August 18, 2026
A permanent public ledger of 227 verified actions on the record. Each entry links directly to its underlying primary government document, council minutes, regulatory filing, or corroborated news report.
-
Anniston
City of Anniston adopted Resolution No. 26 R-97 on August 18, 2026 establishing a 12 month temporary moratorium on permitting, development and licensing of data centers.
-
Anniston
Anniston City Council adopted Resolution No. 26 R-97 on August 18, 2026, imposing a 12 month moratorium on data center permitting, development, expansion and licensing.
-
DeKalb County
DeKalb County Commissioners rejected a proposed hyperscale data center in Ellenwood following nearly a year of community opposition while maintaining a countywide moratorium study.
-
Lake County
Lake County Zoning Board of Appeals voted 6 to 0 to recommend a temporary eight month moratorium on data centers in unincorporated county areas on August 18, 2026.
-
Ypsilanti Township
Ypsilanti Board of Trustees unanimously passed a 6 month moratorium on construction of large electric utility expansion to slow data center construction on August 18.
-
Lee County
More than 150 residents attended a Lee County Board of Commissioners meeting on August 18, 2026 to oppose a proposed data center facility on Lower Moncure Road.
-
Nebraska
Governor Jim Pillen appointed 17 members to Nebraska Data Center Task Force to examine impacts of data center growth on water, power and local infrastructure.
-
New Mexico
New Mexico Supreme Court issued a unanimous stay pausing proceedings on Project Jupiter's air quality permit application on August 18, 2026.
-
Pennsylvania
Governor Josh Shapiro signed Executive Order 2026-05 on August 18, 2026, converting the Governor's Responsible Infrastructure Development (GRID) standards into mandatory conditions for Department of Environmental Protection permits and state sales tax exemptions and removing data centers from the Permit Fast Track Program.
-
Pennsylvania
Governor Shapiro signed an executive order on August 18, 2026 limiting data center construction.
-
Pennsylvania
Governor Shapiro signed an executive order requiring data centers applying for permits with the state to comply with his Governor's Responsible Infrastructure Development (GRID) requirements on August 18, 2026.
-
Pennsylvania
Pennsylvania Department of Environmental Protection launched a Data Center Permit Tracker on August 18, 2026 at the direction of Governor Josh Shapiro.
-
Pennsylvania
Pennsylvania Department of Environmental Protection launched a Data Center Permit Tracker on August 18, 2026 at the direction of Gov. Josh Shapiro following his Governor's Responsible Infrastructure Development (GRID) executive order signed the same day, requiring all data centers applying for permits to comply with GRID requirements and showing 23 confirmed data center projects statewide.
-
Pennsylvania
Governor Josh Shapiro signed an executive order on August 18 imposing strictest guardrails on data centers, removing artificial intelligence data centers from permit fast track and requiring local approval before Department of Environmental Protection reviews applications.
-
Pennsylvania
Pennsylvania Department of Environmental Protection launched a Data Center Permit Tracker map on August 18, 2026, at the direction of Governor Josh Shapiro, showing all proposed data center projects that have engaged with the department; it went live the same day Shapiro signed his executive order requiring compliance with the Governor's Responsible Infrastructure Development (GRID) requirements.
-
Pennsylvania
Governor Josh Shapiro signed Executive Order 2026-05 on August 18, 2026.
-
Pennsylvania
Pennsylvania Governor Josh Shapiro issued an executive order on August 18, 2026, requiring a framework that puts consumers before data centers in dampening grid usage and prohibiting data center utility cost pass throughs to ordinary customers.
-
Pennsylvania
Governor Josh Shapiro signed an executive order on Tuesday imposing stricter regulations on data center projects in Pennsylvania and removing them from the PA Permit Fast Track program.
-
El Paso
El Paso City Council voted 8 to 0 on August 18, 2026 to send an official letter to Governor Greg Abbott clarifying that El Paso Electric operates on the Western Interconnection outside ERCOT and requesting regional flexibility on state data center directives.
-
Spanish Fork
After a six hour public hearing, Spanish Fork City Council tabled a vote on Title 15 amendments that would set rules for self powered data centers until September 1.
-
Chesapeake
Chesapeake City Council voted unanimously on August 18, 2026 to approve an amended data center zoning ordinance that eliminates by right data center development citywide, removes the Fentress Airfield overlay allowance, and prohibits groundwater use.
-
Richmond
Community town hall held on August 18, 2026 at Studio Two Three in Richmond focused on data center expansion opposition.
-
Chesapeake
Chesapeake adopted a data center ordinance on August 18 with no noise limit included.
-
Spokane County
Spokane County Board of Commissioners unanimously approved a four month pause on new data center permits on Tuesday.
-
Winnebago County
The Winnebago County Board adopted Ordinance 57-08-2026, a 12 month moratorium on new data center zoning applications in the towns where the county controls zoning (Algoma, Omro, Neenah and Nekimi).
-
Adam Baugh, partner at Withey Morris Baugh PLC, stated the entitlement process for new data centers in Phoenix and neighboring cities is infinitely harder today than a year ago. Said August 18, 2026.
-
Patterson City officials
City officials said the additional time will allow Patterson to examine potential effects on water supplies, energy infrastructure, air quality and noise levels. Said August 18, 2026.
-
Patterson city attorney
Patterson remains in the early stages of determining how it will regulate the developments. Said August 18, 2026.
-
New Castle County Council candidate
Hoover cited study suggesting proposed data centers in New Castle County could raise wholesale electric rate in Delaware by 80 percent. Said August 18, 2026.
-
Dan Cronin, Vice President & Operations Manager, Turner
Turner is advancing work across the campus with interior buildout already underway. Said August 18, 2026.
-
Calvert County Commissioner
Commissioner Catherine M. Grasso asked staff to begin process to revoke zoning for data centers and rescind rezoning that changed land in Lusby to industrial. Said August 18, 2026.
-
Calvert County Commissioner
Commissioner Mike Hart proposed expansion of moratorium to cover other industries beyond data centers. Said August 18, 2026.
-
Democratic candidate for Congress
Democrat William Lawrence has proposed a federal moratorium on data centers to allow time for establishing regulations. Said August 18, 2026.
-
House Speaker Mike Johnson said a broad moratorium against data centers is a dangerous prospect because the US is in a race with China on AI. Said August 18, 2026.
-
Congressman (R-Charlotte)
Tom Barrett, Congressman from Charlotte, Michigan, is drafting legislation to prohibit federal agencies from overriding local control for data center zoning. Said August 18, 2026.
-
Yellowstone County commissioner
Commissioner Mark Morse stated county does not have authority to impose emergency interim zoning. Said August 18, 2026.
-
Montana State Senator
State Senator Ellie Boldman introduced a bill draft request to ban large scale data centers statewide for the 2027 Montana legislature session. Said August 18, 2026.
-
Former North Dakota University System Chancellor Mark Hagerott discussed North Dakota's emerging role in artificial intelligence and data center development. Said August 18, 2026.
-
Governor of Nebraska
Governor Pillen said the task force will ensure county officials have necessary tools, zoning guidelines and policy frameworks to manage data center growth effectively. Said August 18, 2026.
-
Governor
Gov. Jim Pillen announced 17 members to the state's new Data Center Task Force. Said August 18, 2026.
-
Jim Pillen, Governor of Nebraska
Task force membership includes 17 officials including executives from Berkshire Hathaway Energy, Tenaska, OPPD, NPPD, Lincoln Electric System, and county commissioners from multiple jurisdictions. Said August 18, 2026.
-
Governor of Nebraska
Pillen stated task force must balance economic development with protecting state resources including land, electricity and water. Said August 18, 2026.
-
Matthew Viger, a student, stated that AI data centers lower tax values, putting cities in budget crises and decreasing investment ability. Said August 18, 2026.
-
Mayor of Rochester
Mayor Chuck Grassie said no proposals for data centers have been submitted to Rochester but expressed concerns about water usage, energy usage and environmental impacts. Said August 18, 2026.
-
Raymond Wayman, Zoning Board of Approval member, stated ordinance allows city to ask right questions of data center developers. Said August 18, 2026.
-
Governor of Pennsylvania
Governor Josh Shapiro said while there are no AI data centers up and running in Pennsylvania right now, only five have the permits they would need to begin operating. Said August 18, 2026.
-
Governor of Pennsylvania
Governor Josh Shapiro said there are more than 100 data center proposals under discussion in Pennsylvania. Said August 18, 2026.
-
Governor of Pennsylvania
Josh Shapiro stated he announced two data center projects last year that would generate thousands of new jobs and bring in $20 billion in new investment to Pennsylvania. Said August 18, 2026.
-
Pennsylvania Governor
Shapiro previously committed $20 billion from Amazon to build at least two data centers in Bucks and Luzerne Counties. Said August 18, 2026.
-
Governor Shapiro branded more than 100 Pennsylvania data center proposals as mostly speculative. Said August 18, 2026.
-
Josh Shapiro, Pennsylvania Governor
Developers must bring their own power and pay related electricity expenses. Said August 18, 2026.
-
Pennsylvania Governor
Gov. Josh Shapiro characterized data center developers as predatory. Said August 18, 2026.
Position note: Follows June 2025 announcements promoting a 20 billion dollar Amazon data center investment in Pennsylvania, before the August 2026 executive order establishing strict developer power and community rules.
-
Josh Shapiro, Governor of Pennsylvania, stated the state has received more than 100 data center proposals from technology companies. Said August 18, 2026.
-
Josh Shapiro, Pennsylvania Governor
Developers must use increasingly clean power sources. Said August 18, 2026.
-
Josh Shapiro, Pennsylvania Governor
Developers must hire locally and offer robust community benefits agreement. Said August 18, 2026.
-
Governor of Pennsylvania
Gov. Josh Shapiro reversed course on data centers in August, characterizing most proposals as speculative. Said August 18, 2026.
-
Governor of Texas
By August 18, Abbott said about 20 companies agreed to comply with his standards.
-
Unnamed resident
Residents noted that the proposed data center location is in the heart of the town, not on the outskirts. Said August 18, 2026.
-
Spanish Fork residents
Residents expressed concerns over noise pollution, water resource impacts, location over a fault line, and whether the facility would be a test site. Said August 18, 2026.
-
Jeff Chavez, Volition CEO, stated data center developers should reuse existing infrastructure instead of buying thousands of acres. Said August 18, 2026.
-
Utah officials and investors at Beehive Energy Alliance
Workforce shortages, not funding or ideas, may be the real constraint on energy project delivery in Utah. Said August 18, 2026.
-
Mapleton resident identified as Crosby
A resident stated that neighborhoods are not interested in being a test site for Volition's unproven technology. Said August 18, 2026.
-
Volition officials
Volition's plan includes no diesel generation, a dry cooled system, and a noise limit. Said August 18, 2026.
-
Teresa P., Spanish Fork resident, expressed concern that data centers should not be built in residential backyards regardless of need. Said August 18, 2026.
-
Mapleton resident identified as Crosby
Residents expressed concerns that Volition has not provided sufficient data or evidence to support claims of minimal community impact. Said August 18, 2026.
-
Jeff Chavez, CEO, Volition Industries
Facility would generate its own power with natural gas fuel cells, never connect to the grid, use closed loop cooling with a one time 500,000 gal fill and 250,000 gal per year, and request no tax breaks. Said August 18, 2026, Spanish Fork City Council public hearing.
-
Unnamed resident
A resident raised concerns that the data center location is over a fault line and questioned earthquake safety. Said August 18, 2026.
-
Jack Urquhart, Spanish Fork communications manager, explained the municipal code amendment is needed because the developer proposes generating its own power. Said August 18, 2026.
-
Resident Sarah S. pleaded with the council to listen to residents' concerns, not just hear them. Said August 18, 2026.
-
Volition officials stated their data center will not strain local resources due to being self powered, will be in an existing building, and will have reduced emissions and increased property tax revenue. Said August 18, 2026.
-
Volition officials stated their data center will not strain local resources due to being self powered, will have no diesel generation, is dry cooled, and has noise limits. Said August 18, 2026.
-
Unnamed resident
A resident stated that data centers have promised minimal water use then sued for more water access. Said August 18, 2026.
-
Spokane County Commissioner
County Commissioner Chris Jordan said data centers could consume the same energy as one half of the entirety of Spokane County. Said August 18, 2026.
-
Mason Data Center Proposal
A data center proposal in Mason prompted the city to schedule a town hall as new details about the project emerged. The record reads proposed, August 18, 2026.
-
Southeast Raleigh data center
A proposed southeast Raleigh data center was withdrawn following community opposition, though a developer was still pursuing it as of August 21 before the withdrawal was confirmed. The record reads cancelled, August 18, 2026.
-
River Pointe Data Center
Slate Belt Holdings has proposed a data center campus in Upper Mount Bethel Township, with supervisors discussing a draft agreement amid resident opposition. The record reads proposed, August 18, 2026.
-
Volition Industries Spanish Fork
After a public hearing of more than six hours, Spanish Fork City Council tabled the Title 15 amendments the project depends on until September 1. The record reads waiting on permits, August 18, 2026.
-
Westover
Westover approved a 6 month moratorium on data centers.
-
Arizona
Arizona Governor Katie Hobbs secured agreement from lawmakers to impose a three year moratorium on the state's sales tax exemption for data centers.
-
Harrington
Harrington rejected ordinance that would allow data centers in city limits.
-
Marion County
Marion County Board workshop rescheduled to September 21, 2026.
-
Marion County
Marion County commissioners directed staff to draft a 12 month permitting moratorium on data centers.
-
Marion County
Citizens Workshop on Data Centers scheduled for August 24, 2026 in Ocala.
-
Waterloo
City of Waterloo is considering a three month data center moratorium.
-
Iowa
Iowa academics created a tool for localities to weigh data center proposals including water, power, tax, land use, and emergency services.
-
Illinois
Illinois governor's race involves data center regulations as a deciding issue.
-
Illinois
Illinois Governor JB Pritzker halted new sales tax exemptions for data centers until lawmakers impose tougher standards on their operations.
-
Kentucky
Beshear issued a data center executive order.
-
Massachusetts
A Massachusetts initiative petition filed would require electricity safeguards, water system capacity evidence, drought response plan, and two-thirds local voter approval before data center permitting.
-
Maine
Maine legislature passed bill proposing moratorium on new data centers; Governor vetoed.
-
Yellowstone County
Commission scheduled to discuss emergency zoning request at August 27, 2026 meeting in Billings.
-
Yellowstone County
Yellowstone County commissioners agreed to discuss emergency interim zoning ordinance following public meeting on Tuesday, August 18, 2026.
-
Greensboro
Greensboro establishes 180 day data center moratorium.
-
Lee County
Eric Davidson, a newly appointed Republican commissioner, offered a motion to impose a 90 day moratorium on new data centers but withdrew it after County Attorney Whitney Parrish advised commissioners lacked authority to enact a moratorium without following state mandated procedures.
-
Lee County
Lee County Board of Commissioners rejected a resolution urging the North Carolina General Assembly to research and enact legislation for data centers.
-
Kearney
Kearney Planning Commission meeting scheduled for Friday, Aug. 21 to discuss conditional use permit.
-
Nebraska
The executive order authorized the formation of a Data Center Task Force with 17 members to evaluate impacts on water resources, power grids, and local infrastructure.
-
Nebraska
Governor Jim Pillen signed an executive order in July 2026 ending taxpayer subsidies for large scale data centers in Nebraska.
-
Nebraska
Governor Jim Pillen created data center task force with 17 members in July after barring new data centers from receiving tax incentives.
-
New York
New York Governor Kathy Hochul ordered a one year ban on large data centers to give the state time to impose protections for the environment and energy grid.
-
New York
New York Governor Kathy Hochul issued moratorium on data centers for up to one year in July 2026.
-
Oregon
Oregon will be the first jurisdiction in Ohio to bring forth a citizen led petition to limit the size of data centers.
-
Oregon
Oregon voters will decide the fate of large scale data centers in November.
-
Pennsylvania
Pennsylvania restricted data center construction.
-
Pennsylvania
Governor Shapiro stated that if the local community does not approve a data center project, the state will not approve it either, giving veto power to municipalities.
-
Pennsylvania
Governor Shapiro signed an executive order mandating four minimum standards for data center development: companies must pay for their own energy, minimize noise and air pollution and water usage, hire local workers, and give back to communities in negotiated benefit agreements.
-
Pennsylvania
Executive order bars data center developers from using non disclosure agreements.
-
Aberdeen
Aberdeen City Council held first of three meetings on Monday to discuss proposed data center ordinance.
-
Utah
Rep. Colin Jack outlined pending legislation replacing Utah's expiring sales tax exemption for solar/wind business inputs with broader exemption across all energy sources, offset by smaller tax on generated energy.
-
Central Nebraska Today
Phase 1 projected water usage of 455,600 gallons per year. Kearney, Buffalo County, NE, 2026.
Key Figure 455,600 gallons per year -
Associated Construction Publications
Expanded campus will deliver 5 gigawatts of IT capacity across nearly 10 million square feet. Richland Parish, LA, 2026.
Key Figure 5 GW -
ABC15 Arizona
More than 66 gigawatts of data center capacity are under construction in North America. Arizona, statewide, 2026.
Key Figure 66 GW -
Central Nebraska Today
Phase 2 projected water usage of 911,200 gallons per year. Kearney, Buffalo County, NE, 2026.
Key Figure 911,200 gallons per year -
ABC15 Arizona
About 2 gigawatts of data center capacity is underway in Arizona. Arizona, statewide, 2026.
Key Figure 2 GW -
Central Nebraska Today
Phase 3 projected water usage of 2,240,073 gallons per year. Kearney, Buffalo County, NE, 2026.
Key Figure 2,240,073 gallons per year -
Baton Rouge Business Report
Construction expected to support up to 2,250 jobs for local contractors, skilled tradespeople and suppliers. Shreveport, Caddo Parish, and Bossier Parish, LA, 2026.
Key Figure 2,250 jobs -
Missoula Current
In the first quarter of 2026, 75 proposed nationwide data center projects worth approximately $130 billion faced organized opposition. United States, national, 2026.
Key Figure 130,000,000,000 USD -
thelensnola.org
The seven new gas plants would each be rated at 754 megawatts of power, totaling 7,540 MW. Richland Parish, LA, 2026.
Key Figure 754 MW -
YouTube
The proposed data center would generate 250 megawatts of power on site. Spanish Fork, Utah County, UT, 2026.
Key Figure 250 MW -
KSLA
AWS invested $400 million in water infrastructure to support all three campuses. Shreveport, Caddo Parish, LA, 2026.
Key Figure 400,000,000 USD -
Central Nebraska Today
Proposed data center electrical demand will be 368 megawatts. Kearney, Buffalo County, NE, 2026.
Key Figure 368 MW -
ABC15 Arizona
Data center vacancy is at 1 percent nationally for the third year in a row. United States, national, 2026.
Key Figure 1 percent -
TechBuzz News
$18.2 billion spent in, through and around Utah's energy ecosystem from January 2023 through December 2025 across 11 energy subsectors. Salt Lake City, UT, 2026.
Key Figure 18,200,000,000 USD -
Data Center Knowledge
North American data center vacancy remains at 1 percent for the third consecutive year. North America, 2026.
Key Figure 1 percent -
The Cool Down
Massachusetts requires 74,574 signatures to place the initiative on the ballot in November 2028. Massachusetts, statewide, 2026.
Key Figure 74,574 signatures -
KSLA
Total investment in all three Caddo Bossier area data centers is $18 billion. Shreveport, Caddo Parish, LA, 2026.
Key Figure 18,000,000,000 USD -
For High-Density AI, Available Data Center Space May Not Be Usable
JLL reports only a small share of North America's 1% data center vacancy can support high density AI at 140-160 kW per rack with liquid cooling.
-
Data centers, crypto, and tax revisions take center stage in Tuesday primaries - CNBC
CNBC reports on primary elections in Alaska, Florida and Wyoming, with data centers emerging as a campaign issue in Florida's gubernatorial and Senate races.
-
Brookwood residents continue to voice concerns over potential data center - cbs42.com
Brookwood residents voiced concerns over a potential data center project in their area. Community opposition to a data center proposal is being expressed.
-
Westover approves 6-month moratorium on data centers - WBRC 6 News
Westover approved a 6 month moratorium on data centers. The action represents a jurisdictional pause on new data center development.
-
The Agenda: Fayetteville revisits data center rules - Axios
Fayetteville is revisiting its data center zoning rules. The article reports on municipal reconsideration of local data center regulations.
-
Patterson extends data center moratorium through July 2027 - KCRA
Patterson, California City Council voted unanimously to extend data center moratorium through July 15, 2027, citing need to study effects on water, energy, air quality and noise.
-
Major data center bills advance in California despite industry pushback - Canary Media
Major data center bills advanced in California despite industry opposition. The legislation appears to have progressed through the legislative process despite pushback from the data center industry.
-
Harrington shoots down ordinance that would allow data centers in city limits - Delaware Public Media
Harrington city leadership rejected an ordinance that would have permitted data centers within city limits. The decision bars data center development in the jurisdiction.
-
Citizens Workshop on Data Centers Set for Aug. 24 in Ocala - 352today
Marion County citizens workshop on data centers held Aug. 24; county commissioners considering 12 month permitting moratorium.
-
A Black DeKalb Community Fought a Massive Data Center for Nearly a Year and Won - Capital B News - Atlanta
A Black community in DeKalb County opposed a large data center project for nearly a year and successfully blocked it. The community's advocacy resulted in cancellation of the proposed facility.
-
Iowa academics launch tool to help localities weigh proposed data centers - route-fifty.com
Iowa academics launched a decision support tool to help local governments evaluate proposed data center projects on water, power, tax, land use, and emergency services.
-
City of Waterloo considering three-month data center moratorium - KCRG
The City of Waterloo is considering a three month data center moratorium. The city is studying a temporary restriction on data center development.
-
Dubuque to consider six-month data center moratorium, survey shows residents oppose facilities - KCRG
Dubuque considers a six month data center moratorium; a survey shows residents oppose data center facilities in the area. The city is weighing restrictions on data center development.
-
Data center drama, power outage chaos and the Illinois film industry | The Chicago Report - FOX 32 Chicago
A news segment reports on data center drama and power outage chaos alongside Illinois film industry impacts. The exact nature of the discussion cannot be determined from the headline alone.
-
Data center drama, power outage chaos and the Illinois film industry | The Chicago Report - FOX 32 Chicago
Illinois has seen disputes over data centers as well as disruption from power outages.
-
Illinois governor’s race could be decided on data center regulations - The Real Deal
Illinois data center regulations are a significant issue in the governor's race. The outcome will shape policy on data centers statewide.
-
Shapiro issues data center order, takes a swipe at Pittman - Indiana Gazette Online
Governor Shapiro issued an order on data centers. The record notes a policy action by state leadership on the industry.
-
After Johnson County data center lawsuit, petitioners say town ‘retaliated’ - kansascity.com
Petitioners involved in a Johnson County data center lawsuit claim the town retaliated against them. The accusation suggests conflict between local opposition and municipal response.
-
Developer says Ky data center with Anthropic ties meets new limits on environmental, energy impact - Louisville Public Media
A developer of a Kentucky data center with Anthropic ties says the project meets new environmental and energy impact limits. The statement addresses regulatory compliance for the data center.
-
Does Beshear’s data center executive order have ‘teeth’ without state law to back it up? - Kentucky Lantern
Governor Beshear issued a data center executive order. The article questions whether the order has sufficient legal authority without supporting state legislation.
-
Meta hides data center info as it pushes more risks to Entergy’s customers - thelensnola.org
Meta fought transparency demands on job creation and power use; Louisiana PSC overruled judge to kill subpoena; decision expected December 2026.
-
Expanded Meta Data Center Creates More Jobs and Opportunity in Richland Parish, Louisiana - Associated Construction Publications
Turner Construction reports Meta's expanded Richland Parish data center campus now targets 5 gigawatts of IT capacity across nearly 10 million square feet, representing over $50 billion in investment.
-
Amazon announces $6B data center investment in Shreveport - thecentersquare.com
Amazon Web Services announces third data center campus at Shreveport; total region investment grows to $18 billion.
-
Amazon Web Services announces third data center in NW Louisiana, sets community meeting date - shreveportbossieradvocate.com
Amazon Web Services announces third northwest Louisiana data center at Resilient Technology Park in west Shreveport for total $18 billion regional investment.
-
Amazon’s data center network in Northwest Louisiana is going to get bigger - Louisiana Illuminator
Amazon expanded its Northwest Louisiana data center hub on August 18, 2026, adding a third facility in Shreveport and increasing total investment from $12 billion to $18 billion. The expansion adds 210 permanent jobs and increases construction jobs from 1,500 to 2,250.
-
Massachusetts voters could gain the final say on data centers under new petition - The Cool Down
A Massachusetts initiative petition filed would require local voter approval and electricity and water safeguards before data center permitting.
-
Massachusetts needs a data-center strategy, not a series of permits - CommonWealth Beacon
Massachusetts paused data center tax exemption applications on June 25 to develop stronger protections for ratepayers, energy, water, and environment.
-
Calvert County commissioners pass 6-month data center moratorium - FOX 5 DC
Calvert County commissioners unanimously pass six month moratorium on data center applications after Amazon withdrew nuclear plant project.
-
South of the Mason-Dixon Line, Maryland counties scramble to respond to data centers - Pennsylvania Capital-Star
Maryland counties enact data center moratoriums and bans. Harford County became first to impose permanent ban; 13 total counties have temporary moratoriums.
-
Calvert County approves 6-month data center moratorium after Amazon pullout - WJLA
Calvert County commissioners voted unanimously August 18 to approve a six month data center moratorium after Amazon abandoned its project.
-
Six-month moratorium on data centers approved in Calvert - somdnews.com
Calvert County commissioners voted unanimously August 18 to impose a six month moratorium on data center projects, pausing new site plan applications.
-
Johnson warns against data center pause stumping in Michigan swing seat - The Detroit News
House Speaker Johnson opposes federal data center moratorium; warns it would harm U.S. AI competitiveness against China.
-
Mason sets town hall for data center proposal as new details emerge - Lansing State Journal
An unidentified developer proposes a hyperscale data center on 400 acres in Vevay Township Michigan for $1 billion capital investment.
-
North Loop Mpls. residents gather to discuss proposed data center project - MPR News
North Loop residents in Minneapolis gathered to discuss a proposed data center project in their neighborhood. The meeting reflects community response to the project.
-
Commissioners agree to discuss emergency zoning request over proposed Broadview data center - KTVQ
Yellowstone County commissioners agree to discuss emergency interim zoning to pause the proposed 5,000 acre Quantica data center south of Broadview; hearing set for August 27.
-
Viewpoint: Montana should be first to ban data centers - Missoula Current
Montana State Sen. Ellie Boldman announced first bill for 2027 session to ban large scale data centers statewide, citing water and land protection; cited opposition to 75 data center projects worth $130 billion in Q1 2026.
-
Data centers may face new tariffs next year in Duke Energy region in NC - Raleigh News & Observer
Data centers may face new tariffs next year in Duke Energy's North Carolina region. The potential rate change would affect operating data center costs.
-
Commissioners reject attempts to pause data center project - rantnc.com
Lee County, North Carolina commissioners rejected a moratorium motion and a state legislation resolution in response to resident opposition to a proposed data center.
-
Raleigh is the largest city in the state without a data center moratorium. Why? - WRAL
Raleigh is reported as the largest city in North Carolina without a data center moratorium. The report examines why the city has not adopted restrictions like other jurisdictions.
-
Greensboro establishes 180-day data center moratorium - FOX8 WGHP
Greensboro established a 180 day moratorium on data center development. The action pauses new data center approvals in the city.
-
Data centers may face new tariffs next year in Duke Energy region in NC - Raleigh News & Observer
Data centers in the part of North Carolina served by Duke Energy could be subject to new tariffs starting next year.
-
The race to power AI could reshape North Carolina’s grid — and its communities - North Carolina Health News
An article reports on how data center development and AI power demands could reshape North Carolina's electrical grid and communities. The piece examines the broader impacts of data center expansion in the state.
-
Proposed southeast Raleigh data center withdrawn after community opposition - ABC11 News
A proposed southeast Raleigh data center project was withdrawn after community opposition. The project has been cancelled.
-
North Dakota Uniquely Positioned to Lead in AI National Defense, Says Cyber Security Expert - The Flag - AM 1100 and FM 92.3 WZFG
Former North Dakota University System Chancellor says North Dakota is emerging as a leader in artificial intelligence and data center development.
-
Gov. Jim Pillen appoints 17 members to Nebraska Data Center Task Force - Northeast News Channel Nebraska
Governor Jim Pillen appointed 17 members to a Nebraska Data Center Task Force to examine impacts of data center growth on water, power and local infrastructure.
water power -
Data center conditional use permit to be discussed at Kearney Planning Commission meeting - Central Nebraska Today
Kearney Planning Commission will discuss a conditional use permit for Worldwide Mission Critical data center east of the city.
-
Gov. Pillen appoints 17 members to Nebraska Data Center Task Force - KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE
Nebraska Governor Pillen appointed 17 members to a Data Center Task Force to evaluate impact on water, power and infrastructure after signing an order ending taxpayer subsidies for large data centers.
-
Nebraska Gov. Jim Pillen introduces new members to data center task force - KETV
Nebraska Governor Jim Pillen announces 17 members of new data center task force created to balance development with resource protection after barring new tax incentives.
-
Gov. Jim Pillen appoints 17 members to Nebraska Data Center Task Force - Northeast News Channel Nebraska
Gov. Jim Pillen appointed 17 members to Nebraska's Data Center Task Force to examine impacts of data center growth on water, power and local infrastructure.
-
Tight restrictions on data centers in effect after public meeting in Rochester - WMUR
Rochester, New Hampshire ordinance took effect restricting data centers to recycling industrial zone requiring conditional use permit.
-
How New York Is Restricting Data Centers - The New York Times
New York is restricting data centers, according to The New York Times. The specific restrictions and their scope are not detailed in the headline.
-
How New York Is Restricting Data Centers - The New York Times
The state of New York is putting restrictions in place on data centers.
-
Amazon eyes land for suburban county's first hyperscale data center - Cincinnati Enquirer
Amazon is reportedly seeking land in a suburban Ohio county for that county's first hyperscale data center. The project is still in the exploratory stage with no project on the record yet.
-
Data center boom moves into small-town Ohio - Spectrum News
Data center development is expanding into rural Ohio towns. The article reports on the trend of data center projects moving into small communities across the state.
-
Oregon voters to decide fate of large-scale data centers in November - WTVG
Oregon voters will decide the fate of large scale data centers in a November election through a citizen led petition. Oregon would be the first jurisdiction in Ohio to bring forth such a citizen led petition to limit data center size.
-
Shapiro Signs Executive Order Restricting Data Center Development, Giving More Authority to Local Communities - PoliticsPA
Pennsylvania Governor Josh Shapiro signed an executive order implementing strict GRID requirements for data centers, blocking speculative projects and giving local communities more authority over development.
policy -
Gov. Shapiro imposes restrictions on 'speculative' data centers and requires community approval on projects - PhillyVoice
Governor Shapiro signed an executive order on August 18, 2026 to limit AI data center development in Pennsylvania, requiring community approval, local benefits agreements, and sustainability certification, while removing proposals from state fast track permitting.
-
Pennsylvania Governor Josh Shapiro Signs Executive Order Limiting Data Center Construction - WENY News
Governor Josh Shapiro signed an executive order on August 18, 2026 limiting data center construction in Pennsylvania with requirements for community approval and sustainability certification.
-
Pa. Gov. Shapiro signs executive order to 'rein in' data center development - 90.5 WESA
Governor Shapiro signed an executive order requiring data center developers to meet strict GRID standards and obtain local approval before projects proceed.
-
Gov. Shapiro signs executive order putting guardrails on Pennsylvania data centers - FOX 29 Philadelphia
Governor Shapiro signed Executive Order 2026-05 requiring data center developers to meet Responsible Infrastructure Development standards and secure local approval before permitting.
-
Shapiro order: No data center development without meeting his regulatory standards - WVIA Public Media
Governor Shapiro signed an executive order imposing GRID standards on data center developers without backing legislation, requiring local approval and strict environmental standards.
-
Gov. Josh Shapiro expected to sign executive order restricting data center development in Pennsylvania - TribLIVE.com
Governor Shapiro signed an executive order on August 18, 2026, removing data centers from fast track permitting, requiring local approval for state permits, mandating developers bring their own power, and establishing community benefit agreements.
-
PA governor signs executive order on AI data centers: 'nation’s strictest guardrails' - WHP Harrisburg
Governor Shapiro signed an executive order on August 18, 2026, establishing GRID Standards requiring data center developers to bring their own power, hire locally, obtain local approval, and provide community benefits agreements.
-
Shapiro signs executive order banning data center NDA’s, adding development restrictions - The Shenandoah Sentinel
Governor Shapiro signed an executive order banning data center nondisclosure agreements, removing data centers from the Permit Fast Track Program, and requiring local approval before state permits are issued.
-
Shapiro issues executive order putting guardrails on data centers - CBS News
Pennsylvania Governor Shapiro issued an executive order establishing data center guardrails requiring local approvals, benefit agreements, and standards on energy, pollution, water, and hiring.
-
Gov. Josh Shapiro announces new limits on data centers in Pennsylvania - CNN
Gov. Josh Shapiro announces Pennsylvania will no longer prioritize data center permits or grant tax exemptions unless projects meet standards on electricity costs, water use and community engagement.
-
Shapiro Signs Order With ‘Strictest’ Data Center Rules in US (1) - news.bloomberglaw.com
Pennsylvania Governor Josh Shapiro issued executive order with GRID guidelines requiring data centers to secure community approval, prohibit non disclosure agreements, and exclude them from fast track permitting.
-
Shapiro reverses course on data center industry he once embraced - thecentersquare.com
Governor Shapiro has reversed his prior support for the data center industry. The policy shift marks a change in the state's position on data center development.
-
Gov. Shapiro signs data center executive order. Critics say it falls short. - Pennsylvania Capital-Star
Governor Shapiro signed a data center executive order in Pennsylvania. Critics argue the order does not adequately address their concerns about data centers.
-
Gov. Josh Shapiro takes a hard line against ‘predatory’ data center developers in Pennsylvania - NBC News
Governor Josh Shapiro of Pennsylvania took a hard line against data center developers he called predatory. His statement marks a significant policy stance on data center development in the state.
-
Pennsylvania Becomes Latest State to Restrict Data-Center Construction - WSJ
Pennsylvania implemented restrictions on data center construction, joining other states with similar policies. The restriction represents a regulatory change affecting the industry.
-
Data center moratorium for 12 months passes in this SC county - The State
Fairfield County, South Carolina approves 12 month moratorium on data center construction to research permanent restrictions.
-
Aberdeen begins data center ordinance discussions - Yahoo
Aberdeen City Council begins first of three meetings to discuss proposed data center ordinance to guide future facility development.
zoning -
Congressional Candidate Molder Supports Memphis Data Center Moratorium - Radio NWTN
Columbia Mayor Chaz Molder, congressional candidate, supports Memphis City Council data center moratorium and plans to bring similar resolution to Columbia.
-
Judge temporarily blocks data center in Westlake, planned data center in Prosper in spotlight
Judge issued temporary restraining order against Westlake data center; Denton City Council considers moratorium on data center development.
-
Dallas council members seek new rules amid data center boom - Dallas News
Dallas council members seek new rules in response to data center boom, article text unavailable.
-
Utah's Energy Playbook: Beehive Energy Alliance Panelists Break Down Incentives, Capital and the Data Center Debate
Utah officials and energy leaders discuss state incentives and workforce constraints at Beehive Energy Alliance panel, with pending legislation on energy tax exemptions.
-
‘Not interested in being a test site’: Residents oppose potential data center in Spanish Fork
Spanish Fork residents express concerns about Volition data center ordinance at council meeting; council votes to table decision pending written input.
-
Spokane County reverses course, approving four-month data center pause - RANGE Media
Spokane County commissioners unanimously approved a four month moratorium on data center permits after weeks of public criticism about secrecy and environmental concerns.
-
Contested 5-GW Ridgeline Gas, Solar, and Data-Center Complex in West Virginia Clears Site-Control Question - POWER Magazine
A contested 5 gigawatt complex combining a gas plant, solar facility, and data center in West Virginia cleared a site control question. The item reports progress on permitting for a mixed use energy and data center project.
-
Meta Louisiana data center
Interior buildout already underway in first buildings. The record reads being built, reported August 18, 2026.
-
Meta Louisiana data center
Entergy Louisiana filed an application in April 2026 for seven additional gas fired power plants to serve Meta's data center expansion. The record reads being built, reported August 18, 2026.
-
Meta Louisiana data center
Meta's data center in Richland Parish requires a total of 10 new gas plants, including three already approved last year. The record reads being built, reported August 18, 2026.
-
Meta Louisiana data center
The commission's final decision on the seven new gas plants is scheduled for December 16, 2026. The record reads being built, reported August 18, 2026.
-
Meta Louisiana data center
Meta expanded Richland Parish data center from originally announced 2 gigawatts to 5 gigawatts of IT capacity. The record reads being built, reported August 18, 2026.
-
Amazon Web Services Louisiana data centers
Amazon Web Services announced plans in February 2026 to build two data centers in northwest Louisiana. The record reads reported, reported August 18, 2026.
-
Amazon Web Services Louisiana data centers
AWS is adding a third data center at Resilient Technology Park in west Shreveport. The record reads reported, reported August 18, 2026.
-
Amazon Web Services Calvert Cliffs Data Center Proposal
Amazon withdrew plans to build three data centers near Calvert Cliffs Nuclear Plant in Lusby. The record reads cancelled, reported August 18, 2026.
-
Quantica Broadview Data Center
Proposed data center project spans 5,000 acres south of Broadview. The record reads reported, reported August 18, 2026.
-
CyrusOne Lee County Data Center
A proposed 90 megawatt data center is planned near Cumnock on Lower Moncure Road with plans to drill beneath Deep River. The record reads approved, reported August 18, 2026.
-
Google Lincoln Data Center
The task force's first meeting was anticipated in September 2026. The record reads reported, reported August 18, 2026.
-
Kearney Data Center
Existing 100 megawatts of capacity from cryptocurrency operation will be repurposed for first phase. The record reads reported, reported August 18, 2026.
-
Kearney Data Center
Sound Study indicates facility will meet maximum sound level of 55 dBA at property lines. The record reads reported, reported August 18, 2026.
-
Kearney Data Center
Existing cryptocurrency mining facility will be decommissioned following completion of phase one. The record reads reported, reported August 18, 2026.
-
Nebius and DataOne Vineland AI Data Center Campus
Planning Board approved power supply changes to the phase two site plan, which was already under construction; reported August 18. The record reads approved.
-
Volition Industries Spanish Fork
Volition proposes converting an existing 28 acre distribution center into a data center. The record reads proposed, reported August 18, 2026.
-
Volition Industries Spanish Fork
The city's Development Review Committee recommended the ordinance amendment be approved. The record reads waiting on permits, reported August 18, 2026.
-
Volition Industries Spanish Fork
Volition, a Provo based company, applied for an ordinance amendment to change Title 15 of the Spanish Fork Municipal Code to allow Data Centers and Onsite Power Generation Facilities in light industrial zones. The record reads waiting on permits, reported August 18, 2026.
-
Volition Industries Spanish Fork
Volition proposes generating its own power using natural gas rather than connecting to Spanish Fork's electrical grid. The record reads proposed, reported August 18, 2026.
-
Volition Industries Spanish Fork
The proposed data center would be located at the old Fingerhut warehouse at the mouth of Spanish Fork Canyon. The record reads proposed, reported August 18, 2026.
-
Volition Industries Spanish Fork
The Planning Commission recommended the ordinance be modified to limit the amount of power generated and the number of data centers allowed. The record reads waiting on permits, reported August 18, 2026.