Reported Built from one source

Homer City Plant Redevelopment

The Homer City plant redevelopment is now being built by 1,800 contractors and tradespeople. It is reported; the record holds no sourced date for when it reached that stage.

How much power it needs, how much water it would use and who would use it have not been disclosed.

Last verified · 4 sources, 0 primary · A skeleton record: built from one source, not yet reviewed in depth by a person. · How to read this page

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Land
3,200 acres
third party estimate [2]
Power it would draw
Not disclosed
Water
Not disclosed
Reported by others: 25,000,000 gallons per day (Input Fort Wayne). Their figure, not the record's.
Who leads it
Not disclosed
Who would use it
Not disclosed
Jobs once it runs
Not disclosed
Tax each year
Not disclosed
Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs Not disclosed
How much water it would use Not disclosed
How loud it would be Not disclosed
Jobs once it runs Not disclosed
Tax it would pay each year Not disclosed

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Not disclosed
Who is constructing it Not disclosed
How much land 3,200 acres third party estimate [2] goerie.com September 25, 2026
Where its power comes from Not disclosed
Grid connection Not disclosed
How it is cooled Not disclosed

How much water it would use, also reported: 25,000,000 gallons per day, 2026 (Input Fort Wayne: Plans to supply up to 25 million gallons of water per day to Lebanon and LEAP from White River watershed) .

Jobs once it runs, also reported: 1,500 to 2,000 jobs, 2026 (WCCS AM1160 & 101.1FM: AWS stated proposed data centers would generate between 1500 and 2000 jobs) .

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water useA state water right filing or a water supply agreement.
  • Who would use itA lease announcement or a tenant named in a filing.
  • Power the campus would drawA utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind itA land record, a zoning application or a company's own announcement.
  • Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Indiana County and Homer City about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Indiana County case by case Indiana County Conservation District issued two PAG-02 Stormwater General Permits (PAC320065 and PAC320066) to Homer City Generation LP for AI Data Center/Power Plant Complex in Center and Blacklick Townships, Indiana County. paenvironmentdaily.blogspot.com
Indiana County case by case Tabling decision triggers 90 day investigation period for Planning Commission review wccsradio.com
Indiana County case by case Indiana County Planning Commission voted to table Amazon Web Services application for data centers in Center and Black Lick Townships wccsradio.com

What happened

No dated entry is on the record yet.

10 corrections to this record

Every correction, with its reason
  1. · the status of a projects row

    The stage was set by timeline entries that were returned to draft on 2026-09-17 (they had been published onto the record while it was still a draft skeleton). With no published entry behind it the record reads rumored until one is approved. The old and new text.

  2. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  3. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  4. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  5. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  6. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  7. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  8. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  9. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  10. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

Every correction on the record is on the corrections page.

What was said

Mary Nelson, Erie resident, calls for local oversight and complete transparency on data center development
Mary Nelson, letter writer · September 18, 2026 · paraphrased · Erie Times-News local outlet

Every statement about data centers in Pennsylvania, by speaker

The site

Where in Indiana County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.

  • This record: Proposed, ringed
  • data center
  • Dashed edge: the exact site is not in the public record
  • Smaller pins: 19 other published records in Pennsylvania
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

Where
Homer City, Indiana County, Pennsylvania
How exactly it is located
County level, the county seat
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
Nearest records are not computed for a record placed at a county seat.

Comparisons

3 metrics with more than one figure

Every figure on the record for the same thing, the record's own or the document's first, each with who gave it, its date and its basis.

Project footprint

1 figure, 1 source
1,000,000 to 1,500,000 gallons per acreReported

dailyjournal.net, Sep 16, 2026

Show each source's words
  • 1,000,000 to 1,500,000 gallons per acre, dailyjournal.net: Functioning wetland can hold 1 to 1.5 million gallons of water per acre

Permanent jobs

1 figure, 1 source
1,500 to 2,000 jobsReported

WCCS AM1160 & 101.1FM, Sep 10, 2026

Show each source's words
  • 1,500 to 2,000 jobs, WCCS AM1160 & 101.1FM: AWS stated proposed data centers would generate between 1500 and 2000 jobs

Water a day

1 figure, 1 source
25,000,000 gallons per dayReported

Input Fort Wayne, Aug 29, 2026

Show each source's words
  • 25,000,000 gallons per day, Input Fort Wayne: Plans to supply up to 25 million gallons of water per day to Lebanon and LEAP from White River watershed

Questions about this project

7 questions answered from the record

Answered from the rows on this page.

How big is Homer City Plant Redevelopment?

The record has one measure of its size: 3,200 acres (third party estimate, source). Its power capacity is not disclosed.

Who is building Homer City Plant Redevelopment?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

Who will use Homer City Plant Redevelopment?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Homer City Plant Redevelopment say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Homer City Plant Redevelopment stand today?

It is reported; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Homer City or Indiana County decided about it?

Indiana County (rated case by case): Indiana County Conservation District issued two PAG-02 Stormwater General Permits (PAC320065 and PAC320066) to Homer City Generation LP for AI Data Center/Power Plant Complex in Center and Blacklick Townships, Indiana County. (reported September 25, 2026, source); and Indiana County: Tabling decision triggers 90 day investigation period for Planning Commission review (reported September 10, 2026, source). 3 events are on the county's rows; a rule about the area is not a decision about this record.

What is still unknown about Homer City Plant Redevelopment?

Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is building it, who is constructing it, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Homer City plant’s redevelopment now fueled by 1,800 contractors and tradespeople, Pittsburgh Post-Gazette, September 4, 2026, local outlet
  2. Regulate data centers, shale energy to protect people, planet | Letter - Erie Times-News, Erie Times-News, September 18, 2026, local outlet
  3. DEP To Hold Oct. 14 Meeting/Hearing On Major Amendment To Water Quality Permit For Homer City Data Center/Power Plant Complex In Indiana County; Stormwater Permit Issued - PA Environment Digest Blog, PA Environment Digest Blog, September 11, 2026, local outlet
  4. 53 trucks hauling oversized loads to move through Armstrong, Westmoreland and Indiana counties - CBS News, CBS News, September 2, 2026, local outlet

4 sources on file.

Cite this record

Data Center Record, "Homer City Plant Redevelopment", https://datacenterrecord.org/projects/homer-city-plant-redevelopment-pa, last verified September 25, 2026.

Last verified , first recorded . Every correction is logged on the corrections page and under What happened.

Cite this page

Data Center Record, "Homer City Plant Redevelopment", https://datacenterrecord.org/projects/homer-city-plant-redevelopment-pa. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Slug
homer-city-plant-redevelopment-pa
Status value
rumored
Stage
Proposed
Tier
skeleton
Tags
skeleton
Place id
us/pa/indiana-county/homer-city
Coordinates
40.6211, -79.155
Location precision
county
Location source
County seat (Indiana), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location source number
Not disclosed
Location last verified
September 16, 2026
EPA registry id
Not disclosed
Use type values
not_disclosed
Tenancy value
not_disclosed
Cooling type value
not_disclosed
Capacity basis
not_disclosed
Water basis
not_disclosed, gallons_per_day
Acreage basis
third_party_estimate
Interconnection value
not_disclosed
Capacity, if disclosed
Not disclosed
Rating of the county's rows
Case by case
Published
2026-09-04
Last verified
2026-09-25