Data Center Record tracks 234 facilities across Kansas, Oklahoma, Nebraska, Missouri, Arkansas, Louisiana, Texas, New Mexico, North Dakota, South Dakota, Iowa, Minnesota, Montana and Wyoming in the Southwest Power Pool (SPP) regional power market.

Modeled wholesale electricity price effect and regional load

2024 to 2025 wholesale price effect
4.8 percent (+$1.43 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
2028 projected wholesale price effect
5.9 percent (+$1.83 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
Data center share of regional electricity load (2025)
2.2 percent, modeled data center load share, Dallas Fed WP 2606r1, third party estimate.
Fixed cost share of retail electricity bill
62.1 percent (s = 0.621), retail pass through parameter, Dallas Fed WP 2606r1, third party estimate.

States in Southwest Power Pool

Tracked facilities in Southwest Power Pool (234)

Facility State Place Stage Stated power
CleanSpark Rapid City Data Center Proposal SD Rapid City, Pennington County proposed
SDN Communications Sioux Falls Data Center Campus SD Sioux Falls, Minnehaha County running
Amazon Web Services Becker Data Center Campus MN Becker, Sherburne County approved 250 MW
Amazon Montgomery County Data Center Proposal MO New Florence, Montgomery County proposed
Apple Waukee Data Center Campus IA Waukee, Dallas County being built 100 MW
Ark Data Centers Duluth Data Center MN Duluth, St. Louis County running 3 MW
Atomic Data Minneapolis Data Center (MSP250) MN Minneapolis, Hennepin County running 4 MW
Aureon West Des Moines Data Center IA West Des Moines, Polk County running 4 MW
Bluebird Network Quad Cities Data Center (Bettendorf) IA Bettendorf, Scott County running 4 MW
Bluebird Underground Data Center (Springfield) MO Springfield, Greene County running 6 MW
Oppidan Connect Cedar Rapids Data Center (CLOP Cedar Rapids) IA Cedar Rapids, Linn County approved
Centersquare Minneapolis Shakopee Data Center (MSP1) MN Shakopee, Scott County running 12 MW
CloudHQ Chaska Data Center Campus (MSP Campus) MN Chaska, Carver County being built 180 MW
Cologix Des Moines Carrier Hotel (DSM1) IA Des Moines, Polk County running 5 MW
Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3) MN Minneapolis, Hennepin County running 15 MW
Cube NA Data Center Kansas City (101 Holmes) MO Kansas City, Jackson County running 6 MW
CyrusOne Council Bluffs Data Center (OCB1) IA Council Bluffs, Pottawattamie County running 30 MW
DataBank Brooklyn Park Data Center (MSP3 North Metro) MN Brooklyn Park, Hennepin County running 30 MW
DataBank Eagan Data Center (MSP2) MN Eagan, Dakota County running 14 MW
DataBank Kansas City Data Center (MCI1) MO Kansas City, Jackson County running 10 MW
DataBank Twin Cities Edina Data Center (MSP1) MN Minneapolis, Hennepin County running 15 MW
TriTech Center Carrier Hotel Minneapolis MN Minneapolis, Hennepin County running 4 MW
Netrality and Digital Realty 210 North Tucker Carrier Hotel MO St. Louis, St. Louis city running 22 MW
Revitalization Unlimited Downtown Kansas City Data Center MO Kansas City, Jackson County proposed
EdgeConneX Minneapolis Data Center (EDCMSP01) MN Eden Prairie, Hennepin County running 5 MW
Edged Kansas City Data Center Campus (KCM01) MO Kansas City, Clay County being built 100 MW
Edged Council Bluffs Data Center Campus (Project Lola) IA Council Bluffs, Pottawattamie County approved 200 MW
Elk River Technology Park Data Center MN Elk River, Sherburne County proposed 33 MW
Enseva Cedar Rapids Data Center (Hiawatha) IA Hiawatha, Linn County running 8 MW
Flexential Minneapolis Chaska Data Center (MSP01) MN Chaska, Carver County running 9 MW
Former Star Tribune Printing Plant Data Center MN Minneapolis, Hennepin County cancelled
Google Cedar Rapids Data Center IA Cedar Rapids, Linn County being built
Google Council Bluffs Data Center Campus IA Council Bluffs, Pottawattamie County running 350 MW
Google Hermantown Data Center MN Hermantown, St. Louis County proposed
Google Kansas City Data Center Campus (Project Ranger) MO Kansas City, Jackson County being built
Google New Florence Data Center MO New Florence, Montgomery County being built
Google Pine Island Data Center (Project Skyway) MN Pine Island, Goodhue County approved
Google Salix Port Neal Data Center Proposal IA Salix, Woodbury County proposed
H5 Data Centers Twin Cities (Energy Park) MN St. Paul, Ramsey County running 6 MW
H5 Data Centers St. Louis MO St. Louis, St. Louis city running 8 MW
710 North Tucker Carrier Hotel (Globe Building St. Louis) MO St. Louis, St. Louis city running 10 MW
InfoBunker Underground Data Center (Boone) IA Boone, Boone County running 6 MW
Q'Levr Inver Grove Heights Data Center Campus MN Inver Grove Heights, Dakota County proposed
IP Pathways Urbandale Data Center (DSM1) IA Urbandale, Polk County running 4 MW
Iron Gate Data Centers Eagan MN Eagan, Dakota County running 6 MW
Iron Mountain Kansas City Data Center (KCM1) MO Kansas City, Jackson County running 9 MW
LightEdge Altoona Data Center 1 (DSM1) IA Altoona, Polk County running 8 MW
LightEdge Altoona Data Center 2 (DSM2) IA Altoona, Polk County running 10 MW
LightEdge Kansas City SubTropolis Data Center (KCI1) MO Kansas City, Clay County running 12 MW
Lincoln Rackhouse Kansas City Data Center MO Kansas City, Platte County running 6 MW
Meta Altoona Data Center Campus IA Altoona, Polk County running 400 MW
Meta Davenport Data Center Campus IA Davenport, Scott County being built 200 MW
Meta Kansas City Data Center Campus (Golden Plains) MO Kansas City, Jackson County running 150 MW
Meta Rosemount Data Center Campus MN Rosemount, Dakota County running 150 MW
Microsoft Van Meter Data Center Campus IA Van Meter, Dallas County being built 200 MW
Microsoft West Des Moines Data Center Campuses (Alluvion, Osmium, Ginger, Ruthenium, and Maple) IA West Des Moines, Polk County running 500 MW
Nebius AI Data Center Independence MO Independence, Jackson County approved 300 MW
Netrality Kansas City 1102 Grand Carrier Hotel MO Kansas City, Jackson County running 18 MW
Netrality St. Louis 900 Walnut Carrier Hotel MO St. Louis, St. Louis city running 12 MW
NOCIX North Kansas City Data Center (1530 Swift) MO North Kansas City, Clay County running 5 MW

A blank cell means no source states a figure.

All 23 regional markets in Dallas Fed WP 2606r1

Region States Tracked records (CC BY-NC 4.0) 2024 to 2025 wholesale price effect 2028 projected wholesale price effect
Northwest Power Pool (NWPP) WA, OR, ID, MT, NV, UT 105 15.4 percent (+$5.68 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 25.9 percent (+$7.77 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Virginia and Carolina North (SRVC-N) VA, NC 55 15.0 percent (+$5.22 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 27.6 percent (+$9.76 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
WECC California (CAMX) CA 69 8.6 percent (+$3.70 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 17.2 percent (+$6.96 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
MRO West (MROW) IA, MN, ND, NE, SD 76 12.1 percent (+$3.45 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 15.7 percent (+$4.59 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
ERCOT All (ERCT) TX 67 12.6 percent (+$3.15 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 28.0 percent (+$6.10 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Virginia and Carolina South (SRVC-S) NC, SC 46 7.5 percent (+$3.01 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 14.7 percent (+$4.94 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
WECC Southwest (AZNM) AZ, NM 41 8.6 percent (+$2.93 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 14.7 percent (+$4.32 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
WECC Rockies (RMPA) CO, WY 42 7.7 percent (+$2.51 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 12.2 percent (+$3.76 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC NYC and Westchester (NYCW) NY 13 5.2 percent (+$2.46 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 6.0 percent (+$2.63 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC Long Island (NYLI) NY 4 4.5 percent (+$2.40 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 5.3 percent (+$2.62 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
RFC West (RFCW) IN, OH, PA, WV, IL 134 6.7 percent (+$2.29 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 15.7 percent (+$5.11 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC Upstate New York (NYUP) NY 15 5.3 percent (+$2.14 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.7 percent (+$3.34 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Tennessee Valley (SRTV) KY, TN 27 5.8 percent (+$2.03 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.7 percent (+$2.91 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SPP North (SPNO) KS, NE, MO 8 6.5 percent (+$1.87 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.2 percent (+$2.54 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
RFC East (RFCE) DC, DE, MD, NJ, PA 127 5.1 percent (+$1.81 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 13.3 percent (+$4.61 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC South (SRSO) AL, GA 51 4.2 percent (+$1.47 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 5.3 percent (+$1.73 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Midwest (SRMW) IL, MO 28 4.7 percent (+$1.46 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 7.0 percent (+$2.28 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
MRO East (MROE) WI, MI 22 4.0 percent (+$1.39 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 7.9 percent (+$2.60 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC New England (NEWE) CT, MA, ME, NH, RI, VT 34 2.4 percent (+$1.28 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 3.1 percent (+$1.71 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
RFC Michigan (RFCM) MI 25 3.8 percent (+$1.27 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.8 percent (+$2.89 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SPP South (SPSO) OK, AR, LA, TX 16 3.1 percent (+$0.99 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 3.5 percent (+$1.12 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Mississippi Valley (SRMV) AR, LA, MS 26 3.0 percent (+$0.93 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 4.7 percent (+$1.48 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
FRCC All (FRCC) FL 33 1.0 percent (+$0.42 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 0.8 percent (+$0.34 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.

Wholesale price effects are third party estimates from Dallas Fed WP 2606r1 (opens in a new tab) (March 2026, revised October 2026). Tracked record counts are Data Center Record rows licensed under CC BY-NC 4.0.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

What researchers have found

These studies measure different things. Some model wholesale market prices. Some measure what households actually paid. Some model what would happen under a policy change. The record shows each one as the authors stated it and does not rank them.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data