Upper Merion has 1 data center on the record; it is proposed. Upper Merion limits new data centers. The latest decision on the record: Upper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators, September 13, 2026. Montgomery County's own decisions are on the Montgomery County page.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
The data center in Upper Merion
Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.
Upper Merion data center
Upper Merion, Montgomery County
Latest, reported August 17, 2026: MLP Ventures proposal includes closed loop water system cbsnews.com national outlet
- Land
- Not disclosed
- Power
- Not disclosed
- Water
- Not disclosed
- Tenant
- Not disclosed
Where
Drag with one finger to move the map, pinch to zoom. Tap a pin for the data center, a county for its rules
1 data center in Upper Merion: proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.
What Upper Merion has decided
1 body, 2 decisions on the recordWhat the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.
Reported: the source's date; the item names no day of its own.
- Upper Merioncity
Upper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators, reported September 13, 2026.
2 acts on this row
- denial
Upper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators
Also reported by 1 source
- WHYY local outlet
- litigation
Developer sued Upper Merion Township planning commission and board of supervisors; vote scheduled for Thursday pending court order
- denial
What happened
-
· Upper Merion
Denial: Upper Merion Township board rejected proposal for five data centers totaling over 4.6 million square feet relying on natural gas turbines and diesel backup generators northeasttimes.com query feed
-
· Upper Merion
Litigation: Developer sued Upper Merion Township planning commission and board of supervisors; vote scheduled for Thursday pending court order cbsnews.com national outlet
-
· Upper Merion data center
Now reported: MLP Ventures proposal includes closed loop water system cbsnews.com national outlet
The county and nearby counties
Disclosed figures
nothing disclosed by 1 record
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Not disclosed | Basis | |
|---|---|---|---|---|---|
| Power | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Water, stated per day | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Water, stated per year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Permanent jobs | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Tax each year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record |
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year | |
|---|---|---|---|---|---|---|
| Not disclosed | 1 | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed: power, water, jobs, tax each year |
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 1 tracked facility in Upper Merion is for.
How the facilities are cooled
No source on file states how any of the 1 tracked facility in Upper Merion is cooled.
Cite this page
Data Center Record, "Data centers in Upper Merion, Montgomery County, Pennsylvania", https://datacenterrecord.org/states/pa/montgomery-county/upper-merion, updated September 25, 2026.
Cite this page
Data Center Record, "Data center records in Upper Merion, Montgomery County, Pennsylvania", https://datacenterrecord.org/states/pa/montgomery-county/upper-merion. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
The rows here are part of the Pennsylvania export.
For researchers
- Place id
- us/pa/montgomery-county/upper-merion
- Level
- city
- Census GEOID
- Not disclosed
- Rating value
- orange
- Scale word
- Restrictive