August 19, 2026
A permanent public ledger of 280 verified actions on the record. Each entry links directly to its underlying primary government document, council minutes, regulatory filing, or corroborated news report.
-
Grayslake
The village announced on August 19 that it was regretfully postponing the extended public comment session due to safety concerns.
-
Texas
The Texas House State Affairs Committee held an interim hearing on August 19, 2026 examining hyperscale data center load growth, ERCOT 345 kV and 765 kV transmission line planning and residential ratepayer protections.
-
Westlake
The Lakes at Marshall Ridge Homeowners Association filed suit on August 19, 2026 against the Town of Westlake challenging the Circle T Ranch data center approval over municipal notice, noise and transmission impacts.
-
former U.S. Senator
Former U.S. Sen. Doug Jones said voters concerned about data center projects should vote for him because his opponent would allow them without scrutiny. Said August 19, 2026.
-
Huntsville residents
Residents questioned Huntsville leaders about Meta expansion raising concerns about water use, power, jobs, environmental impacts and transparency. Said August 19, 2026.
-
Mayor, Denver
Mayor Johnston stated the process is about putting Denverites over data centers and protecting air, water and quality of life. Said August 19, 2026.
-
U.S. Senator
Collins expressed support for projects at former mill sites with hydropower energy sources. Said August 19, 2026.
-
U.S. Senator
Collins said she shares concern about data centers consuming too much energy and putting stress on energy costs. Said August 19, 2026.
-
U.S. Senator
Sen. Susan Collins said data centers should be handled on a case by case basis. Said August 19, 2026.
-
U.S. Energy Secretary
Energy Secretary Chris Wright said he was unabashedly pro data centers and argued they can expand energy resources and lower electricity rates. Said August 19, 2026.
-
Jake Johnson, DFL Minnesota First Congressional District candidate, demands a moratorium on data center construction. Said August 19, 2026.
-
DFL Minnesota First Congressional District candidate
Johnson says data centers should meet four requirements: keeping bills down, protecting farmland and natural resources, ensuring economic gains in Southern Minnesota, and ending non disclosure agreements. Said August 19, 2026.
-
First District Congressman
Brad Finstad says data center projects should be a community decision, not handed down by Washington. Said August 19, 2026.
-
Yellowstone County Commission Chair Mark Morse said idea of placing moratorium on ballot would need to be discussed at board's discussion meetings before it could move to regular business agenda for a vote. Said August 19, 2026.
-
Attorney John Meyer argued Montana Code 13-28-206 is unconstitutional because it does not facilitate the people's constitutional power of initiative. Said August 19, 2026.
-
Governor Pillen said the task force will help evaluate the impact of data centers on Nebraska's water resources, power grids and local infrastructure. Said August 19, 2026.
-
Nevada Attorney General
On August 19, 2026, Democrat Attorney General Aaron Ford said he will pause new data center tax breaks as governor.
-
Nevada Attorney General and Democratic gubernatorial candidate
Aaron Ford said on August 19, 2026, that he will pause new data center tax breaks as governor to ensure Nevadans get their money's worth.
-
Shawnee city commissioners
City commissioners said the moratorium will give officials time to study potential data center developments and update regulations. Said August 19, 2026.
-
former U.S. labor secretary
Chavez DeRemer says she will focus on investments in energy and data center infrastructure to support AI industry. Said August 19, 2026.
-
Chris Carpenter, IBEW Local 48 political director, told Hillsboro City Council his members had serious concerns with the city's plans for a temporary data center moratorium. Said August 19, 2026.
-
Clackamas County Commissioner
Commissioner Diana Helm said a data center could come into the county and that officials are trying to put a pause on anything happening until they have done their research. Said August 19, 2026.
-
Verrus (implied leadership)
Nelson Abramson spent 20 years at Google including on its data center team, then ran infrastructure at X. Said August 19, 2026.
-
former U.S. labor secretary
Lori Chavez DeRemer accepted newly created role as senior adviser for labor and national infrastructure at Think Big to advocate for data center industry. Said August 19, 2026.
-
Pennsylvania Governor
Executive order mandates data center projects receive all required local approvals before permits are issued. Said August 19, 2026.
-
Matthew Mehalik, Breathe Project executive director, says data center restriction in Pennsylvania is badly needed. Said August 19, 2026.
-
Pennsylvania Governor
Shapiro said Pennsylvania now has the strictest requirements in the entire country for data centers. Said August 19, 2026.
-
Pennsylvania Governor
Gov. Shapiro said: I will not allow Pennsylvanians to be bullied by greedy developers and bulldozed by the lawyers working for these big tech companies. Said August 19, 2026.
-
Memphis
Mayor Young hopes for clarity on data centers and TVA rates at open session. Said August 19, 2026.
-
Governor
In June 2026, Abbott declared he is 'pushing back against these AI data centers that are trying to build in our neighborhoods'. Said August 19, 2026.
-
Governor
Gov. Greg Abbott announced three massive data center projects in Texas in November 2025 alongside Google CEO Sundar Pichai. Said August 19, 2026.
-
U.S. House of Representatives
Rep. Andrea Salinas said every community deserves to drive a hard bargain with data center developers and share in the benefits from data center growth. Said August 19, 2026.
-
Jeff Chavez, CEO of Volition
Volition CEO said their closed loop cooling system would only need about two Utah households' worth of water to fill. Said August 19, 2026.
-
City Community Development Director Dave Anderson stated the city has done more vetting on this amendment than on anything else. Said August 19, 2026.
-
Representative
Rep. Peck toured a South Jordan facility using air and fans for cooling instead of water. Said August 19, 2026.
-
Spanish Fork resident
Teresa P., resident near Fingerhut distribution center, expressed concern about noise, emissions impact. Said August 19, 2026.
-
physicist at Utah State University
Physicist Robert Davies of Utah State University estimated the project could reach 16 gigawatts at full capacity. Said August 19, 2026.
-
Sen. McCay said he does not feel that property tax should be used as much to incentivize data centers. Said August 19, 2026.
-
Volition CEO Jeff Chavez stated the company generates their own power using natural gas powered fuel cells that do not connect to the existing power grid. Said August 19, 2026.
-
CEO, Volition
Volition CEO Jeff Chavez said the proposed facility would use two households' worth of water to fill when first starting operations, then only one household's worth annually. Said August 19, 2026.
-
City Councilman
Councilman Shane Marshall emphasized that getting guardrails right is important. Said August 19, 2026.
-
Volition proposed to contribute at least $500,000 annually to a community fund for addiction recovery, food security and housing support. Said August 19, 2026.
-
City Councilman
Councilman Kevin Oyler stated he takes the issue seriously and is doing his homework despite having many questions. Said August 19, 2026.
-
Sen. McCay said Utah is ahead of most of the country in data center policy. Said August 19, 2026.
-
Jeff Chavez, CEO, Volition
Volition's facilities use natural gas powered fuel cells that do not connect to existing power grid. Said August 19, 2026.
-
Representative
Rep. Nicholeen Peck noted volatility in property tax revenue due to depreciation of assets within data centers. Said August 19, 2026.
-
Jeff Chavez, CEO, Volition
Volition said cooling systems are located indoors to mitigate noise impacts. Said August 19, 2026.
-
Rep. Hawkins said lawmakers are discussing current state policy on data centers and how to define data centers moving forward. Said August 19, 2026.
-
Representative
Rep. Jim Dunnigan raised concerns about air quality and airshed impacts from data centers. Said August 19, 2026.
-
Property owner John B. stated he has received many offers for the warehouse site and considers Volition a better option than a distribution center that would increase truck traffic. Said August 19, 2026.
-
Volition CEO
Chavez said the proposed facility would use only two households' worth of water to fill up initially, then one household's worth per year for humidification. Said August 19, 2026.
-
Spanish Fork resident
Local resident Teresa P. expressed concern about noise, emissions and impact on properties near the proposed data center. Said August 19, 2026.
-
CEO of Volition
Volition CEO Jeff Chavez said their data center project would generate about 250 megawatts of power and use an existing distribution center of about 28 acres. Said August 19, 2026.
-
Jeff Chavez, Volition CEO
Volition plans to create a community fund contributing at least $500,000 per year for addiction recovery, food security, housing support and other community needs. Said August 19, 2026.
-
Virginia Economic Development Partnership
Virginia leads nation in planned data centers, with Northern Virginia accounting for largest concentration of digital infrastructure on Earth. Said August 19, 2026.
-
Milwaukee County Executive
David Crowley argued that every Wisconsin community should have veto power over any data center project within its territory. Said August 19, 2026.
-
Milwaukee County Executive
Tom Tiffany voted for tax cuts that benefit Big Tech and permitting reforms that made data centers easier to build, according to Crowley. Said August 19, 2026.
-
City Engineer, Port Washington
City Engineer Roger Strohm said traffic at shift change is crazy. Said August 19, 2026.
-
Carrie P., a Laramie County voter, listed data center water usage as a top concern, noting that the region's water table is getting low. Said August 19, 2026.
-
Modesto East Claus Road Hyperscale Data Center Proposal
A potential data center in Modesto, California has been proposed and is generating public outcry. The record reads proposed, August 19, 2026.
-
South Elgin Sundowner Road Data Center Proposal
South Elgin rejected a data center development, becoming the latest Chicagoland village to do so. The record reads cancelled, August 19, 2026.
-
Arkansas
Arkansas cities weighing data center restrictions amid growth and environmental concerns.
-
Fayetteville
City implemented harsher penalties for violating city code, including withholding utilities or revoking business licenses.
-
Fayetteville
Data centers must follow stronger protections for noise levels and limits on energy and water use.
-
Fayetteville
Fayetteville City Council unanimously passed an amendment to strengthen the city's data center regulations.
-
Tulare County
Tulare County stalls data center developments with moratorium.
-
Denver
Denver data center moratorium likely to be extended as working group forms.
-
Denver
Working group includes seven community members, two utility representatives, two union representatives, one industry representative, three nonprofit or neighborhood group people, two academia members, two healthcare experts and one air quality expert.
-
Denver
Denver is forming a working group of at least 20 people to guide data center regulation.
-
Denver
Denver has a moratorium on new data center construction through May 2027.
-
Georgia
Georgia Environmental Protection Division ordered workers to stop construction on a data center and power facility due to work beginning without proper permits.
-
Iowa
Petition demands immediate statewide moratorium on all new AI data center construction until comprehensive environmental impact assessments completed.
-
Idaho
Farmers appealed to Idaho Supreme Court after petition seeking to block local data center was thrown out.
-
South Elgin
South Elgin rejected a data center development.
-
Butler County
Butler County tabled proposed data center regulations until September.
-
Olive Branch
Hyperscale data centers categorized as Tier 3, requiring mandatory 2,000 foot setback from public schools, residential areas, parks, and roads.
-
Olive Branch
Hyperscale data centers must not exceed 45 decibels between 9 p.m. to 6 a.m. and 65 decibels at any time at facility boundaries.
-
Olive Branch
Generator power restricted between 2 and 5 p.m. with highest emission standards required.
-
Olive Branch
New ordinance requires data centers to operate closed loop cooling systems.
-
Olive Branch
Olive Branch Board of Mayor and Aldermen approved new zoning ordinance changes restricting data center development.
-
Butte-Silver Bow
Judge Joseph ordered both sides to file briefings by 5 p.m. on Monday before making a final decision on whether equitable estoppel applies.
-
Butte-Silver Bow
The initiative would require approval from two thirds of registered voters for the building or expansion of data centers in Butte-Silver Bow.
-
Butte-Silver Bow
Election Administrator Cindy Sherman initially gave residents a deadline of August 14 to collect signatures for the data center initiative, then changed it retroactively to July 13.
-
Butte-Silver Bow
District Court Judge Frank Joseph heard arguments on whether a ballot initiative to limit data center building on the November ballot in Butte-Silver Bow.
-
Butte-Silver Bow County
Judge ordered more briefing on issue before ruling on case next week, after Billings judge sided with county in similar case last week.
-
Butte-Silver Bow County
District Court Judge Frank Joseph requested more information before deciding lawsuit over rejected data center ballot initiative signatures.
-
Butte-Silver Bow County
Butte-Silver Bow County Clerk and Recorder Cynthia Sherman named as defendant in lawsuit over rejected ballot initiative signatures.
-
Butte-Silver Bow County
406 People First group collected 3,652 signatures on ballot initiative to vote on data centers that were accepted by county clerk on July 31 but rejected on August 10 as not meeting requirements of Montana law adopted in late 2025.
-
Nye County
Nye County Board scheduled future public hearing on countywide ordinance to spell out rules for data centers.
-
Nye County
Nye County commissioners considering special election on whether data centers allowed in Nevada Hydrographic Basin 162 covering much of Pahrump.
-
Nye County
Nye County commissioners approved land use code change banning data centers in Pahrump area.
-
Shawnee
Shawnee approved a temporary moratorium on new data centers effective immediately through end of 2027.
-
Pennsylvania
Pennsylvania House passed bill calling for six month moratorium on data center construction.
-
Pennsylvania
Governor Shapiro issued an executive order affecting data center development.
-
Pennsylvania
Pennsylvania dangles permitting carrot for data centers that bring their own power.
-
Pennsylvania
Data centers must shoulder all costs of their electricity service under the order.
-
Pennsylvania
The order calls for utilities to cut power to data centers first in case of grid emergency.
-
Pennsylvania
Data centers with peak load of at least 25 megawatts must sign a consent order before permit reviews.
-
Pennsylvania
The order prohibits nondisclosure agreements for data centers.
-
Pennsylvania
Pennsylvania Governor signed executive order setting strict requirements on data center developments.
-
Pennsylvania
Shapiro's executive order takes into consideration environmental, energy and community costs of new data centers.
-
Ozaukee County
Enhanced pedestrian control signal and lane widening at Highland Lane and Highland Drive intersection.
-
Ozaukee County
County widening lanes at I-43 ramps and Highway LL, creating dedicated turn lanes.
-
KTUL
Google has contributed more than $2 million in the Tulsa area over the last two years toward workforce and community efforts. Tulsa County, OK, 2026.
Key Figure 2,000,000 USD -
enr.com
NVIDIA will invest 1.5 billion dollars in SB Energy to support its growth. Piketon, Pike County, OH, 2026.
Key Figure 1,500,000,000 dollars -
Newsweek
71 percent in earlier Gallup survey opposed a data center being built in their community. Texas, statewide, 2026.
Key Figure 71 percent -
Newsweek
57 percent of respondents in Reuters/Ipsos poll from June opposed a data center being built in their community. Texas, statewide, 2026.
Key Figure 57 percent -
Newsweek
Pennsylvania has 136 tracked data center facilities: 94 operational, 4 under construction, 38 planned as of August 2026. Pennsylvania, statewide, 2026.
Key Figure 136 facilities -
Ozaukee Press
Vantage Data Centers Lighthouse Campus workforce increased to approximately 5,000 workers in summer 2026. Port Washington, Ozaukee County, WI, 2026.
Key Figure 5,000 workers -
KTTC
Google promises more than $130 million in tax revenue in the first 28 years. Pine Island, Olmsted County, MN, 2026.
Key Figure 130,000,000 USD -
KTUL
Google has contributed over $2 million to support Tulsa County community partners. Tulsa County, OK, 2026.
Key Figure 2,000,000 USD -
enr.com
Initial deployment expected to provide 4.25 gigawatts of AI factory capacity. Piketon, Pike County, OH, 2026.
Key Figure 4.25 GW -
KTUL
Google has invested more than $15 billion in Oklahoma since 2011. Tulsa County, OK, 2026.
Key Figure 15,000,000,000 USD -
KTUL
Google's 2025 investments and technology supported $2.6 billion in economic activity in Oklahoma. Tulsa County, OK, 2026.
Key Figure 2,600,000,000 USD -
vox.com
76 percent of Wisconsin voters say that data center server farms' costs outweigh their benefits. Wisconsin, statewide, 2026.
Key Figure 76 percent -
WBRZ
The full project will result in an additional 1,784 indirect jobs. Shreveport, Caddo Parish, Louisiana, LA, 2026.
Key Figure 1,784 jobs -
KSL News
Volition said the facility would generate around $44 million in tax revenue for the city, school district and taxing entities. Spanish Fork, Utah County, UT, 2026.
Key Figure 44,000,000 USD -
Style Weekly
Virginia has 371 operating data centers with combined capacity of 17,378 megawatts and 459 planned projects adding 37,627 megawatts. Richmond, Virginia, 2026.
Key Figure 17,378 MW -
Data Center Dynamics
AWS pledged $6 billion for Shreveport data center campus. Shreveport, Caddo Parish, LA, 2026.
Key Figure 6,000,000,000 USD -
enr.com
NVIDIA plans to invest up to 105 billion dollars to secure land, power and shell capacity for PORTS Pike Technology Campus. Piketon, Pike County, OH, 2026.
Key Figure 105,000,000,000 dollars -
Newsweek
Allegheny County has 28 data center facilities, largest in Pennsylvania. Pennsylvania, statewide, 2026.
Key Figure 28 facilities -
KTUL
Google has invested more than $15 billion statewide since 2011. Tulsa County, OK, 2026.
Key Figure 15,000,000,000 USD -
Style Weekly
72% of registered Virginia voters oppose granting sales tax exemptions as incentive for data center development. Richmond, Virginia, 2026.
Key Figure 72 percent -
Ozaukee Press
The 672 acre site will contain four data center buildings, warehouse, operations center and support buildings. Port Washington, Ozaukee County, WI, 2026.
Key Figure 672 acres -
KTTC
Google promises hundreds of new jobs with a job multiplier ratio of 9 to 1. Pine Island, Olmsted County, MN, 2026.
Key Figure 9 jobs -
KSL
Project backers cited roughly 2,000 permanent positions. Box Elder County, UT, 2026.
Key Figure 2,000 jobs -
Deseret News
Novva Data Center's cooling system was initially charged with 55,000 gallons of water in 2021 and has had almost no water loss since. Utah, statewide, 2026.
Key Figure 55,000 gallons -
KTUL
Workforce training with the electrical training ALLIANCE will add more than 160 apprentices in Oklahoma by 2030. Tulsa County, OK, 2026.
Key Figure 160 jobs -
WBRZ
Louisiana Economic Development estimates the expanded project will result in an additional 499 indirect new jobs. Shreveport, Caddo Parish, Louisiana, LA, 2026.
Key Figure 499 jobs -
KSL
Project backers cited roughly 10,000 construction jobs. Box Elder County, UT, 2026.
Key Figure 10,000 construction jobs -
E&E News by POLITICO
Amazon plans to spend at least $20 billion for data center hubs in Pennsylvania. Pennsylvania, statewide, 2026.
Key Figure 20,000,000,000 USD -
Newsweek
Texas state comptroller's office estimated data center tax breaks could mean foregoing over 1 billion dollars each year. Texas, statewide, 2026.
Key Figure 1,000,000,000 dollars a year -
KSL
Gallup survey found 71% of Americans oppose data centers being built near their homes. United States, a national poll of the public, 2026.
Key Figure 71 percent -
enr.com
SB Energy plans to invest at least 4.2 billion dollars in new regional grid infrastructure through partnership with AEP Ohio. Piketon, Pike County, OH, 2026.
Key Figure 4,200,000,000 dollars -
spokesman.com
In Michigan and Georgia, 17 data center projects have been delayed or blocked. United States, national, 2026.
Key Figure 17 projects -
enr.com
PORTS Pike power generation capacity about 9.2 gigawatts from natural gas. Piketon, Pike County, OH, 2026.
Key Figure 9.2 GW -
Style Weekly
81% of registered Virginia voters support requiring data centers to offset demands on Virginia's electric infrastructure. Richmond, Virginia, 2026.
Key Figure 81 percent -
E&E News by POLITICO
Pennsylvania added 2.4 gigawatts of new data center capacity between March 2024 and March 2025. Pennsylvania, statewide, 2026.
Key Figure 2.4 GW -
Data Center Dynamics
Construction phase will create approximately 2,250 jobs. Shreveport, Caddo Parish, LA, 2026.
Key Figure 2,250 jobs -
Deseret News
Utah has 48 operational data centers. Utah, statewide, 2026.
Key Figure 48 count -
Newsweek
Texas accounts for more planned data center capacity by megawatts (94,656 MW) than the next three states combined. Texas, statewide, 2026.
Key Figure 94,656 MW -
Deseret News
Novva Data Center saved up to 300 million gallons of water per year using closed loop cooling. Utah, statewide, 2026.
Key Figure 300,000,000 gallons per year -
Bangor Daily News
A University of Massachusetts Lowell/YouGov poll conducted in May 2026 found 72 percent of likely Maine voters opposed to a data center being built in their community. Lincoln, Maine, 2026.
Key Figure 72 percent -
KSL
Physicist Robert Davies of Utah State University estimated the project could reach 16 gigawatts at full capacity. Box Elder County, UT, 2026.
Key Figure 16 GW -
KSL.com
Chavez stated Volition would generate around $44 million in annual tax revenue for the city, school district and other taxing entities. Spanish Fork, Utah County, UT, 2026.
Key Figure 44,000,000 USD -
spokesman.com
At least 75 data center projects worth about $130 billion combined were blocked or delayed by local opposition during first three months of 2026. Doña Ana County, NM; statewide in NY, TX, PA, MI, GA, 2026.
Key Figure 130,000,000,000 USD -
Data Center Dynamics
Shreveport campus will create approximately 210 direct jobs once operational. Shreveport, Caddo Parish, LA, 2026.
Key Figure 210 jobs -
Data Center Dynamics
Total AWS Louisiana data center investment commitment is $18 billion across three campuses. Shreveport, Caddo Parish, LA, 2026.
Key Figure 18,000,000,000 USD -
Newsweek
79 percent of Texans supported AI data centers being forced to disclose their water consumption. Texas, statewide, 2026.
Key Figure 79 percent -
Newsweek
75 percent of Texans in favor of centers funding their own grid upgrades. Texas, statewide, 2026.
Key Figure 75 percent -
WBRZ
The additional investment is expected to create 210 direct new jobs. Shreveport, Caddo Parish, Louisiana, LA, 2026.
Key Figure 210 jobs -
KSL
At least 75 data center projects worth roughly $130 billion were blocked or delayed in the first quarter of 2026. Box Elder County, UT, 2026.
Key Figure 130,000,000,000 USD -
Newsweek
Philadelphia County has 20 data center facilities, second largest in Pennsylvania. Pennsylvania, statewide, 2026.
Key Figure 20 facilities -
KTTC
Google promises estimated $1.1 billion in benefits to Xcel Energy customers over the next 15 years. Pine Island, Olmsted County, MN, 2026.
Key Figure 1,100,000,000 USD -
enr.com
PORTS Pike Technology Campus planned 10 gigawatt data center campus. Piketon, Pike County, OH, 2026.
Key Figure 10 GW -
E&E News by POLITICO
President Trump detailed more than $90 billion in investments for Pennsylvania's AI build out. Pennsylvania, statewide, 2026.
Key Figure 90,000,000,000 USD -
KTUL
Google's investments and technologies helped provide $2.6 billion of economic activity in 2025 for Oklahoma businesses. Tulsa County, OK, 2026.
Key Figure 2,600,000,000 USD -
Newsweek
Texas generated 4.5 billion dollars in tax revenue from data centers in 2024. Texas, statewide, 2026.
Key Figure 4,500,000,000 dollars a year -
KTUL
Google has signed more than 15 agreements to enable development of more than 2.5 GW of new power generation and storage since 2011. Tulsa County, OK, 2026.
Key Figure 2.5 GW -
Can Large-Load Flexibility Ease Data Center Energy Concerns?
Article examines whether large load flexibility could enable data centers to stabilize electrical grids during peak demand periods rather than strain them.
-
Jones, Figures address data centers, November chances at Troy forum - WTVY
Former U.S. Sen. Doug Jones said voters concerned about data center projects should vote for him because his opponent Tommy Tuberville would allow them without scrutiny.
-
Huntsville residents voice concerns over Meta data center expansion - yahoo.com
Huntsville residents raised concerns about Meta data center expansion, citing water, power, jobs, environmental impacts and transparency.
-
Huntsville residents seek answers on impact of Meta data center expansion - rocketcitynow.com
Huntsville residents call for moratorium on new data center projects pending transparent public process; Meta's expansion raises concerns on water, power, environmental impact, and job fulfillment.
-
Proposed data centers could use more electricity than all Alabama homes combined, analysis shows. Who will pay? - route-fifty.com
Analysis shows proposed Alabama data centers could consume more electricity than all state homes combined; Alabama Power promises bills won't rise; state's new SB 270 law requires PSC to evaluate utility contracts on public interest basis starting October 1.
-
Data centers are not inevitable. It’s time for state laws to catch up. - Alabama Reflector
An Alabama Reflector article argues that data centers are not inevitable and calls for state laws to address the issue. The piece presents arguments about data center regulation and policy.
-
Fayetteville City Council approves increasing data center regulations - KNWA FOX24
Fayetteville City Council unanimously passed amendments strengthening data center regulations, including noise, energy, and water restrictions.
-
Study weighs economic impact of AI data centers in rural Arkansas - texarkanagazette.com
A study weighs economic impacts of artificial intelligence data center growth across rural and urban U.S. communities.
-
Arkansas Cities Weigh Data Center Restrictions Amid Growth and Environmental Concerns - KVOM 101.7
Arkansas cities are considering data center restrictions in response to growth and environmental concerns. Multiple municipalities are evaluating regulatory measures on data centers.
-
Biomass-fueled data center project planned in Amador County - myMotherLode.com
New York GreenCloud plans Buena Vista AI Factory, a biomass powered data center in Amador County on a defunct biomass site.
-
Plans for potential data center in Modesto, California, spark public outcry - Data Center Dynamics
A potential data center in Modesto, California is generating public opposition. The item reports on a data center proposal and community response.
-
Tulare County stalls data center developments with moratorium. It could be extended - Fresno Bee
Fresno Bee reports that Tulare County has enacted a moratorium on data center developments. The moratorium could be extended.
-
Denver data center moratorium likely to be extended as working group forms - The Business Journals
Denver's data center moratorium is likely to be extended as a working group forms. The action indicates ongoing jurisdictional restrictions on new data center development.
-
Denver to form data-center regulation group ahead of 2027 moratorium deadline - Colorado Politics
Denver is forming a resident expert panel to guide data center regulation ahead of the May 2027 moratorium deadline.
-
Trumbull residents seek data center moratorium amid $100 million upgrade - CT Insider
Trumbull residents seek a data center moratorium as the town conducts a $100 million infrastructure upgrade. The effort reflects local concern about data center development timing.
-
Data centers loom over the New Castle County Council primary election campaigns | Spotlight Delaware - Newark Post
Data centers are a topic in New Castle County Council primary election campaigns in Delaware. The item reports on political attention to data center issues in a local election.
-
Is a data center coming to your neighborhood? You might not know if this rule changes - WSB-TV
EPA considers eliminating federal public notice requirement for air permits before data center approvals, potentially reducing community awareness.
-
Discussions cease over proposed data center in Maquoketa - WQAD
City of Maquoketa and development consultant Gronen cease preliminary discussions on proposed small to mid sized data center in Highway 61 Industrial Park after resident opposition.
-
Say No to Any New Data Centers in Iowa — Sign The Petition to Support a Moratorium Now! - actionnetwork.org
Advocacy groups are seeking a statewide moratorium on all new AI data center construction in Iowa until comprehensive environmental and public health impacts are studied.
-
After petition seeking to block local data center thrown out, farmers appeal to Idaho Supreme Court - BoiseDev
Farmers filed an appeal to the Idaho Supreme Court after a local petition to block a data center was dismissed. The appeal indicates ongoing legal conflict over a data center project.
-
Grayslake Sets Final Extended Comment Session On Data Center - Patch
Grayslake, Illinois holds final extended public comment session on approved data center campus.
-
South Elgin becomes latest Chicagoland village to reject a data center development - The Real Deal
South Elgin rejected a data center development proposal, following other Chicagoland villages in refusing such projects. The item reports on local zoning or land use decision.
-
Residents raise concerns over potential Rock Island County data center - KWQC
Residents in Rock Island County raised concerns about a potential data center project. Community opposition is documented.
-
Indy halts new data centers through 2027 in rare win for opponents - IndyStar
Indianapolis halted new data centers through 2027, according to opponents' account. The action represents a jurisdiction wide moratorium on data center development.
-
Metropolitan Development Commission unanimously approves data center moratorium in Indy - Fox 59
The Metropolitan Development Commission in Indianapolis unanimously approved a data center moratorium. The action restricts new data center development in the city.
-
Butler County tables proposed data center regulations until September | Trusted News Source for Wichita & Kansas - kake.com
Butler County postponed a vote on proposed data center regulations to September. The jurisdiction is developing regulatory guidance for data center development.
-
KY farm owner wants governments to 'throw on the brakes' after turning down $26M offer from AI data center - cnn.com
A Kentucky farm owner rejected a $26 million offer from an AI data center company and called for government action to stop similar projects. The offer amount signals developer interest in Kentucky farmland.
-
EPIC discusses new Kentucky data center report - WPSD Local 6
EPIC talked about a new report that looks at data centers in Kentucky.
-
AWS pledges $6bn investment in data center campus in Shreveport, Louisiana - Data Center Dynamics
AWS pledged $6 billion to develop a data center campus in Shreveport at the Resilient Technology Park, bringing its total Louisiana commitment to $18 billion across three campuses. The Shreveport project will create about 210 direct jobs and 2,250 construction jobs.
-
Susan Collins takes cautious line on data centers opposed by most Mainers - Bangor Daily News
Sen. Susan Collins said data centers should be handled case by case and expressed support for projects at former mill sites with hydropower. Collins shared concern about energy consumption and stressed that communities should evaluate whether benefits outweigh costs.
-
Congressional candidate demands data center moratorium ahead of Google’s Pine Island celebration - KTTC
DFL congressional candidate demands data center moratorium in Minnesota, citing concerns about water, energy, noise, and transparency.
-
Minneapolis North Loop residents express concerns over potential data center - CBS News
Minneapolis North Loop residents expressed concerns over a potential data center development. Community opposition to the project is documented.
-
North Loop residents question developers over proposed data center at former Star Tribune site - CBS News
Developers proposed a data center at the former Star Tribune site in North Loop, Minneapolis, with residents questioning the project. The proposal indicates a specific development plan for the site.
-
Olive Branch Board of Aldermen approves data center restrictions - Yahoo
Olive Branch, Mississippi approved stricter data center zoning ordinance restricting locations, requiring closed loop cooling, limiting generator use, and setting noise standards for hyperscale facilities.
-
Butte-Silver Bow data center initiative controversy heard in District Court - NBC Montana
District Court Judge Frank Joseph heard arguments over whether a ballot initiative limiting data center development must appear on the November election in Butte-Silver Bow, Montana.
-
Butte-Silver Bow County judge seeks more information in data center ballot initiative lawsuit - KBZK News
Butte district court judge seeks more information before ruling on data center ballot initiative lawsuit challenging deadline validity.
-
Frustrated, rowdy data center opponents make more noise in Yellowstone County - Montana Free Press
Yellowstone County commissioners in Montana took no action on a proposal to put a data center moratorium on the November 2026 ballot, whose signature deadline a 2025 legislative change had moved to July 13.
-
Gov. Pillen Announces Appointments to the Newly Created Data Center Task Force - Nebraska Governor's Office (.gov)
Governor Jim Pillen announced 17 appointments to a newly created Data Center Task Force authorized by executive order. The task force will evaluate data center impacts on Nebraska's water, power, and infrastructure and provide county officials with tools and policies for managing growth.
-
Former Nabisco Site Won't Be A Data Center, Bergen County Mayor Vows - Patch
The Bergen County mayor stated the former Nabisco site will not become a data center. This is a direct statement of opposition to a potential data center project.
-
Tech deploys charm offensive to combat AI data center backlash - The Spokesman-Review
Oracle's Project Jupiter 2.45 GW data center in Doña Ana County faces local backlash as tech firms escalate PR campaigns to combat opposition.
-
Nye County commissioners approve data center ban in Pahrump - FOX5 Vegas
Commissioners in Nye County, Nevada, changed the land use code to ban data centers in the Pahrump area and scheduled a public hearing on a countywide ordinance setting rules for data centers.
-
Ford says he’ll pause data center tax abatements if elected - Nevada Current
Ford said he would pause data center tax abatements if elected to office. The statement addresses Nevada's tax incentive policy on data centers.
-
Data center backlash poised to play critical role in midterms: ‘We don’t even need data centers’ - nypost.com
A May 2026 Gallup poll found 71% of Americans oppose data center construction, while a July survey showed opposition rising sharply across both political parties, with governors in multiple states moving to restrict or regulate data center development.
-
NVIDIA Partners With SB Energy on 10-GW AI Data Center Complex in Ohio - enr.com
NVIDIA invests up to $105 billion with SoftBank to develop 10 gigawatt AI data center campus at former uranium enrichment site in Piketon, Ohio.
-
How Massive Ohio AI Data Center Power Deal Will Impact American Electric Power Company (AEP) Investors - Yahoo Finance
OpenAI Ohio data center to receive 4.25 gigawatts of capacity from AEP with $4.2 billion transmission upgrade funded by project partners.
-
OpenAI joins world’s largest data center project, brings 35,000 construction jobs to Ohio - NBC4 WCMH-TV
NBC4 reports OpenAI joined the world's largest data center project, bringing 35,000 construction jobs to Ohio. The development represents a major employment impact from data center construction.
-
Nvidia Backs OpenAI’s Ohio Data Center Buildout With $105B Guarantee
Nvidia is providing up to $105 billion in residual value guarantees for OpenAI's Ohio data center campus at PORTS Pike Technology Campus in Pike County. The guarantees cover an initial 4.25 GW with an option for 3.75 GW more, totaling about 8 GW of IT capacity.
-
Google confirmed as end user of Tulsa County s Project Clydesdale data center campus - KTUL
Google confirmed it is the end user of Project Clydesdale, a 506 acre data center campus in Tulsa County under construction since October 2025, with plans for workforce training and infrastructure upgrades.
-
Google, Beale Infrastructure share details around new data center campus in Tulsa County - KTUL
Google and Beale Infrastructure announced details for data center campus under construction in Tulsa County near Cherokee Industrial Park with 506 acres, new substation, and workforce training.
-
Shawnee approves temporary moratorium on new data centers - News 9
Shawnee city commissioners approved temporary moratorium on new data centers through end of 2027 to review regulations.
-
Oregon county starts data center moratorium process, but 45-day gap leaves an opening - The Cool Down
Clackamas County Oregon board voted unanimously to start formal process for moratorium on data center applications with required 45 day notice.
-
Former U.S. labor secretary from Oregon lands job advocating for data center industry - OregonLive.com
Former U.S. labor secretary Lori Chavez DeRemer joins Think Big as senior adviser for labor and data center infrastructure advocacy.
-
Portland’s Union Electricians Are Moving to Idaho at an Alarming Rate - Willamette Week
IBEW Local 48 electrical workers union supports data center development to provide jobs as Oregon union construction work declines due to Intel slowdown and lack of regional projects.
-
Eugene environmental groups alarmed by potential data center - kezi.com
Eugene city received zone verification request for potential data center at former Hynix campus; environmental groups raised concerns about energy and water impacts.
-
Data center restriction in Pennsylvania is badly needed, anti pollution advocate says - CBS News
Pennsylvania Governor Josh Shapiro placed guardrails on data center development; an anti pollution advocate says the state needs data center restrictions.
-
Shapiro on placing guardrails on AI data centers in Pennsylvania: "I don't want developers running roughshod" - CBS News
Pennsylvania Governor Josh Shapiro says he will not allow data center developers to run roughshod over communities, citing executive order with strict guardrails.
-
Pennsylvania Governor signs executive order imposing strict requirements on data center developments - Data Center Dynamics
Pennsylvania's governor signed an executive order requiring data center projects to receive all required local approvals before permits are issued.
-
Pennsylvania Moves to Rein In AI Data Centers After Community Backlash - Newsweek
Pennsylvania Governor Shapiro signed executive order requiring AI data center developers to pay all electricity costs, source clean power, obtain local approval, and disclose project details.
-
PAX-1 data center project removed from PA Permit Fast Track Program under Shapiro executive order
Pennsylvania Governor Josh Shapiro signed an executive order removing data centers from the PA Permit Fast Track program and imposing stricter environmental and transparency requirements; PAX-1 in Cumberland County is affected.
-
Pennsylvania Gov. Shapiro signs order to limit new data centers - E&E News by POLITICO
Pennsylvania Governor Shapiro signs executive order requiring local approval before data center permits, tightening eligibility rules.
-
Why PA data centers want public officials to sign NDAs - Spotlight PA
Spotlight PA reports on data center developers requesting NDAs from public officials in Pennsylvania. The practice suggests efforts to limit disclosure of project details.
-
Sweeping new data center rules give local governments more leverage in Pennsylvania - Smart Cities Dive
Pennsylvania Governor Shapiro signs executive order establishing strict guardrails on data center development, requiring local approval and community benefits.
-
Data center inquiries made for Trainer-Lower Chichester tract - delcotimes.com
Link Logistics explored data center use at Trainer Lower Chichester property; local officials await formal proposal as Pennsylvania considers statewide moratorium.
-
More Delaware County communities address data center zoning - delcotimes.com
Delaware County municipalities address data center zoning with proposed ordinances requiring environmental review, setbacks, water monitoring, and decommissioning plans.
-
Data center projects across Pennsylvania face uncertainty under new Shapiro order - fox43.com
Pennsylvania Governor Shapiro issued an executive order affecting data center projects statewide. Multiple projects are now facing uncertainty about their status.
-
Pennsylvania dangles permitting carrot for data centers that bring their own power - Utility Dive
Pennsylvania is offering faster permitting for data centers that provide their own power supply. The policy change encourages self powered data center development.
-
Gov. Bill Lee, Tennessee Cabinet Visit Fisk Amid Data Center Controversy - The Tennessee Tribune
Tennessee Governor Bill Lee visited Fisk University in Nashville amid controversy over a data center.
-
Mayor Young hopes for clarity on data centers, TVA rates at open session - WREG.com
Memphis Mayor Young hopes an open session will bring clarity on data centers and TVA rates.
-
Texas Governor Pauses New Data Centers, Mirroring Growing U.S. Skepticism - Industrial Info
Texas Governor Greg Abbott ordered state energy agencies to pause permitting of new data centers on August 3, 2026, citing water and power concerns.
-
Texas House hearing talks data center growth, possible regulation, power supply - NBC 5 Dallas-Fort Worth
The Texas House held a hearing on data center growth, possible regulation, and power supply. The hearing addresses jurisdictional policy on the data center industry.
power -
Texas Data Center Moratorium: Local Regulation & State Action - MultiState
MultiState reports on Texas data center regulation including a moratorium, local zoning rules, and state level actions. The article covers regulatory developments affecting the sector.
zoning -
Texas lawmakers hear debate on data centers, transmission lines - KEYE
Texas House State Affairs Committee heard testimony on data center power demands and 765 kV transmission line costs; Governor Abbott halted data center grid connections pending audit.
-
Texas’s Data Center Dominance At Risk - Newsweek
Texas data center dominance at risk as local and state opposition mounts; Governor Abbott orders pause on interconnection requests pending grid audit.
-
Austin-area residents are pushing for data center bans. State leaders are divided on what to do next - KUT
Austin area residents and Texas localities push for data center bans and restrictions amid bipartisan concerns about water and power consumption.
-
Texas Data Center Tax Break: 6 Projects Fail Compliance Review - Good Jobs First
Texas audit found 6 of 20 data center projects reviewed failed to meet job and facility size requirements; state cannot verify promised employment gains justify $3.3 billion subsidy cost.
-
Texas welcomed data centers, now it’s backtracking. It’s time for a real plan - dallasnews.com
Texas reassesses data center policy after rapid growth; state and local governments seek regulatory frameworks.
-
House Bill Would Put Federal Electricity Tax on Data Centers
House bill H.R. 10102 proposes a 1 cent per kilowatt hour federal excise tax on data center electricity to fund housing, conservation, and infrastructure.
-
Utah considers changes to laws governing data centers - Deseret News
Utah lawmakers consider policy changes to enforce water efficient cooling technologies for data centers statewide.
-
Residents voice concerns over self-powered data center proposal in Spanish Fork - KSL News
Spanish Fork City Council debates data center regulations for Volition's self powered AI data center proposal at former Fingerhut warehouse site.
-
Utah lawmakers weigh costs, benefits of data centers during interim session - KUTV
Utah lawmakers discussed data center policy during interim legislative session, raising concerns about water use, energy, infrastructure, and property tax incentives.
-
City council to revisit resolution regarding data centers in Spanish Fork after hours of public comment - FOX 13 News Utah
Spanish Fork city council tabled a resolution to amend ordinance allowing data center self generation of power after five hour public hearing with dozens of commenters opposing the Volition project.
-
Kevin O'Leary Admits ‘We Have Not Properly Communicated’ Utah Data Center Plans, Promises More Transparency - Yahoo Finance
Kevin O'Leary acknowledged his Stratos data center project in Box Elder County, Utah mishandled public communication and pledged to release detailed plans for a one gigawatt facility and become more transparent with the community. The original project was pitched at up to 9 gigawatts but faces statewide opposition and calls for significant downsizing.
-
Google data center capped at 2M gallons of water a day until infrastructure upgraded - WDBJ7
Western Virginia Water Authority caps Google data center water allocation at 2 million gallons daily pending infrastructure upgrades, though contract allows up to 8 million gallons.
-
Photos: Data Center Town Hall at Studio Two Three - Style Weekly
Richmond activists hold town hall opposing data center expansion, citing polls showing 72% of Virginians oppose tax exemptions and 81% support infrastructure cost requirements.
-
Plans for data center campus in Virginia’s Prince William County refiled - Data Center Dynamics
JK Land Holdings refiled plans for a five building data center campus on an 82 acre property in Gainesville, Prince William County, Virginia. The proposal reduces building height and square footage from earlier versions and requires a special use permit.
-
Port grapples with ‘crazy’ data center traffic
Port Washington installs temporary traffic signals at I-43 to manage gridlock from Vantage data center construction with 5,000 workers.
-
PNK Group's WI Rapids data center webinar addresses water use, cooling - Daily Tribune Media
PNK Group holds webinar on Wisconsin Rapids data center project detailing closed loop cooling system using propylene glycol and minimizing domestic water use.
-
The strange politics of the AI backlash - vox.com
Wisconsin governor's race features candidates David Crowley and Tom Tiffany disagreeing over data center policy; both favor local control but oppose statewide moratorium.
-
Plan For Data Center Puts Spotlight On Lax Fremont County Zoning Laws - Cowboy State Daily
Fremont County, Wyoming zoning laws are highlighted as lax in a plan for a data center. The report concerns local jurisdiction regulation of data center development.
-
‘True’ conservatives, public lands, data centers top issues for Wyoming primary election voters - WyomingNews.com
Wyoming primary voters prioritized conservative values, public lands, data centers and taxes; article reports their stated motivations.
-
Google Pine Island Data Center (Project Skyway)
Google and Ryan Companies promised an initial capital investment of more than $700 million into Pine Island. The record reads proposed, reported August 19, 2026.
-
Google Pine Island Data Center (Project Skyway)
Google promised $3 million directly to Pine Island city. The record reads proposed, reported August 19, 2026.
-
Google Pine Island Data Center (Project Skyway)
Google is expected to announce the project's Panther Program and other initiatives benefiting the Pine Island School District, with a projected investment of $24 million. The record reads proposed, reported August 19, 2026.
-
PORTS-Pike Technology Campus
PORTS Pike data center campus located on site of former Portsmouth Gaseous Diffusion Plant uranium enrichment facility near Columbus, Ohio. The record reads approved, reported August 19, 2026.
-
PORTS-Pike Technology Campus
SB Energy will develop, own and operate data center campus including power generation. The record reads approved, reported August 19, 2026.
-
PORTS-Pike Technology Campus
Bechtel and Kiewit Corp tapped to provide engineering, procurement, construction and other services for PORTS Pike. The record reads approved, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
Google is the end user of Project Clydesdale, a 506 acre data center campus in unincorporated Tulsa County. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
Beale Infrastructure officially broke ground on Project Clydesdale in October 2025. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
The project will include approximately 1.5 miles of new water lines and infrastructure upgrades. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
Located just west of Owasso. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
Support for training more than 160 apprentices in electrical trades by 2030. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
1.5 miles of new water lines and infrastructure upgrades for Washington County Rural Water District #3. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
Construction of a new on site substation funded by Beale. The record reads being built, reported August 19, 2026.
-
Project Clydesdale (Google Tulsa County)
506 acre campus in unincorporated Tulsa County near Cherokee Industrial Park. The record reads being built, reported August 19, 2026.
-
PAX-1 Data Center
The 700 acre PAX-1 property is located off Country Club Road and construction crews have already begun moving dirt. The record reads reported, reported August 19, 2026.
-
PAX-1 Data Center
The PAX-1 data center project in Cumberland County does not have all the necessary permits to operate. The record reads reported, reported August 19, 2026.
-
Stratos Project
Stratos project was originally pitched at up to 9 gigawatts across a 40,000 acre site near the Great Salt Lake. The record reads waiting on permits, reported August 19, 2026.
-
Stratos Project
O'Leary's team will release plans for a one gigawatt facility detailing its heat, light, noise and water profile. The record reads waiting on permits, reported August 19, 2026.
-
Stratos Project
O'Leary has pledged to scale back the development. The record reads waiting on permits, reported August 19, 2026.
-
Volition Industries Spanish Fork
Volition is proposing a development agreement holding the company accountable to all statements made about the project. The record reads waiting on permits, reported August 19, 2026.
-
Volition Industries Spanish Fork
Council meeting to revisit data center resolution at September 1 meeting. The record reads proposed, reported August 19, 2026.
-
Volition Industries Spanish Fork
Volition aims to redevelop the former Fingerhut warehouse site at 4000 E. U.S. 6 into a self powered AI data center. The record reads waiting on permits, reported August 19, 2026.
-
Volition Industries Spanish Fork
Jeff Chavez, Volition CEO, said project would generate about 250 megawatts of power. The record reads proposed, reported August 19, 2026.
-
Volition Industries Spanish Fork
Volition proposed redevelopment of former Fingerhut warehouse site at 4000 E. U.S. 6 in Spanish Fork for self powered AI data center. The record reads proposed, reported August 19, 2026.
-
Volition Industries Spanish Fork
Volition project would utilize an existing distribution center about 28 acres in size. The record reads proposed, reported August 19, 2026.
-
Volition Industries Spanish Fork
Volition's closed loop cooling system would need about two Utah households' worth of water to fill. The record reads proposed, reported August 19, 2026.
-
Vantage Port Washington Data Center Campus
Traffic lights were to be operational by August 24, 2026. The record reads being built, reported August 19, 2026.
-
Vantage Port Washington Data Center Campus
Temporary traffic lights installed at highways 32 and H at I-43 interchange. The record reads being built, reported August 19, 2026.
-
Vantage Port Washington Data Center Campus
Vantage is paying for traffic improvements and law enforcement officers for traffic control. The record reads being built, reported August 19, 2026.
-
Vantage Port Washington Data Center Campus
Project is expected to be completed in 2028. The record reads being built, reported August 19, 2026.
-
Vantage Port Washington Data Center Campus
Data center campus broke ground in December 2025. The record reads being built, reported August 19, 2026.