- United States Reference figure
Statista, Number of data centers worldwide by country (April 2026). data centers in the United States: 4,423 facilities. Facilities counted by Statista for the United States; the counting rule and the underlying list are not published, 2026. statista.com
- United States Reference figure
Cleanview, US Data Center Map (September 2026). data centers in the United States, operating plus planned: 3,436 facilities. Operating facilities plus planned projects on Cleanview's US data center tracker: 1,306 operating and 2,082 planned, 2026. cleanview.co
- Utah Timeline entry
Volition Industries Spanish Fork. This entry recorded the September 1 delay under the status permitting, before the status rule adopted on 2026-09-05, under which a project waiting on an enabling text amendment is proposed. The entry of the same date and source records the same event as proposed. Spanish Fork City Council delayed the Title 15 vote a second time, for two more weeks, and Volition Industries said it may take the project to another community. The record reads waiting on permits from 2026-09-01. fox13now.com, local outlet
- Utah Timeline entry
Volition Industries Spanish Fork. Mayor Mike Mendenhall posted on Facebook that he supports the proposal, citing the tax revenue and jobs the company has described. The record reads waiting on permits from 2026-08-25. ksl.com, local outlet
- Utah Timeline entry
Volition Industries Spanish Fork. After a public hearing of more than six hours, Spanish Fork City Council tabled the Title 15 amendments the project depends on until September 1. The record reads waiting on permits from 2026-08-18. heraldextra.com, local outlet
- Utah Timeline entry
Volition Industries Spanish Fork. Volition Industries held a public open house on the proposal at the Spanish Fork Library. The record reads proposed from 2026-08-14. thecougarchronicle.com, local outlet
- Utah Timeline entry
Volition Industries Spanish Fork. Volition Industries presented a self powered data center at the former Fingerhut warehouse to the Spanish Fork City Council in a work session. The record reads proposed from 2026-04-21. utah.gov, primary source