Homer City Energy Campus Redevelopment, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
1 event, April 17, 2025. Also on the record, under the month each belongs to: 4 statements, 1 figure from another source and 2 dates when source pages were read and verified. The facts, newest first: the record; the place: Pennsylvania.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2025 1 event
-
(source date; the content gives no date of its own)
being built
Homer City Energy Campus being transformed for data center innovation from brownfield [3]
-
Also in July 2025: 1 statement
-
(content date; reported from elsewhere)
Statement · Donald Trump, President
They're going to spend billions of dollars on rebuilding it. It's going to be the largest plant of its kind in the world, I believe. It's going to be great.
Inquirer.com (opens in a new tab) local outlet
-
2026 6 under the months
-
Also in September 2026: 2 statements, 1 figure from another source and 2 dates when source pages were read and verified
-
(source date; the content gives no date of its own)
Entry
Fifty three trucks hauling oversized loads will travel through Armstrong, Westmoreland, and Indiana counties over four months transporting large industrial pieces [7]
-
(content date)
Entry
The Homer City plant redevelopment is now being built by 1,800 contractors and tradespeople. [4]
-
(source date; the content gives no date of its own)
Figure · Tom's Hardware
4.5 GW: AWS data center campus in Homer City Pennsylvania proposed 4.5 GW across 36 buildings without seeking tax incentives Tom's Hardware (opens in a new tab) national outlet
-
(said in the source itself)
Statement · Mary Nelson, letter writer
Mary Nelson, Erie resident, calls for local oversight and complete transparency on data center development Erie Times-News (opens in a new tab) news outlet
-
(said in the source itself)
Statement · Josh Shapiro, Governor of Pennsylvania
Governor Shapiro stated his administration counted only five of more than 100 data center proposals statewide with permits to build, describing a Gold Rush atmosphere with developers bullying neighbors. Creators Syndicate (opens in a new tab) news outlet
-
-
Also in October 2026: 1 statement
-
(content date; reported from elsewhere)
Statement · Alex Bomstein, Advocate
The AI data center boom is truly the greatest threat to a stable climate that we face today
Inquirer.com (opens in a new tab) local outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- being built
- Events on the timeline
- 1
- Under the months
- 7
- Stage changes
- 1
- Decisions
- 0
- Statements
- 4
- Figures
- 1
- Entries and decisions under the months
- 2