Edged Energy is constructing a 3 building, 100 MW waterless cooling data center campus at 3420 North Arlington Avenue in Kansas City, Clay County, Missouri. It is being built; the record holds no sourced date for when it reached that stage.
How much water it would use and who would use it have not been disclosed.
Tap a pin for the data center, the parcel for its record
- This record: Being built, ringed
- data center
- Smaller pins: 24 other published records in Missouri
Details
- this record's location, ringed
- parcel outline, from the county parcel record
- city limits, U.S. Census Bureau, on a town level record
- county boundary
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
What is known
Each figure as its source gave it. The number in brackets is its place in the source list.
- Power it would draw
- 100 MW the developer's figure About 1 percent of New York City's summer peak demand in 2024.
- [2] edged.us
- Who leads it
- Edged Energy as stated by the source
- Undisclosed in public filings
- Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
- Edged Kansas City Data Center Campus (KCM01), capacity: 100 MW.
- New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
- 100 ÷ 10,245 = 0.01 (MW over MW).
Sources:
- Edged Energy (opens in a new tab)
- NYISO, 2025 Load and Capacity Data Report (Gold Book) (opens in a new tab), Table I-4a, Baseline Summer Non-Coincident Peak Demand, Historical and Forecast, page 26, Zone J, 2024 row (2024)
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Every field, with who said it and when (Researcher view)
Impact figures
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | 100 MW | the developer's figure | [2] edged.us (opens in a new tab) | October 27, 2026 |
| How much water it would use | [1] edged.us (opens in a new tab) | |||
| How loud it would be | ||||
| Jobs once it runs | ||||
| Tax it would pay each year |
The record's fields
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Edged Energy | as stated by the source | October 27, 2026 | |
| Who is constructing it | ||||
| How much land | ||||
| Buildings | 3 buildings | operator page, verified October 27, 2026 | [2] edged.us (opens in a new tab) | October 27, 2026 |
| Where its power comes from | ||||
| Grid connection | ||||
| How it is cooled | Closed loop liquid | as stated by the source | [1] edged.us (opens in a new tab) | October 27, 2026 |
| Cooling fluid |
A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
Still not public, and where it would show up
The record adds each the day a source gives it. Why these documents.
- Water use A state water right filing or a water supply agreement.
- Who would use it A lease announcement or a tenant named in a filing.
- Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.
What happened
No dated entry is on the record yet.
-
Read on October 27, 2026 (the day the page was read; it gives no date of its own)
Verified facility status from Missouri state agency permits, utility dockets, municipal planning filings, or operator campus specifications.
The site
The pin is the site's address.
- Where
- 3420 North Arlington Avenue, Kansas City, MO 64161, Kansas City, Clay County, Missouri [2] edged.us (opens in a new tab)
- How exactly it is located
- Exact, at the address
- The parcel
- No parcel outline in the public record
- Nearest homes
- Not computed for a record placed at a place center
- Nearest records
- LightEdge Kansas City SubTropolis Data Center (KCI1), 0.4 mi
- Google Kansas City Data Center Campus (Project Ranger), 2.6 mi
- NOCIX North Kansas City Data Center (1530 Swift), 5.5 mi
- NOCIX North Kansas City Clay Data Center, 5.5 mi
- Cube NA Data Center Kansas City (101 Holmes), 6.1 mi
Keep going
Questions about this project
5 questions answered from the record
How big is Edged Kansas City Data Center Campus (KCM01)?
-
The record has 2 measures of its size: 100 MW (the developer's figure, edged.us (opens in a new tab)) and 3 buildings (operator page, verified October 27, 2026, edged.us (opens in a new tab)). Its acreage is not disclosed.
Who is building Edged Kansas City Data Center Campus (KCM01)?
-
Edged Energy is the developer. No construction contractor is named on the record yet.
How much power and water does Edged Kansas City Data Center Campus (KCM01) say it needs?
-
Power: 100 MW (the developer's figure, edged.us (opens in a new tab)). Water: not disclosed by any source on file.
Where does Edged Kansas City Data Center Campus (KCM01) stand today?
-
It is being built; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
What has Kansas City or Clay County decided about it?
-
No decision by Kansas City or Clay County about data centers is on the record. The Clay County page and the Missouri scorecard list every rated row the day a person publishes one.
Sources
Primary documents
- Edged US: Edged Kansas City (3420 N Arlington Ave, Kansas City, MO) Facility Specifications (opens in a new tab), Edged US, January 1, 2026
Reporting
- Edged Kansas City Data Center Campus (KCM01) Official Disclosure (opens in a new tab), Edged Energy, query feed
2 sources on file.
About this data
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Edged Kansas City Data Center Campus (KCM01)
Cite this page
Data Center Record, "Edged Kansas City Data Center Campus (KCM01)", https://datacenterrecord.org/projects/edged-kansas-city-data-center-campus-mo. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Stage
- Being built
- Tier
- built from one source
- Tags
- Built from one source
- Coordinates
- 39.1568, -94.4785
- How the location is known
- Location from the site's street address.
- Location source
- https://edged.us/
- Coordinate source
- Edged Kansas City KCM01 specification
- Cooling
- Closed loop liquid
- How capacity was disclosed
- the developer's figure
- Capacity, if disclosed
- 100 MW, the developer's figure
- Published
- October 21, 2026
- Last verified
- October 27, 2026
- Undisclosed in public filings