Data centers in Homer City, Pennsylvania
Homer City has 1 data center on the record; it is being built. No city rule about data centers is on the record for Homer City yet. Indiana County's own decisions are on the Indiana County page.
The data center in Homer City
Every Homer City record 1 record · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Homer City Energy Campus Redevelopment Homer City, Indiana County | Being built Proposed, no permit applications received | Homer City Redevelopment LLC | 4,500 | The Homer City plant redevelopment is now being built by 1,800 contractors and tradespeople. post-gazette.com (opens in a new tab) local outlet September 4, 2026 | the developer's figure | site | 2 | 2026-10-23 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
What happened
-
Broke groundHomer City Energy Campus Redevelopment
Homer City Energy Campus being transformed for data center innovation from brownfield
datacenterfrontier.com (opens in a new tab) trade press
What was said
The AI data center boom is truly the greatest threat to a stable climate that we face today
Governor Shapiro stated his administration counted only five of more than 100 data center proposals statewide with permits to build, describing a Gold Rush atmosphere with developers bullying neighbors.
Mary Nelson, Erie resident, calls for local oversight and complete transparency on data center development
They're going to spend billions of dollars on rebuilding it. It's going to be the largest plant of its kind in the world, I believe. It's going to be great.
The county and nearby counties
Distances run between the centers the Census Bureau gives each place. Every Pennsylvania county.
Disclosed figures
4.5 GW power
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 4.5 GW | 1 | 0 | 1 the developer's figure |
| Water, stated per day | 0 | 1 | ||
| Water, stated per year | 0 | 1 | ||
| Permanent jobs | 0 | 1 | ||
| Tax each year | 0 | 1 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 1 | 4.5 GW |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 1 tracked facility in Homer City is for.
How the facilities are cooled
No source on file states how any of the 1 tracked facility in Homer City is cooled.
About this data
Report a correction · Send a tip about Homer City · The rows here are part of the Pennsylvania export.
Cite this page
Data Center Record, "Data center records in Homer City, Indiana County, Pennsylvania", https://datacenterrecord.org/states/pa/indiana-county/homer-city. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Level
- city
- Census GEOID
- 4235408
- Census geography
- Incorporated place, Homer City borough
- Rating