProposedDickson City Development LLCsite22026-10-23
Digital Realty 833 Chestnut Street Philadelphia Data CenterPhiladelphia, PhiladelphiaRunningDigital Realty10the developer's figuresite22026-10-23
Emaus Ave WarehouseAllentown, LehighProposedQuantm LLCsite22026-10-23
Equinix PH1 PhiladelphiaPhiladelphia, PhiladelphiaRunningEquinix4.8the developer's figureEPA registry22026-10-23
Fezzik Energy data center, MidlandMidland, BeaverProposedFezzik Energysite22026-10-23
Flexential Philadelphia Collegeville (PHL01)Upper Providence Township, MontgomeryRunningFlexential3.6the developer's figuresite22026-10-23
Frackville DataNew Castle Township, SchuylkillProposedKRNL Data Centerssite22026-10-23
Gouldsboro Data Center Project / Project GoldClifton Township, LackawannaProposedQuantm Group LLC / 1778 Rich Pike LLCsite22026-10-23
H5 Data Centers PhiladelphiaPhiladelphia, PhiladelphiaRunningH5 Data CentersEPA registry22026-10-23
H5 Data Centers PittsburghPittsburgh, AlleghenyRunningH5 Data Centerssite22026-10-23
Hendricks data center, Penn Forest TownshipPenn Forest Township, CarbonProposedHendrickssite22026-10-23
Iron Mountain Western Pennsylvania Data Center (WPA-1)Cherry Township, ButlerRunningIron Mountain Data Centers21the developer's figuresite22026-10-23
KSR data center, Plains TownshipPlains Township, LuzerneProposedKSRsite22026-10-23
LBT Investment Group LLC data center, Sugarloaf TownshipSugarloaf Township, LuzerneProposedLBT Investment Group LLCsite22026-10-23
Linde Data Center / Forest City Energy Center LLCClinton Township, WayneProposedsite22026-10-23
Londonderry Data CenterLondonderry Township, DauphinProposedLondonderry Data Center Developersite22026-10-23
Mount Carmel Township Data CenterMount Carmel Township, NorthumberlandProposedsite22026-10-23
Nescopeck / Valley View Wood Data CenterNescopeck Township, LuzerneProposedsite22026-10-23
Outrigger Data CenterMifflin Township, ColumbiaProposedsite22026-10-23
Pocono Manor Investors data center, Tobyhanna TownshipTobyhanna Township, MonroeProposedPocono Manor Investorssite22026-10-23
Project Green MountainArchbald, LackawannaProposedGreen Mountain 6 LLCsite22026-10-23
Project HummingbirdMonongahela Township, GreeneProposedInternational Electric Powersite22026-10-23
Project ScottArchbald, LackawannaProposedPatrinely and Provident Real Estatesite22026-10-23
Spring Mountain Quakake TunnelPacker Township, CarbonProposedNorthPoint Developmentsite22026-10-23
Sunnyside Road Data CenterJessup, LackawannaProposedSunnyside Road Associates LLCsite22026-10-23
TierPoint Allentown TekPark Data CenterUpper Macungie Township, LehighRunningTierPointsite12026-10-23
TierPoint Bethlehem Data CenterBethlehem, NorthamptonRunningTierPointsite22026-10-23
TierPoint Lehigh Valley Data CenterBethlehem, NorthamptonRunningTierPointsite22026-10-23
TierPoint Philadelphia Navy Yard Data CenterPhiladelphia, PhiladelphiaRunningTierPointsite12026-10-23
TierPoint Valley Forge Data CenterLower Providence Township, MontgomeryRunningTierPointsite22026-10-23
United Fiber & Data York Data CenterYork, YorkRunningUnited Fiber & DataEPA registry22026-10-23
Verdantas and Prologis data center, Allen TownshipAllen Township, NorthamptonProposedVerdantas / Prologissite22026-10-23
West Hazleton Data CenterWest Hazleton, LuzerneProposedOne Trinity Real Estatesite22026-10-23
Zediker Station Data CenterSouth Strabane Township, WashingtonProposedCNXsite22026-10-23
MLP Ventures King of Prussia Data Center CampusKing of Prussia, MontgomeryStalled or cancelledMLP Venturessite22026-10-23
Lancaster AI Hub WestLancaster, LancasterProposedChirisa Technology Parks (CoreWeave)100the developer's figuresite22026-10-23
Aligned PIT-01 (Project Phoenix)Shippingport, BeaverBeing builtAligned Data Centers2,000the developer's figuresite22026-10-23
Newport Ridge Data CenterNewport Township, LuzerneProposedNewport Ridge LLCsite22026-10-23
TECfusions Keystone Connect AI Data CenterNew Kensington, WestmorelandRunningTECfusions3,000the developer's figuresite22026-10-23
Smithfield Gateway ProjectSmithfield Township, MonroeProposedDEPG Moiser Assoc. LP / DEPG of Shawnee II Assoc. LPsite22026-10-23
Homer City Energy Campus RedevelopmentHomer City, IndianaBeing builtHomer City Redevelopment LLC4,500the developer's figuresite22026-10-23
Scranton Materials Data CenterRansom Township, LackawannaProposedMudiita Land Venture LLCsite22026-10-23
PAX-1 Data CenterMiddlesex Township, CumberlandProposedPAX-1 Developer LLCsite22026-10-23
Amazon Luzerne Data Center (Susquehanna Campus)Salem Township, LuzerneBeing builtAmazon Web Servicessite22026-10-23
Lower Mount Bethel Technology CenterLower Mount Bethel Township, NorthamptonProposedPeron Developmentsite22026-10-23
Wildcat Ridge Data Center CampusArchbald, LackawannaProposedPine Line Incsite12026-10-23
River Pointe Data CenterUpper Mount Bethel Township, NorthamptonProposedSlate Belt Holdings LLC (Talen Energy)site22026-10-23
4-3 Salem Township Data CenterSalem Township, LuzerneProposed4-3 Glen Brook Group3,500the developer's figuresite12026-10-23
Pittsburgh International Race Complex Data Center (Switch)Big Beaver, BeaverProposedWampum I LLC (Switch)site22026-10-23
Falls Township Data Center (Keystone Trade Center)Falls Township, BucksProposedAmazon Web Servicessite12026-10-23
Kline Township Data Center DevelopmentKline Township, SchuylkillProposedAmazon Web Servicessite22026-10-23
Starpointe Data CenterHanover Township, WashingtonProposedPrime Data Centerssite22026-10-23
900 Conshohocken Rd. Data CenterPlymouth Township, MontgomeryProposedMLP Venturessite22026-10-23
Highridge Data Project NebiusButler Township, SchuylkillProposedNorthPoint Developmentsite12026-10-23
QTS Salem TownshipSalem Township, LuzerneProposedQTS Data Centerssite12026-10-23
1205 Commonwealth Dr. Data Center (Pennhurst)East Vincent Township, ChesterProposedPennhurst Holdings LLCsite12026-10-23
Hunlock Data CenterHunlock Township, LuzerneProposedCastleton Commodities / UGI Development Companysite12026-10-23
Project GravityArchbald, LackawannaProposedArchbald 25 Developer LLCsite12026-10-23
Sharon Data Center ProjectSharon, MercerProposedKeel Infrastructuresite22026-10-23
Triboro Industrial Park Data CenterThroop, LackawannaProposedTriboro Industrial Park Developer LLCsite22026-10-23
Project Boson / Highway Auto Data CenterArchbald, LackawannaProposedKriger Construction Companysite22026-10-23
Carbon Node East / Panther CreekNesquehoning, CarbonProposedKeel Infrastructure / Bitfarms (Stronghold)site22026-10-23
Project AtlasSouth Whitehall Township, LehighProposedEdged US / CDE Acquisitionssite22026-10-23
Springdale Data CenterSpringdale, AlleghenyProposedAllegheny DC Property Co. LLCsite22026-10-23
Project HazelnutHazle Township, LuzerneProposedNorthPoint Developmentsite12026-10-23
Lancaster AI Hub EastLancaster, LancasterProposedChirisa Technology Parks (CoreWeave)200the developer's figuresite22026-10-23
Wyalusing Energy CenterWyalusing Township, BradfordProposedKlondike Digital Infrastructuresite22026-10-23
Project Forge Data CenterEast Whiteland Township, ChesterProposedSentinel Green Fig LLC150the developer's figuresite22026-10-23

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every Pennsylvania county (67)

27 of 67 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRulesHow it treats data centers
Lackawanna County42069121
Luzerne County42079123
Philadelphia County4210160
Allegheny County4200350
Northampton County4209550
Montgomery County4209141
Beaver County4200730
Carbon County4202530
Lehigh County4207731
Schuylkill County4210730
Chester County4202920
Dauphin County4204321
Indiana County4206321
Lancaster County4207120
Monroe County4208921
Washington County4212520
Bradford County4201510
Bucks County4201710
Butler County4201910
Columbia County4203710
Cumberland County4204110
Greene County4205910
Mercer County4208510
Northumberland County4209710
Wayne County4212710
Westmoreland County4212911
York County4213310
Berks County4201101case by case
Blair County4201301
Delaware County4204502
Montour County4209301case by case
Union County4211901
Wyoming County4213101case by case

A blank rating cell means no person has set one for the county. A county without a record is listed, not linked.

34 counties with no records yet
  • Adams County
  • Armstrong County
  • Bedford County
  • Cambria County
  • Cameron County
  • Centre County
  • Clarion County
  • Clearfield County
  • Clinton County
  • Crawford County
  • Elk County
  • Erie County
  • Fayette County
  • Forest County
  • Franklin County
  • Fulton County
  • Huntingdon County
  • Jefferson County
  • Juniata County
  • Lawrence County
  • Lebanon County
  • Lycoming County
  • McKean County
  • Mifflin County
  • Perry County
  • Pike County
  • Potter County
  • Snyder County
  • Somerset County
  • Sullivan County
  • Susquehanna County
  • Tioga County
  • Venango County
  • Warren County

The rules in Pennsylvania 24 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
Pennsylvaniastatecase by casePUC established model large load tariff in May 2026 to ensure customers requiring 50 megawatts or more bear the costs they add to electric system. abc27.com (opens in a new tab) local outlet May 1, 202638 acts on this row
Every act on the Pennsylvania row
  1. moratorium

    Pennsylvania House of Representatives voted 202-1 on House Bill 2674 to prohibit data centers from obtaining public utility status.

    mychesco.com (opens in a new tab) news outlet

  2. hearing

    Gov. Josh Shapiro issued an executive order requiring developers to meet stricter commitments before the state reviews their permit applications.

    wtae.com (opens in a new tab) local outlet

  3. statement

    Governor Josh Shapiro announced an executive order requiring data center developers to pay the full cost of all energy needed to power their project while meeting environmental, transparency and community benefit requirements.

    delawareonline.com (opens in a new tab) local outlet

  4. event

    Governor Josh Shapiro issued Executive Order 2026-05 to protect Pennsylvania consumers from data center impacts

    newsweek.com (opens in a new tab) national outlet

  5. event

    Pennsylvania launched a public data center permit tracker operated by the Department of Environmental Protection showing proposed data center projects and their environmental permit status

    newsweek.com (opens in a new tab) national outlet

    Also reported by 1 source
  6. event

    House Bill 2674, sponsored by state Rep. Chris Pielli, D Chester, was approved by the House Consumer Protection, Technology & Utilities Committee and advances to the full House

    mychesco.com (opens in a new tab) news outlet

  7. approval

    Senate Bill 1408 was unanimously approved by the Senate Communications and Technology Committee on September 29, 2026, prohibiting use of non disclosure agreements between data center developers and local governments and state agencies

    news-graphic.com (opens in a new tab) news outlet

    Also reported by 3 sources
  8. event

    On Tuesday, lawmakers in the Pennsylvania House and Senate backed separate proposals related to data centers, including one that would bar non disclosure agreements for public agencies.

    tribdem.com (opens in a new tab) news outlet

  9. rate rule

    The PUC approved a settlement in PPL Electric Utilities' rate case that requires data centers to make an annual contribution to customer assistance programs.

    spotlightpa.org (opens in a new tab) local outlet

  10. moratorium

    Pennsylvania introduced SB 1359 and HB 2533 for three year moratorium and impact studies.

    mashable.com (opens in a new tab) national outlet

  11. statement

    A report commissioned by Pennsylvania utility regulators examined scenarios in which the regional electricity grid would fall short of demands six times per decade on average if new power plants are built over the next 15 years

    penncapital-star.com (opens in a new tab) local outlet

  12. event

    Amazon receives discount on 6% sales and use tax on equipment it has pledged to buy, store or use in Pennsylvania

    politicspa.com (opens in a new tab) local outlet

  13. event

    Pennsylvania has pulled datacenters out of fast track permitting and made state permits conditional on new guardrails

    newsletter.semianalysis.com (opens in a new tab) news outlet

  14. event

    Commission unanimously adopted motion by Vice Chair Kimberly Barrow addressing PJM proposed RBP and Interim Resource Adequacy Service

    paenvironmentdaily.blogspot.com (opens in a new tab) local outlet

    Also reported by 1 source
  15. statement

    Pennsylvania Public Utility Commission released independent analysis warning rapid data center development could impact electricity reliability

    abc27.com (opens in a new tab) local outlet

    Also reported by 5 sources
  16. moratorium adopted

    Pennsylvania Governor Josh Shapiro imposed moratorium on data centers not covering their own power needs

    reuters.com (opens in a new tab) query feed

    Also reported by 1 source
  17. event

    Pennsylvania Public Utility Commission voted 5-0 to establish a Ratemaking Working Group to examine potential changes to utility ratemaking practices

    dailyenergyinsider.com (opens in a new tab) news outlet

    Also reported by 3 sources
  18. event

    Pennsylvania PUC voted unanimously to approve motions for emergency curtailment rule updates and technical conference on data center cost allocation

    utilitydive.com (opens in a new tab) news outlet

    Also reported by 2 sources
  19. event

    Pennsylvania Public Utility Commission voted 5-0 Wednesday to begin updating emergency electric load control rules focusing on customer curtailment order during grid conditions

    local21news.com (opens in a new tab) query feed

    Also reported by 4 sources
  20. moratorium

    Senator Katie Muth introduced a bill calling for a 3 year moratorium on data center development

    dailykos.com (opens in a new tab) query feed

  21. ordinance

    Pennsylvania House passed legislation to codify GRID standards, but Senate did not act

    datacenterfrontier.com (opens in a new tab) trade press

  22. event

    Governor Shapiro issued an executive order affecting data center project scrutiny at local level

    theconversation.com (opens in a new tab) national outlet

  23. event

    Governor Josh Shapiro removed AI data centers from Pennsylvania's fast track program and required local approval, enforceable commitments on power, water and community benefits

    fortune.com (opens in a new tab) national outlet

  24. moratorium

    Stacy Garrity backed a temporary moratorium on new data centers in Pennsylvania

    time.com (opens in a new tab) national outlet

  25. event

    Josh Shapiro revoked fast track approval for new data warehouses in Pennsylvania after previously touting an Amazon data center

    time.com (opens in a new tab) national outlet

  26. event

    Shapiro announced a state portal for feedback on data centers and a map.

    thecentersquare.com (opens in a new tab) query feed

  27. moratorium adopted

    Pennsylvania House passed bill calling for six month moratorium on data center construction

    delcotimes.com (opens in a new tab) news outlet

  28. event

    Pennsylvania Department of Environmental Protection launched a Data Center Permit Tracker on August 18, 2026 at the direction of Governor Josh Shapiro

    wcexaminer.com (opens in a new tab) local outlet

  29. event

    Pennsylvania restricted data center construction

    wsj.com (opens in a new tab) national outlet

  30. event

    Pennsylvania Governor Josh Shapiro issued August 18 executive order creating GRID framework for large data centers

    datacenterfrontier.com (opens in a new tab) trade press

    Also reported by 3 sources
  31. event

    Governor Josh Shapiro signed Executive Order 2026-05 on August 18, 2026

    statecapitallobbyist.com (opens in a new tab) news outlet

    Also reported by 22 sources
  32. event

    Data center projects removed from PA Permit Fast Track Program effective with Executive Order 2026-05

    statecapitallobbyist.com (opens in a new tab) news outlet

    Also reported by 1 source
  33. event

    Gov. Josh Shapiro signed his executive order on data center development last month with promises of the strictest guardrails on development

    broadandliberty.com (opens in a new tab) news outlet

  34. rate rule

    PUC established model large load tariff in May 2026 to ensure customers requiring 50 megawatts or more bear the costs they add to electric system

    abc27.com (opens in a new tab) local outlet

    Also reported by 3 sources
  35. moratorium

    State Sen. Katie Muth introduced a bill this year that would impose a three year moratorium on data center development

    insideclimatenews.org (opens in a new tab) news outlet

  36. event

    Josh Shapiro signed an executive order in summer 2026 imposing tight requirements and restrictions on data centers in Pennsylvania

    wcti12.com (opens in a new tab) local outlet

  37. event

    Shapiro's fast track program introduced in late 2024 was intended to allow state approvals for key projects at the speed of business.

    sungazette.com (opens in a new tab) query feed

  38. event

    Pennsylvania's General Assembly first approved a sales tax exemption for data center developments in 2021 under Governor Tom Wolf

    inquirer.com (opens in a new tab) local outlet

    Also reported by 1 source

Last verified October 20, 2026.

382026-10-20
Wellsborocitycase by caseThe amendment passed unanimously and now requires all data centers to comply with ordinances about light levels, water usage and environmental impact. weny.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Wellsboro row
  1. ordinance

    The amendment passed unanimously and now requires all data centers to comply with ordinances about light levels, water usage and environmental impact

    weny.com (opens in a new tab) local outlet

Last verified September 23, 2026.

12026-09-23
Philadelphiacitynot ratedMayor Cherelle Parker signed an executive order to create a task force to guide data center regulations. whyy.org (opens in a new tab) local outlet Reported Sep 172 acts on this row
Every act on the Philadelphia row
  1. event

    Mayor Cherelle Parker signed an executive order to create a task force to guide data center regulations.

    whyy.org (opens in a new tab) local outlet

  2. moratorium

    Activists rallied at Philadelphia City Hall calling for data center moratorium

    6abc.com (opens in a new tab) query feed

    Also reported by 3 sources

Last verified September 17, 2026.

22026-09-17
North Coventrycitynot ratedNorth Coventry supervisors voted unanimously against a proposal to put a small scale data center at the former Coventry Mall site. pottsmerc.com (opens in a new tab) query feed Reported Sep 91 act on this row
Every act on the North Coventry row
  1. denial

    North Coventry supervisors voted unanimously against a proposal to put a small scale data center at the former Coventry Mall site

    pottsmerc.com (opens in a new tab) query feed

Last verified September 9, 2026.

12026-09-09
Lancastercitynot ratedLancaster Residents Against Glut and Exhaust appealed second data center approval at 216 Greenfield Road after city planning commission granted conditional preliminary approval. thecooldown.com (opens in a new tab) query feed Reported Sep 91 act on this row
Every act on the Lancaster row
  1. litigation

    Lancaster Residents Against Glut and Exhaust appealed second data center approval at 216 Greenfield Road after city planning commission granted conditional preliminary approval

    thecooldown.com (opens in a new tab) query feed

Last verified September 9, 2026.

12026-09-09
Bethlehemcitynot ratedNo dated act on this row yet.2026-08-28
Archbaldcitynot ratedMid Valley School District issued a request for proposals for a baseline environmental sound and noise study of school complex on Underwood Road in Throop. thetimes-tribune.com (opens in a new tab) query feed Reported Sep 61 act on this row
Every act on the Archbald row
  1. event

    Mid Valley School District issued a request for proposals for a baseline environmental sound and noise study of school complex on Underwood Road in Throop.

    thetimes-tribune.com (opens in a new tab) query feed

Last verified September 17, 2026.

12026-09-17
Berks Countycountycase by caseBerks County township adopted ordinance setting limits for future AI data centers. wgal.com (opens in a new tab) local outlet Apr 29, 20261 act on this row
Every act on the Berks County row
  1. ordinance

    Berks County township adopted ordinance setting limits for future AI data centers

    wgal.com (opens in a new tab) local outlet

Last verified April 29, 2026.

12026-04-29
Blair Countycountynot ratedNo dated act on this row yet.2026-09-22
East Buffalo Townshipcitynot ratedNo dated act on this row yet.
Hazle Townshipcitynot ratedHazle Township enacted a municipal moratorium on the data center project. theguardian.com (opens in a new tab) national outlet Reported Oct 194 acts on this row
Every act on the Hazle Township row
  1. moratorium adopted

    Hazle Township enacted a municipal moratorium on the data center project

    theguardian.com (opens in a new tab) national outlet

  2. moratorium adopted

    Hazle Township's government rejected the data center project on zoning grounds and placed a temporary moratorium on data center construction

    breitbart.com (opens in a new tab) national outlet

  3. moratorium adopted

    Hazle Township supervisors passed a 180 day freeze on new data center applications on June 8, 2026, pausing Project Hazelnut while officials rewrite zoning rules

    thecooldown.com (opens in a new tab) national outlet

  4. denial

    Hazle Township Supervisors voted 3-0 on November 14, 2025 to deny land development approval for Project Hazelnut

    standardspeaker.com (opens in a new tab) news outlet

Last verified October 19, 2026.

42026-10-19
Indiana Countycountynot ratedIndiana County Conservation District issued two PAG-02 Stormwater General Permits (PAC320065 and PAC320066) to Homer City Generation LP for AI Data Center/Power Plant Complex in Center and Blacklick Townships, Indiana County. paenvironmentdaily.blogspot.com (opens in a new tab) local outlet Reported Sep 253 acts on this row
Every act on the Indiana County row
  1. event

    Indiana County Conservation District issued two PAG-02 Stormwater General Permits (PAC320065 and PAC320066) to Homer City Generation LP for AI Data Center/Power Plant Complex in Center and Blacklick Townships, Indiana County.

    paenvironmentdaily.blogspot.com (opens in a new tab) local outlet

  2. event

    Tabling decision triggers 90 day investigation period for Planning Commission review

    wccsradio.com (opens in a new tab) query feed

  3. event

    Indiana County Planning Commission voted to table Amazon Web Services application for data centers in Center and Black Lick Townships

    wccsradio.com (opens in a new tab) query feed

Last verified September 25, 2026.

32026-09-25
Lackawanna Countycountynot ratedLackawanna County Commissioners approved contract for AI data center health impact study. paenvironmentdaily.blogspot.com (opens in a new tab) local outlet Reported Sep 171 act on this row
Every act on the Lackawanna County row
  1. event

    Lackawanna County Commissioners approved contract for AI data center health impact study

    paenvironmentdaily.blogspot.com (opens in a new tab) local outlet

Last verified September 17, 2026.

12026-09-17
Lehigh Countycountynot ratedNo dated act on this row yet.2026-09-16
Luzerne Countycountynot ratedNo dated act on this row yet.2026-09-17
Marple Townshipcitycase by caseMarple Township ordinance requires environmental, traffic, and economic impact studies, noise and vibration standards with tighter limits during overnight hours, and proof that adequate water is available without groundwater damage. thecooldown.com (opens in a new tab) national outlet Aug 27, 20262 acts on this row
Every act on the Marple Township row
  1. ordinance

    Marple Township's proposed ordinance prohibits open loop evaporative cooling systems because they use large amounts of water and contribute to urban heat islands

    thecooldown.com (opens in a new tab) national outlet

  2. ordinance

    Marple Township drafted a data center ordinance requiring minimum site size of 2 acres and 1,000 foot setback from other properties, permitting data centers only in light industrial districts

    thecooldown.com (opens in a new tab) national outlet

Last verified August 27, 2026.

22026-08-27
Montour Countycountycase by caseCitizens of Montour County won a rare victory in February when county leaders denied a rezoning application for a data center. insideclimatenews.org (opens in a new tab) news outlet Sep 22, 20261 act on this row
Every act on the Montour County row
  1. denial

    Citizens of Montour County won a rare victory in February when county leaders denied a rezoning application for a data center

    insideclimatenews.org (opens in a new tab) news outlet

Last verified September 22, 2026.

12026-09-22
Newtown Townshipcitynot ratedNewtown Township planning commission recommended an ordinance that would set limits on data center development. audacy.com (opens in a new tab) national outlet Sep 251 act on this row
Every act on the Newtown Township row
  1. ordinance

    Newtown Township planning commission recommended an ordinance that would set limits on data center development

    audacy.com (opens in a new tab) national outlet

Last verified September 25, 2026.

12026-09-25
Salem Townshipcitynot ratedDEP published notice inviting comments on NPDES Water Quality Permit for Amazon Data Services ADS Berwick Data Center in Salem Township, Luzerne County. paenvironmentdaily.blogspot.com (opens in a new tab) local outlet Reported Sep 182 acts on this row
Every act on the Salem Township row
  1. event

    DEP published notice inviting comments on NPDES Water Quality Permit for Amazon Data Services ADS Berwick Data Center in Salem Township, Luzerne County

    paenvironmentdaily.blogspot.com (opens in a new tab) local outlet

  2. litigation

    Planning Commission voted Thursday to recommend township supervisors approve expansion of data center overlay district for third project despite court stay order

    thecentersquare.com (opens in a new tab) national outlet

    Also reported by 1 source

Last verified September 23, 2026.

22026-09-23
Smithfield Townshipcitynot ratedSmithfield Township postponed a conditional use hearing on the data center development that was publicly advertised. lehighvalleylive.com (opens in a new tab) query feed Reported Sep 72 acts on this row
Every act on the Smithfield Township row
  1. hearing

    Smithfield Township postponed a conditional use hearing on the data center development that was publicly advertised.

    lehighvalleylive.com (opens in a new tab) query feed

  2. ordinance

    Supervisors amended the township zoning ordinance last month to strengthen regulations regarding future data center proposals.

    lehighvalleylive.com (opens in a new tab) query feed

Last verified September 7, 2026.

22026-09-07
Swatara Townshipcitynot ratedSwatara Township Board of Commissioners approved community benefits agreements for Highlands West and Highlands East data centers. local21news.com (opens in a new tab) local outlet Reported Oct 111 act on this row
Every act on the Swatara Township row
  1. approval

    Swatara Township Board of Commissioners approved community benefits agreements for Highlands West and Highlands East data centers

    local21news.com (opens in a new tab) local outlet

Last verified October 11, 2026.

12026-10-11
Upper Burrell Townshipcitynot ratedUpper Burrell Township established a 180 day moratorium on data center development in May 2026. keystonenewsroom.com (opens in a new tab) local outlet May 20261 act on this row
Every act on the Upper Burrell Township row
  1. moratorium

    Upper Burrell Township established a 180 day moratorium on data center development in May 2026

    keystonenewsroom.com (opens in a new tab) local outlet

    Also reported by 1 source

Last verified September 8, 2026.

12026-09-08
Upper Merioncitycase by caseUpper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators. northeasttimes.com (opens in a new tab) query feed Sep 13, 20262 acts on this row
Every act on the Upper Merion row
  1. denial

    Upper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators

    northeasttimes.com (opens in a new tab) query feed

    Also reported by 1 source
  2. litigation

    Developer sued Upper Merion Township planning commission and board of supervisors; vote scheduled for Thursday pending court order

    cbsnews.com (opens in a new tab) national outlet

Last verified September 13, 2026.

22026-09-13
Wyoming Countycountycase by caseWyoming County Commissioners approved an amendment to the SALDO on September 8, 2026 to regulate high intensity nonresidential land developments such as data centers, applying to commercial projects 10,000 square feet or larger. wcexaminer.com (opens in a new tab) local outlet Sep 8, 20264 acts on this row
Every act on the Wyoming County row
  1. ordinance

    Wyoming County commissioners voted to formally adopt an amendment to the county's Subdivision and Land Development Ordinance for data center development

    rocket-courier.com (opens in a new tab) news outlet

  2. event

    Amended SALDO takes effect on September 9, 2026.

    wcexaminer.com (opens in a new tab) local outlet

  3. ordinance

    Wyoming County Commissioners approved an amendment to the SALDO on September 8, 2026 to regulate high intensity nonresidential land developments such as data centers, applying to commercial projects 10,000 square feet or larger.

    wcexaminer.com (opens in a new tab) local outlet

  4. event

    Wyoming County Planning Commission voted unanimously on a proposed SALDO amendment to regulate high intensity nonresidential land development such as data centers with a 10,000 square foot threshold.

    wcexaminer.com (opens in a new tab) local outlet

Last verified September 23, 2026.

42026-09-23

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

Pennsylvania laws and the full scorecard

Bills and laws in Pennsylvania

2 signed into law, 44 bills tracked

44 bills tracked in the Pennsylvania legislature, 2 of them signed into law, grouped by where each stands. A row opens its own page; the Pennsylvania laws page has what each law requires.

Signed into law 3

Moving 3

In committee 38, 5 shown here

33 more in committee on the Pennsylvania laws page.

44 bills tracked, 2 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
H.B. 2821 2025-2026 Regular Session In committee 2026-10-02 In general provisions, further providing for definitions; and, in subdivision and land development, providing for local option for high impact data centers.
H.B. 2535 2025-2026 Regular Session Passed its first chamber 2026-09-30 Providing for the public safety regulation of large load users; requiring the submission of emergency operations plans and generalized infrastructure inventories as a condition of occupancy; protecting confidential security information; and providing for enforcement and penalties.
S.B. 1345 2025-2026 Regular Session In committee 2026-09-30 In zoning, providing for optional temporary moratorium on acceptance or consideration of new applications for high impact data centers.
S.B. 1408 2025-2026 Regular Session In committee 2026-09-30 Prohibiting certain nondisclosure agreements between public agencies and data centers.
S.R. 369 2025-2026 Regular Session In committee 2026-09-30 Directing the Legislative Budget and Finance Committee to conduct a study on the future viability of data center technology and facilities.
S.B. 1442 2025-2026 Regular Session In committee 2026-09-25 Prohibiting data centers from being developed or operated by certain foreign entities; and providing for enforcement by Attorney General.
H.R. 630 2025-2026 Regular Session In committee 2026-09-24 Directing the Legislative Budget and Finance Committee to conduct a study on data center decommissioning in Pennsylvania and provide recommendations.
S.B. 1455 2025-2026 Regular Session In committee 2026-09-24 In general provisions relating to government and administration, providing for pre-application procedure for a proposed data center.
S.B. 1459 2025-2026 Regular Session In committee 2026-09-24 Requiring proposed data centers to conduct water usage studies.
S.B. 1460 2025-2026 Regular Session In committee 2026-09-24 In zoning, prohibiting the location of data centers.
S.B. 1461 2025-2026 Regular Session In committee 2026-09-24 In general provisions, further providing for definitions; and, in zoning, providing for hyperscale data centers and public input.
S.B. 1469 2025-2026 Regular Session In committee 2026-09-24 In rates and distribution systems, providing for large load hyperscale data center tariffs.
S.B. 1470 2025-2026 Regular Session In committee 2026-09-24 In water resources planning, providing for water conservation requirements for data centers.
H.B. 2760 2025-2026 Regular Session In committee 2026-09-09 Providing for the protection of water supplies by requiring commercial data centers to restore or replace a polluted or diminutive water supply; and imposing duties on the Department of Environmental Protection.
H.B. 2359 2025-2026 Regular Session In committee 2026-07-10 In computer data center equipment incentive program, further providing for definitions, for application for certification, for eligibility requirements relating to sales and use tax refund program, for notification, for eligibility requirements relating to sales and use tax exemption program and for notification and records.
S.B. 1384 2025-2026 Regular Session In committee 2026-07-10 In tax credit and tax benefit administration, further providing for definitions; in computer data center equipment incentive program, providing for certification prohibition; providing for Governor's Responsible Infrastructure Development certification and standards; and imposing duties.
H.B. 2496 2025-2026 Regular Session In committee 2026-06-30 In general provisions, providing for pause on data center proposals.
H.B. 1667 2025-2026 Regular Session In committee 2026-06-26 In sales and use tax, further providing for exclusions from tax; in gross receipts tax, further providing for imposition of tax and for establishment of revenue-neutral reconciliation; providing for educational tax credits; in manufacturing and investment tax credit, further providing for business firms and for tax credit certificates; repealing provisions relating to Computer Data Center Equipment Incentive Program; in general provisions, providing for data centers; prohibiting the imposition of a tax on gross receipts received from the sale of electric energy; imposing a penalty; and making repeals.
H.B. 2198 2025-2026 Regular Session In committee 2026-06-26 Repealing provisions relating to Computer Data Center Equipment Incentive Program; and, in general provisions, providing for data centers.
H.B. 2650 2025-2026 Regular Session In committee 2026-06-25 In tax credit and tax benefit administration, further providing for definitions; in computer data center equipment incentive program, providing for certification prohibition; providing for Governor's Responsible Infrastructure Development certification and standards; and imposing duties.
S.B. 1344 2025-2026 Regular Session In committee 2026-06-04 Repealing provisions relating to computer data center equipment incentive program; in general provisions, providing for transfer of tax from certain sale of computer data equipment; and establishing a restricted account in the Motor License Fund.
S.B. 1359 2025-2026 Regular Session In committee 2026-06-04 Imposing a Statewide moratorium on hyperscale data center development and permitting; and providing for enforcement.
H.B. 2532 2025-2026 Regular Session In committee 2026-05-27 Repealing provisions relating to computer data center equipment incentive program; in general provisions, providing for transfer of tax from certain sale of computer data equipment; and establishing a restricted account in the Motor License Fund.
H.B. 2533 2025-2026 Regular Session In committee 2026-05-27 In zoning, providing for optional moratorium on filing or consideration of new applications for high impact data centers.
H.B. 2539 2025-2026 Regular Session In committee 2026-05-27 In Computer Data Center Equipment Incentive Program, further providing for application for certification, for eligibility requirements relating to Sales and Use Tax Refund Program and for eligibility requirements relating to Sales and Use Tax Exemption Program.
S.B. 1323 2025-2026 Regular Session In committee 2026-05-20 Providing for the regulation of commercial data centers; imposing duties on the Pennsylvania Public Utility Commission, the Department of Human Services and the Pennsylvania Energy Development Authority; establishing the Data Center Low-Income Home Energy Assistance Program Enhancement Account and the Pennsylvania Energy Independence Account; providing for clean firm energy requirements, contract filing, commission review, disclosure requirements, backup generation standards, curtailment standards and certification and expedited interconnection for commercial data centers bringing incremental clean firm energy resources; and imposing penalties.
H.B. 2515 2025-2026 Regular Session In committee 2026-05-13 Providing for commercial data center transparency regarding energy use, water use and noise pollution; imposing duties on the Department of Environmental Protection, the Department of Transportation and the Office of Attorney General; and imposing civil penalties.
H.B. 2516 2025-2026 Regular Session In committee 2026-05-13 In general provisions, further providing for definitions; in comprehensive plan, providing for comprehensive plan element for commercial data centers; and, in zoning, providing for zoning, commercial data centers and agricultural land protections and for zoning, commercial data centers, approval procedure and minimum standards.
H.B. 2246 2025-2026 Regular Session In committee 2026-05-01 In water resources planning, further providing for State water plan and providing for covered data centers; and promulgating regulations.
H.B. 2150 2025-2026 Regular Session In committee 2026-04-23 Providing for annual reporting of energy consumption and water consumption by data centers; and imposing a penalty.
H.B. 2151 2025-2026 Regular Session In committee 2026-04-23 Providing for data center ordinance assistance.
S.B. 1297 2025-2026 Regular Session In committee 2026-04-23 In Computer Data Center Equipment Incentive Program, further providing for application for certification and for separation of facilities, providing for additional eligibility requirements, further providing for notification, for revocation of certification, for application for certification and for separation of facilities, providing for additional eligibility requirements and further providing for notification and records and for revocation of certification.
H.B. 1834 2025-2026 Regular Session In committee 2026-03-31 Providing for the regulation of commercial data centers; imposing duties on the Pennsylvania Public Utility Commission, the Department of Human Services and the Pennsylvania Energy Development Authority; establishing the Data Center Low-Income Home Energy Assistance Program Enhancement Account and the Pennsylvania Energy Independence Account; providing for clean firm energy requirements, contract filing, commission review, disclosure requirements, backup generation standards, curtailment standards and certification and expedited interconnection for commercial data centers bringing incremental clean firm energy resources; and imposing penalties.
S.B. 724 2025-2026 Regular Session In committee 2026-03-31 Providing for regulation of large load customers and public utilities and for community benefits agreements between large load customers and community-based organizations; establishing the Data Center LIHEAP Enhancement Fund; and imposing duties on the Department of Human Services and the Pennsylvania Public Utility Commission.
H.B. 2153 2025-2026 Regular Session In committee 2026-01-21 In taxation by school districts, further providing for definitions, providing for disposition of data center property tax revenue and further providing for school district tax notices.
S.B. 1114 2025-2026 Regular Session In committee 2025-12-15 In restructuring of electric utility industry, providing for large load customers; and making editorial changes.
H.B. 2061 2025-2026 Regular Session In committee 2025-12-03 In computer data center equipment incentive program, further providing for application for certification and for eligibility requirements.
S.B. 991 2025-2026 Regular Session In committee 2025-09-05 Providing for a permitting process for data center siting; and imposing powers and duties on the Department of Environmental Protection.
S.B. 939 2025-2026 Regular Session In committee 2025-07-14 Establishing the Office of Transformation and Opportunity and the Artificial Intelligence, Data Center and Emerging Technology Regulatory Sandbox Program; and providing for powers and duties of office and for permits for high impact data centers that have their own power.
H.B. 1342 2021-2022 Regular Session Sent to the governor 2022-07-08 In sales and use tax, further providing for definitions, for exclusions from tax and for licenses; in personal income tax, further providing for classes of income and repealing provisions relating to COVID-19 emergency finance and tax provision; in corporate net income tax, further providing for definitions and for imposition of tax; in insurance premiums tax, further providing for imposition of tax and for credits for assessments paid; in vehicle rental tax, further providing for definitions and for vehicle rental tax; in research and development tax credit, further providing for limitation on credits; in entertainment production tax credit, further providing for definitions, for credit for qualified film production expenses, for limitations, for reissuance of film production tax credits and for limitations; in Waterfront Development Tax Credit, further providing for limitations; in City Revitalization and Improvement Zones, further providing for reports, for restrictions and for confidentiality; in Innovate in PA tax credit, further providing for duties; in Neighborhood Improvement Zones, further providing for confidentiality; in Keystone Opportunity Zones, Keystone Opportunity Expansion Zones and Keystone Opportunity Improvement Zones, further providing for extension for new job creation or new capital investment and for additional keystone opportunity expansion zones; providing for airport land development zones and for Pennsylvania child and dependent care enhancement program and for tax credit; in inheritance tax, further providing for transfers not subject to tax; in Public Transportation Assistance Fund, further providing for Public Transportation Assistance Fund; in table game taxes, providing for General Fund deposit; in Computer Data Center Equipment Incentive Program, further providing for definitions, for sales and use tax exemption, for eligibility requirements and for revocation of certification; in general provisions, providing for allocation of tax credits; making transfers; and making related repeals.
H.B. 952 2021-2022 Regular Session Signed 2021-06-30 In sales and use tax, further providing for exclusions from tax; in personal income tax, further providing for classes of income, for withholding tax requirement for nonemployer payors, for information statement for nonemployer payors and for information statement for payees, providing for electronic payment, further providing for requirements concerning returns, notices, records and statements and for additions, penalties and fees; in corporate net income tax, further providing for definitions; in bank and trust company shares tax, further providing for definitions; in realty transfer tax, correcting a scrivener's error relating to credits against tax; in tax credit eligibility, further providing for definitions and for eligibility and providing for application and administration, for assessment, for administering agency training, for broker registration, for tax credit and tax benefit reports, for allocation of tax credits or tax benefits awarded upon appeal and for guidelines; in research and development tax credit, further providing for credit for research and development expenses, for carryover, carryback, refund and assignment of credit and for report to General Assembly; in entertainment production tax credit, further providing for definitions, for credit for qualified film production expenses, for reissuance of film production tax credits, for definitions and for limitations and providing for Pennsylvania live events industry COVID-19 emergency assistance; further providing for application and approval of tax credit; in keystone opportunity zones, keystone opportunity expansion zones and keystone opportunity improvement zones, providing for extension for keystone opportunity expansion zone and further providing for additional keystone opportunity expansion zones; in mixed-use development tax credit, further providing for mixed-use development tax credits; in keystone innovations zones, further providing for keystone innovation zone tax credits and for annual report; in Pennsylvania Housing Tax Credit, further providing for Pennsylvania Housing Tax Credit and for annual report; in table game taxes, repealing provisions relating to expiration; in procedure and administration, further providing for petition for reassessment, for petition procedure and for review by board; in computer data center equipment incentive program, further providing for definitions and providing for applicability and for sales and use tax exemption program; in general provisions, further providing for bad checks, electronic funds transfers not credited upon transmission, additions to tax; imposing duties on the Department of Revenue; and making editorial changes.
S.R. 264 2019-2020 Regular Session Signed 2019-10-29 Recognizing October 29, 2019, as "International Data Center Day" in Pennsylvania.
H.B. 262 2019-2020 Regular Session Sent to the governor 2019-06-28 In sales and use tax, further providing for definitions, for imposition of tax, for exclusions from tax, for licenses, for persons required to make returns, for tax held in trust for the Commonwealth, for assessment, for collection of tax and for crimes and providing for class actions; in personal income tax, further providing for classes of income, providing for contributions for Veterans' Trust Fund, further providing for returns of married individuals, deceased or disabled individuals and fiduciaries and providing for paid tax return preparers and required information on personal income tax returns; in corporate net income tax, further providing for manufacturing innovation and reinvestment deduction; in realty transfer tax, further providing for definitions and for excluded transactions and providing for transfer of tax; in entertainment production tax credit, further providing for definitions, for carryover, carryback and assignment of credit, for limitations, for film production tax credit districts, for definitions, for carryover, carryback and assignment of tax credit and for limitations; in resource enhancement and protection tax credit, further providing for definitions, for Resource Enhancement and Protection Tax Credit Program, for tax credits, for project certification and for annual tax credits; in historic preservation incentive tax credit, further providing for definitions and for tax credit certificates, establishing the Historic Rehabilitation Tax Credit Administration Account, further providing for carryover, carryback and assignment of credit, for pass-through entity, providing for annual report to General Assembly, further providing for application of Internal Revenue Code and for limitation and providing for recapture; in coal refuse energy and reclamation tax credit, further providing for definitions, for application and approval of tax credit and for limitation on tax credits; in tax credit for new jobs, further providing for application process; in city revitalization and improvement zones, further providing for definitions and for restrictions; in manufacturing and investment tax credit, further providing for definitions, for rural growth funds, for requirements, for rural growth fund failure to comply, for reporting obligations, for business firms, for tax credit certificates, for claiming the tax credit, for prohibitions, for revocation of tax credit certificates and for exit; in neighborhood assistance tax credit, further providing for definitions, for public policy and for tax credit; in keystone opportunity zones, keystone opportunity expansion zones and keystone opportunity improvement zones, providing for additional designations; in mixed-use development tax credit, further providing for mixed-use development tax credits; in inheritance tax, further providing for inheritance tax; in table game taxes, reenacting provisions relating to table game taxes and further providing for expiration; in strategic development areas, further providing for sales and use tax and for local sales and use tax; in computer data center equipment incentive program, further providing for limitations; providing for independent public schools; and making a related repeal.
H.B. 2370 2015-2016 Regular Session Signed 2016-11-21 Amending the act of July 13, 2016 (P.L.526, No.84), entitled, "An act amending the act of March 4, 1971 (P.L.6, No.2), entitled 'An act relating to tax reform and State taxation by codifying and enumerating certain subjects of taxation and imposing taxes thereon; providing procedures for the payment, collection, administration and enforcement thereof; providing for tax credits in certain cases; conferring powers and imposing duties upon the Department of Revenue, certain employers, fiduciaries, individuals, persons, corporations and other entities; prescribing crimes, offenses and penalties,' as follows: In sales and use tax: further providing for definitions, for exclusions from tax, for discount and for crimes. In personal income tax: further providing for definitions, for classes of income and for tax withheld; providing for contributions for tuition account programs; and further providing for requirement of withholding tax, for information statement, for time for filing employers' returns, for payment of taxes withheld, for employer's liability for withheld taxes, for employer's failure to withhold, for declarations of estimated tax and for citation authority. In corporate net income tax: further providing for reports and payment of tax; providing for amended reports; and further providing for enforcement, rules and regulations and inquisitorial powers of the department. In bank and trust company shares tax: further providing for imposition of tax, for ascertainment of taxable amount and exclusion of United States obligations, for apportionment and for definitions. In gross receipts tax: further providing for imposition of tax. In realty transfer tax: further providing for definitions, for exempt parties and for excluded transactions. In cigarette tax: further providing for incidence and rate of tax, for floor tax, for stamp to evidence the tax, for commissions on sales and for disposition of certain funds. Imposing a tobacco products tax. In research and development tax credit: further providing for time limitations. In film production tax credit: making editorial changes; further providing for scope of article, definitions and for limitations; providing for reissuance of film production tax credits, for concert rehearsal and tour and for video game production. Establishing the coal refuse energy and reclamation tax credit. Establishing the waterfront development tax credit. In tax credit for new jobs: further providing for definitions and for tax credits. In city revitalization and improvement zones: further providing for definitions and for establishment of contracting authority; providing for contracting authority duties; further providing for approval, for functions of contracting authorities, for qualified businesses, for funds, for reports, for calculation of baseline, for certification, for transfers, for restrictions, for transfer of property, for Commonwealth pledges and for guidelines; and providing for review. Establishing the Manufacturing and Investment Tax Credit. In neighborhood assistance tax credit: further providing for definitions, for tax credit and for grant of tax credit. In neighborhood improvement zones: further providing for definitions and for Neighborhood Improvement Zone Funds; and providing for taxes, for property assessment and for exceptions. In Keystone Special Development Zone Program: further providing for Keystone Special Development Zone tax credit. Providing for keystone opportunity zones, keystone opportunity expansion zones and keystone opportunity improvement zones. Providing for mixed-use development tax credit, the Mixed-use Development Program and Mixed-use Development Program Fund. Providing for Keystone Innovation Zones. In malt beverage tax: further providing for limited tax credits. In inheritance tax: further providing for definitions, for transfers not subject to tax and for deductions not allowed. Providing for table game taxes. In procedure and administration: further providing for petition procedure. Establishing the computer data center equipment incentive program. Providing for a tax amnesty program. Making related repeals. Further providing for preemption of local government tax. Directing the Office of Attorney General to attempt to obtain the consent of participating manufacturers under the Master Settlement Agreement for amendments. Providing for applicability for imposed taxes," further providing for the applicability of realty transfer tax exclusion provisions; and imposing a duty on the Department of Revenue to refund certain realty transfer taxes paid.

44 bills tracked in Pennsylvania; 2025-2026 Regular Session, legislature in session; last checked October 26, 2026. The last check found no bill not already tracked; the 44 tracked bills stand. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. Pennsylvania's members: 15 yea, 1 nay, 1 present or not voting. How each member voted

MemberPartyPosition
Boyle (PA)DNot Voting
BresnahanRYea
Dean (PA)DYea
DeluzioDYea
Evans (PA)DYea
FitzpatrickRYea
HoulahanDYea
Joyce (PA)RYea
Kelly (PA)RYea
Lee (PA)DNay
MackenzieRYea
MeuserRYea
PerryRYea
ReschenthalerRYea
ScanlonDYea
SmuckerRYea
Thompson (PA)RYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. Pennsylvania's members: 1 yea, 1 nay. How each member voted

MemberPartyPosition
Fetterman (D-PA)DNay
McCormick (R-PA)RYea

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What happened

  1. CancelledMLP Ventures King of Prussia Data Center Campus

    Developer withdrew applications for seven proposed data centers in King of Prussia, canceling scheduled zoning hearing.

  2. Moratorium adoptedHazle Township

    Hazle Township enacted a municipal moratorium on the data center project

The full Pennsylvania timeline, year by year

What was said

We have incorporated a lot of the public comment in there
Irvin Kimmel Jr., Commissioner, Somerset County · October 22, 2026 · quoted · Hoodline (opens in a new tab) national outlet
Trump said U.S. communities that don't have data centers will end up being backwards and poor.
Donald Trump, U.S. President · September 24, 2026 · paraphrased · newscentermaine.com (opens in a new tab) local outlet

Every Pennsylvania statement, by speaker (163)

157 more on this page, one per speaker and claim; 163 statements in all
"I know that what I am asking you to do is not popular. But quite frankly we have met the standards under the ordinance and we ask you to approve it."
Edmund Campbell, Land Use Counsel, Cornell Realty Management Archbald Borough Council hearing WVIA News / The Allegheny Front (opens in a new tab) local outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Archbald Borough Council hearing.

Primary source: WVIA News / The Allegheny Front (opens in a new tab).

"I know it is not over but we are going to take the win that it was and we are going to continue on. We know that this is unfortunately a marathon but we live here and we are not going anywhere."
Tamara Misewicz-Healey, Co-Founder, Stop Archbald Data Centers WVIA News / The Allegheny Front (opens in a new tab) local outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Primary source: WVIA News / The Allegheny Front (opens in a new tab).

Hayes says data center impacts can reach beyond the companies building the facilities, potentially affecting neighbors and taxpayers through electricity costs and the availability of public water.

Watershed Sciences and Engineering WITF (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WITF (opens in a new tab).

Dr. Benjamin Hayes, program director of Watershed Sciences and Engineering, says many large data centers use water to cool their equipment.

WITF (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WITF (opens in a new tab).

King says Pennsylvania's energy resources and location near major East Coast cities make it appealing to companies developing AI data centers, and the rapid expansion of AI is contributing to growing energy demand.

Bucknell University WITF (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WITF (opens in a new tab).

Brian R. King, an associate professor of computer science at Bucknell University, says data centers house powerful computers used to train and operate AI models, relying on graphics processing units that require substantial amounts of electricity.

WITF (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WITF (opens in a new tab).

Hayes argues that communities need to consider how multiple data center projects could affect the same watershed or power supply, rather than evaluating each proposal in isolation.

Watershed Sciences and Engineering WITF (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WITF (opens in a new tab).

Governor Shapiro's executive order, called the GRID Executive Order, requires data center developers to make legally binding commitments to self funding energy development, public outreach and transparency, workforce concessions, and environmental requirements.

Governor of Pennsylvania Altoona Mirror (opens in a new tab) news outlet · [Archived Copy] (opens in a new tab)
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Altoona Mirror (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Township solicitor Patrick Fanelli stated that municipalities cannot ban data centers outright because it would be an illegal taking of private property, and that if legal development requirements are met, approval is mandatory.

Taylor Township solicitor Altoona Mirror (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Altoona Mirror (opens in a new tab).

Stacy Garrity said she held five listening sessions across Pennsylvania with local officials and community leaders who said they are not against data centers but want time to update zoning

Republican State Treasurer WTAE (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: WTAE (opens in a new tab).

Stacy Garrity, who earlier this year called for a pause on hyperscale data center development, said real leaders get stakeholders around the table to find out what is needed to protect ratepayers and communities, taking as long as it takes

Republican State Treasurer WGAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: WGAL (opens in a new tab).

Shapiro's approach to Pennsylvania's growing data center industry has shifted. He once celebrated the multimillion dollar investments, but introduced an executive order this summer that tightened restrictions on the AI infrastructure boom.

Pennsylvania Governor WITF (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WITF (opens in a new tab).

Stacy Garrity argued that Shapiro came out against data center development solely in response to public backlash, when he had previously promoted Pennsylvania as a strong candidate for more data centers.

Republican state Treasurer LancasterOnline (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: LancasterOnline (opens in a new tab).

Governor Josh Shapiro defended his executive order approach requiring local community approval before data center permitting, saying if a local community does not want a data center it will not be built and the proposal will not be heard by the Commonwealth for permitting

WGAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: WGAL (opens in a new tab).

Also reported by: Altoona Mirror (opens in a new tab) news outlet .

Governor Josh Shapiro said data center developers must generate their own power at developer expense, protect air and water, earn local community support through local ordinances or resolutions, include local labor, and include local benefits agreements before the Commonwealth considers permits

WTAE (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: WTAE (opens in a new tab).

Paige Cognetti, Scranton Mayor and Pennsylvania 8th Congressional District candidate, stated data centers should pay their own way without tax breaks, not raise electric bills, not poison water, and hire union labor; NDAs should not hide data center information

Scranton Mayor and Democratic congressional candidate Scranton Times-Tribune (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Scranton Times-Tribune (opens in a new tab).

Senator Dick Durbin stated the Ratepayer Protection Act does nothing to establish a requirement that data centers pay for grid upgrades they need

U.S. Senator The Center Square (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: The Center Square (opens in a new tab).

Andy Bater notes Pennsylvania has made progress in regulating data centers including Governor Shapiro's GRID standards and PUC's large load tariff

Pennsylvania Farm Bureau state board director Farm and Dairy (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Farm and Dairy (opens in a new tab).

Pennsylvania Senate Majority Leader Joe Pittman said a statewide moratorium is not a possibility and local governments should have ability to dictate the future of their own communities

Pennsylvania State Senate Majority Leader NBC10 Philadelphia (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NBC10 Philadelphia (opens in a new tab).

Andrea Verobish and Scott Barger represent most of Blair County and part of Huntingdon County

State Rep R-79th District and Scott Barger, State Rep R-80th District wjactv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wjactv.com (opens in a new tab).

Patrick Cicero, attorney at the Pennsylvania Utility Law Project and former state consumer advocate, said the PUC should have been assigning customer assistance costs to all rate classes.

Spotlight PA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Spotlight PA (opens in a new tab).

Josh Shapiro called for strict guardrails on the development and use of advanced technology and signed an executive order imposing tight requirements and restrictions on data centers in Pennsylvania.

Pennsylvania Governor WBFF (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBFF (opens in a new tab).

Also reported by: WCTI (opens in a new tab) local outlet .

Data center regulations would not be introduced until next fall, according to Alex Bomstein of the Clean Air Council.

executive director of the Clean Air Council WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

Stephen DeFrank, Pennsylvania Public Utility Commission Chairman, warned that if more data centers interconnect than expected with no new generation, loss of load events could increase from one every ten years to 13 per year by 2030

WGAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WGAL (opens in a new tab).

Jon Gordon, senior policy director for Advanced Energy United, said PJM is lagging behind other grid operators and that time is running out to get new generation proposed, financed, permitted and constructed

penncapital-star.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: penncapital-star.com (opens in a new tab).

Joe Pittman, Senate Majority Leader, blamed former Governor Tom Wolf's decision to join a regional carbon trading program for the reliability crunch and stated all sources of power should be embraced

Senate Majority Leader (R-Indiana) penncapital-star.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: penncapital-star.com (opens in a new tab).

Steve DeFrank, Pennsylvania Public Utility Commission Chairman, stated that Pennsylvania is at an energy crossroads and that data center development brings significant opportunities but growth cannot come at the expense of reliable and affordable service

penncapital-star.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: penncapital-star.com (opens in a new tab).

DeFrank emphasized need for data center projects to include their own power supplies and for the state to increase overall power generation with a mix of natural gas, nuclear, and green energy

Pennsylvania Public Utility Commission Chairman WGAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WGAL (opens in a new tab).

Abe Silverman, researcher at the Ralph O'Connor Sustainable Energy Institute at Johns Hopkins University, said the grid would be running at the red line

researcher at Ralph O'Connor Sustainable Energy Institute at Johns Hopkins University penncapital-star.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: penncapital-star.com (opens in a new tab).

Molly Parzen, executive director of Conservation Voters of Pennsylvania, said the state must work with PJM Interconnection and federal government to ensure Pennsylvania families do not pay for increased power demand from data centers

WGAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WGAL (opens in a new tab).

Steve DeFrank, Public Utility Commission Chairman, said PJM Interconnection must take urgent action to make sure electricity supply keeps up with demand from data centers

Pennsylvania Public Utility Commission Chairman WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

PPL director of communications said PPL has been warning about data center demand impact on nation's largest power grid for years

Dana Burns WFMZ.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WFMZ.com (opens in a new tab).

Abe Silverman, energy consultant and research scholar at Johns Hopkins University, warned of potential monthly blackouts if data centers continue to connect without new power generation

WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

PUC Chairman DeFrank warned that electricity demand and supply are moving out of balance due to data center development

Pennsylvania Public Utility Commission Chairman witf.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: witf.org (opens in a new tab).

Protesters rallied in Hazleton, Pennsylvania on August 12 calling on Rep. Rob Bresnahan to oppose data center expansion and reject Big Tech contributions.

Hazleton protesters In These Times (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: In These Times (opens in a new tab).

Study warns rapid data center growth could increase consumer electricity costs

Pennsylvania Public Utility Commission WGAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WGAL (opens in a new tab).

Philadelphia has no local zoning laws or regulations governing data center development

WHYY WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

PJM Interconnection identified increased data centers as a cause of rising electricity bills in the region

WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

City officials identified two sites in Philadelphia with potential for AI data centers but no current proposals exist

Philadelphia City officials WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

Anthropic endured an uncomfortable relationship with the Trump administration with the Pentagon trying to label the company's models a security risk and a temporary ban of one of its more advanced models

Associated Press reporting The Philadelphia Inquirer (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Philadelphia Inquirer (opens in a new tab).

Pennsylvania PUC Chairman Steve DeFrank said data center development is putting reliability of electricity supplies in Pennsylvania and nearby regions at risk by causing demand projections to exceed anticipated supply

Pennsylvania Public Utility Commission Chairman The Bradford Era (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Bradford Era (opens in a new tab).

Also reported by: The Center Square (opens in a new tab) national outlet .

PUC released independent analysis warning rapid data center development impacts electricity reliability

Pennsylvania Public Utility Commission Yahoo ABC27 (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Setting: Yahoo.

Primary source: ABC27 (opens in a new tab).

Amazon committed to build 20 billion dollars worth of data centers in Pennsylvania including a facility in Bucks County.

WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

The No Data Centers in Philly campaign will hold a press conference and rally at Philadelphia City Hall at noon on Monday.

WHYY (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WHYY (opens in a new tab).

Shawmar Pitts of Philly Thrive stated absence of regulations amounts to dangerous situation and data centers raise PECO electricity bills pollute air and water and power surveillance systems

managing co-director of Philly Thrive Northeast Times (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Northeast Times (opens in a new tab).

Harvie previously supported tax break for Amazon data center in Falls Township during Bucks County Commissioners vote in December 2020

HuffPost (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: HuffPost (opens in a new tab).

Tony Dastra argued residents should have right to present case to zoning hearing board under Municipalities Planning Code

Lancaster resident The Cool Down (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Cool Down (opens in a new tab).

In Lower Mount Bethel Township in Northampton County eight different elected officials or staff each signed a mutual confidentiality agreement with Talen Energy Supply.

Lower Mount Bethel Township elected officials and staff Williamsport Sun-Gazette (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Williamsport Sun-Gazette (opens in a new tab).

Gov. Josh Shapiro and opponent Stacy Garrity are navigating public opinion around data centers in Pennsylvania gubernatorial race

WBUR reporting WBUR (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBUR (opens in a new tab).

Senator Richard Blumenthal launched a nationwide investigation in March into the use of NDAs and other restrictions that may limit public disclosure of data centers' energy usage, water needs and potential community impacts

United States Senator newsweek.com (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: newsweek.com (opens in a new tab).

Better Path Coalition and No False Climate Solutions PA coalitions oppose hyperscale data center development in Pennsylvania

Daily Kos (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Daily Kos (opens in a new tab).

Deputy Chief of Staff Sam Robinson said the administration wants to respect local decision making in zoning and siting, noting that some parts of Pennsylvania have one house per square mile where data center siting may make sense

Deputy Chief of Staff to Governor Shapiro Yahoo Spotlight PA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Setting: Yahoo.

Primary source: Spotlight PA (opens in a new tab).

Garrity held five listening sessions around Pennsylvania on data center concerns

Republican candidate for Pennsylvania governor WJAC (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WJAC (opens in a new tab).

Stacy Garrity, Republican candidate and current state treasurer, called for a pause on new data center development

Republican candidate for Pennsylvania governor WJAC (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WJAC (opens in a new tab).

Lt. Gov. Austin Davis said the Shapiro Administration has put strict new guardrails in place on data center development

Pennsylvania Lieutenant Governor WJAC (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WJAC (opens in a new tab).

Pennsylvania Gov. Josh Shapiro shifted his stance from generally supporting data centers to placing restrictions after Republican opposition criticism, recently signing an executive order imposing new rules

Pennsylvania Governor Brookings (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Brookings (opens in a new tab).

Senator John Fetterman stated that AI supremacy and energy dominance underpin national security and expressed concern about China's advantages from U.S. overreaction to data center concerns.

U.S. Senator, Pennsylvania WBFF (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WBFF (opens in a new tab).

Democrat Brian Wrightson wants the state to ban all data center developments and implement a moratorium.

Democrat candidate for Pennsylvania state Senate 40th District spotlightpa.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: spotlightpa.org (opens in a new tab).

Republican state Sen. Rosemary Brown announced a plan to introduce a package of bills requiring developers to undergo third party evaluation of water use.

Pennsylvania state Senator (40th District) spotlightpa.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: spotlightpa.org (opens in a new tab).

Rep. Byron Donalds introduced the Protecting Ratepayers Act to ensure private developers bear investment costs of data center developments

Representative CNBC (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: CNBC (opens in a new tab).

Matthew Mehalik, Breathe Project executive director, says data center restriction in Pennsylvania is badly needed

CBS News (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: CBS News (opens in a new tab).

Gov. Josh Shapiro characterized data center developers as predatory

Pennsylvania Governor NBC News (opens in a new tab) national outlet

Position note: Follows June 2025 announcements promoting a 20 billion dollar Amazon data center investment in Pennsylvania, before the August 2026 executive order establishing strict developer power and community rules.

Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NBC News (opens in a new tab).

Shapiro announced data center standards requiring at least 32% clean energy and community benefits agreements in exchange for tax breaks, announced in detail in June 2026

Governor of Pennsylvania Spotlight PA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Spotlight PA (opens in a new tab).

After a joint venture between PPL Corporation and Blackstone to invest $25 billion in data center development in Pennsylvania was announced in July 2025, Bresnahan pointed to potential benefits in NEPA.

U.S. Congressman Scranton Times-Tribune (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Scranton Times-Tribune (opens in a new tab).

"They're going to spend billions of dollars on rebuilding it. It's going to be the largest plant of its kind in the world, I believe. It's going to be great."
Donald Trump, President, Office of the President Public remarks Inquirer.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Public remarks.

Primary source: Inquirer.com (opens in a new tab).

On the November 3, 2026 ballot in Pennsylvania: Governor (3), U.S. House, District 1 (2), U.S. House, District 2 (2), U.S. House, District 3 (2), U.S. House, District 4 (2), U.S. House, District 5 (2), U.S. House, District 6 (2), U.S. House, District 7 (2), U.S. House, District 8 (2), U.S. House, District 9 (2), U.S. House, District 10 (2), U.S. House, District 11 (2), U.S. House, District 12 (2), U.S. House, District 13 (2), U.S. House, District 14 (2), U.S. House, District 15 (2), U.S. House, District 16 (2), U.S. House, District 17 (2); 5 of 37 candidates with a statement on data centers on the record. Every candidate.

Already running in Pennsylvania

18 sites are serving load, 6 of them in Philadelphia County.

See the 18 running sites
  1. 365 Data Centers Philadelphia (PH2) Philadelphia, Philadelphia County Running 2.4 MW
  2. Comcast XSDC Data Center North Fayette Township, Allegheny County Running
  3. DataBank Philadelphia (PHL1) Philadelphia, Philadelphia County Running 3.1 MW
  4. DataBank Pittsburgh (PIT2) North Fayette Township, Allegheny County Running 4 MW
  5. DataBank Pittsburgh Downtown (PIT1) Pittsburgh, Allegheny County Running 4.5 MW
  6. Digital Realty 833 Chestnut Street Philadelphia Data Center Philadelphia, Philadelphia County Running 10 MW
  7. Equinix PH1 Philadelphia Philadelphia, Philadelphia County Running 4.8 MW · Operational since 2011 (15 years)
  8. Flexential Philadelphia Collegeville (PHL01) Upper Providence Township, Montgomery County Running 3.6 MW
  9. H5 Data Centers Philadelphia Philadelphia, Philadelphia County Running
  10. H5 Data Centers Pittsburgh Pittsburgh, Allegheny County Running
  11. Iron Mountain Western Pennsylvania Data Center (WPA-1) Cherry Township, Butler County Running 21 MW
  12. TECfusions Keystone Connect AI Data Center New Kensington, Westmoreland County Running 3 GW
  13. TierPoint Allentown TekPark Data Center Upper Macungie Township, Lehigh County Running
  14. TierPoint Bethlehem Data Center Bethlehem, Northampton County Running
  15. TierPoint Lehigh Valley Data Center Bethlehem, Northampton County Running
  16. TierPoint Philadelphia Navy Yard Data Center Philadelphia, Philadelphia County Running
  17. TierPoint Valley Forge Data Center Lower Providence Township, Montgomery County Running
  18. United Fiber & Data York Data Center York, York County Running

Questions about Pennsylvania data centers

How many data center projects are on the record in Pennsylvania?

79 projects are on the record in Pennsylvania: 38 proposed, 19 waiting on permits, 3 being built, 18 running and 1 cancelled. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in Pennsylvania?

13.5 GW is disclosed across 15 of 79 records: Homer City Energy Campus Redevelopment (4.5 GW, the developer's figure, source (opens in a new tab)), 4-3 Salem Township Data Center (3.5 GW, the developer's figure, source (opens in a new tab)) and TECfusions Keystone Connect AI Data Center (3 GW, the developer's figure, source (opens in a new tab)) and 12 more under Disclosed figures. The other 64 records have not disclosed capacity. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in Pennsylvania say they will use?

Not disclosed. None of the 79 records on file for Pennsylvania states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in Pennsylvania?

61 developers are named on the record: TierPoint (5 records), Amazon Web Services (4 records), DataBank (3 records), NorthPoint Development (3 records), Chirisa Technology Parks (CoreWeave) (2 records), H5 Data Centers (2 records), MLP Ventures (2 records), 365 Data Centers, 4-3 Glen Brook Group, Aligned Data Centers, Allegheny DC Property Co. LLC, Archbald 25 Developer LLC, Archbald I LLC / Archbald II LLC, Avison Young, Breaker Street Associates LLC, Brewster Land Company LLC, Castleton Commodities / UGI Development Company, CNX, Comcast Corporation, Corscale, DEPG Moiser Assoc. LP / DEPG of Shawnee II Assoc. LP, Dickson City Development LLC, Digital Realty, Edged US / CDE Acquisitions, Equinix, Fezzik Energy, Flexential, Green Mountain 6 LLC, Hendricks, Homer City Redevelopment LLC, International Electric Power, Iron Mountain Data Centers, Keel Infrastructure, Keel Infrastructure / Bitfarms (Stronghold), Klondike Digital Infrastructure, Kriger Construction Company, KRNL Data Centers, KSR, LBT Investment Group LLC, Londonderry Data Center Developer, Mudiita Land Venture LLC, Newport Ridge LLC, One Trinity Real Estate, Patrinely and Provident Real Estate, PAX-1 Developer LLC, Pennhurst Holdings LLC, Peron Development, Pine Line Inc, Pocono Manor Investors, Prime Data Centers, QTS Data Centers, Quantm Group LLC / 1778 Rich Pike LLC, Quantm LLC, Sentinel Green Fig LLC, Slate Belt Holdings LLC (Talen Energy), Sunnyside Road Associates LLC, TECfusions, Triboro Industrial Park Developer LLC, United Fiber & Data, Verdantas / Prologis and Wampum I LLC (Switch). 4 records name no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in Pennsylvania have rules about data centers?

23 county and city rows are on the record, 6 of them rated: Wellsboro is rated case by case: The amendment passed unanimously and now requires all data centers to comply with ordinances about light levels, water usage and environmental impact, September 15, 2026, source (opens in a new tab), Berks County is rated case by case: Berks County township adopted ordinance setting limits for future AI data centers, April 29, 2026, source (opens in a new tab) and Marple Township is rated case by case: Marple Township ordinance requires environmental, traffic, and economic impact studies, noise and vibration standards with tighter limits during overnight hours, and proof that adequate water is available without groundwater damage, August 27, 2026, source (opens in a new tab). The state's own row is rated case by case, with 38 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in Pennsylvania, by county?

60 records are not yet running. Lackawanna County: Archbald I LLC and Archbald II LLC Data Centers (proposed), Breaker Street Data Center (proposed), Dickson City Data Center (proposed), Gouldsboro Data Center Project / Project Gold (proposed), Project Boson / Highway Auto Data Center (waiting on permits), Project Gravity (waiting on permits), Project Green Mountain (proposed), Project Scott (proposed), Scranton Materials Data Center (proposed), Sunnyside Road Data Center (proposed), Triboro Industrial Park Data Center (waiting on permits) and Wildcat Ridge Data Center Campus (proposed); Luzerne County: 4-3 Salem Township Data Center (proposed), Amazon Luzerne Data Center (Susquehanna Campus) (being built), Avison Young data center, Wilkes-Barre (proposed), Brewster Land Company LLC data center, Dorrance Township (proposed), Hunlock Data Center (proposed), KSR data center, Plains Township (proposed), LBT Investment Group LLC data center, Sugarloaf Township (proposed), Nescopeck / Valley View Wood Data Center (proposed), Newport Ridge Data Center (proposed), Project Hazelnut (waiting on permits), QTS Salem Township (waiting on permits) and West Hazleton Data Center (proposed); Beaver County: Aligned PIT-01 (Project Phoenix) (being built), Fezzik Energy data center, Midland (proposed) and Pittsburgh International Race Complex Data Center (Switch) (waiting on permits); Carbon County: Carbon Node East / Panther Creek (waiting on permits), Hendricks data center, Penn Forest Township (proposed) and Spring Mountain Quakake Tunnel (proposed); Northampton County: Lower Mount Bethel Technology Center (proposed), River Pointe Data Center (proposed) and Verdantas and Prologis data center, Allen Township (proposed); Schuylkill County: Frackville Data (proposed), Highridge Data Project Nebius (waiting on permits) and Kline Township Data Center Development (waiting on permits); Chester County: 1205 Commonwealth Dr. Data Center (Pennhurst) (proposed) and Project Forge Data Center (waiting on permits); Dauphin County: Corscale Dauphin data center (proposed) and Londonderry Data Center (proposed); Indiana County: Amazon Web Services data center, Center Township (proposed) and Homer City Energy Campus Redevelopment (being built); Lancaster County: Lancaster AI Hub East (waiting on permits) and Lancaster AI Hub West (waiting on permits); Lehigh County: Emaus Ave Warehouse (proposed) and Project Atlas (waiting on permits); Monroe County: Pocono Manor Investors data center, Tobyhanna Township (proposed) and Smithfield Gateway Project (proposed); Washington County: Starpointe Data Center (waiting on permits) and Zediker Station Data Center (proposed); Allegheny County: Springdale Data Center (waiting on permits); Bradford County: Wyalusing Energy Center (waiting on permits); Bucks County: Falls Township Data Center (Keystone Trade Center) (waiting on permits); Columbia County: Outrigger Data Center (proposed); Cumberland County: PAX-1 Data Center (waiting on permits); Greene County: Project Hummingbird (proposed); Mercer County: Sharon Data Center Project (waiting on permits); Montgomery County: 900 Conshohocken Rd. Data Center (proposed); Northumberland County: Mount Carmel Township Data Center (proposed); and Wayne County: Linde Data Center / Forest City Energy Center LLC (proposed). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of Pennsylvania itself decided?

2 state laws are on the record: H.B. 952 (signed, June 30, 2021, source (opens in a new tab)) and H.B. 2370 (signed, November 21, 2016, source (opens in a new tab)). The state's own scorecard row carries 38 dated acts, the newest October 20, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

13.5 GW power

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power13.5 GW156415 the developer's figure
Water, stated per day079
Water, stated per year079
Permanent jobs079
Tax each year079

A blank cell means no record in Pennsylvania disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power13.5 GW156415 the developer's figure
Water, stated per day079
Water, stated per year079
Permanent jobs079
Tax each year079

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 79 tracked facilities in Pennsylvania are for.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use7913.5 GW

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

MethodFacilitiesShare of facilities
Closed loop liquid11%
No stated cooling type7899%

79 facilities in Pennsylvania. A facility carries one cooling method; nothing here is estimated.

Sources read for Pennsylvania

22 sources

22 sources are read for Pennsylvania:

Newspapers
Pittsburgh Post-Gazette, The Philadelphia Inquirer
Public broadcaster
WHYY
Economic development
PA Department of Community and Economic Development
Official
Pennsylvania DEP Data Center Permit Tracker
Search feeds
17 news searches
Every feed, with its kind and tier

What the monitor reads for Pennsylvania: feeds every four hours, pages daily.

Public broadcaster

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Pennsylvania", https://datacenterrecord.org/states/pa, updated October 23, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in Pennsylvania", https://datacenterrecord.org/states/pa. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
PA
Rating of the state's own row
Case by case
Count by status
proposed 38, waiting on permits 19, being built 3, running 18, cancelled 1
Located records
79 located, 0 at a centroid, 0 without coordinates

Researcher view · Pennsylvania · 79 data center sites, 22 buildings where disclosed, 24 rule rows, 44 bills · basis and source tier on every row · verified October 23, 2026

Download CSV JSON GeoJSON