● Being Built Announced May 20, 2026 · 3 Buildings · Google

Google New Florence Data Center

Street address Interstate 70 and State Highway 19, New Florence, MO 63363, Montgomery County verified address Exact, at the address [1] Google: Data center locations

Overview, regulatory gates and specifications

Google is constructing a hyperscale data center campus along Interstate 70 in New Florence, Montgomery County, Missouri. [10] Filings on the record specify 3 planned or operational buildings. [1] Google lists Google New Florence data center at New Florence, Missouri on its own page of data center locations, read September 14, 2026. [1]

Verified Site & Permit Summary
Verified address
Interstate 70 and State Highway 19, New Florence, MO 63363, Montgomery County verified address
Operator / developer
Google
Permit / registry ID
KOMU 8 on file [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
3 buildings operator page
[1] datacenters.google
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Google as stated by the source
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Katie Ottenweller

Google energy market development

DID Recorded statement at Leader Publications (September 16, 2026)
SAID Katie Ottenweller, Google energy market development, stated Google will pay for 100% of power costs to serve data center operations (September 16, 2026) kbia.org (opens in a new tab)

Geoff Marke

Missouri Office of Public Counsel chief economist

DID Recorded statement at Leader Publications (September 16, 2026)
SAID Geoff Marke, Missouri Office of Public Counsel chief economist, stated public counsel recommends community support be required for AI data center companies (September 16, 2026) kbia.org (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google New Florence Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 3 buildings agency filing [1] datacenters.google
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: being built (source date; the content gives no date of its own)

    Google announced 15 billion USD investment in May 2026 for hyperscale data center campus in New Florence, Missouri including 500 MW additional power capacity.

    [12] finance.yahoo.com

  2. (content date)

    Google committed $15 billion to a new AI hyperscale campus in Missouri, as noted in a 2026 North America Data Center Construction Market Report.

    [1] datacenters.google

  3. (content date)

    Montgomery County Commission unanimously approved tax incentive package for Google data center

    [11] komu.com

  4. · Status: approved (content date)

    Google announced $15 billion investment in data center in New Florence, Montgomery County, Missouri

    [10] komu.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google New Florence data center at New Florence, Missouri on its own page of data center locations, read September 14, 2026.

    [1] datacenters.google

8 corrections to this record

Every correction, with its reason
  1. · Publication status

    Held unplaced under the record's rules (October 13, 2026): the entry's words are about Alberta, and this record is in Missouri. Kept off the record, never deleted; it can be restored.

  2. · Record merge

    The same project on two records: the $15 billion Google data center at New Florence, Montgomery County, Missouri (history entry 583 of the retired record says so). Merged into the New Florence record on the editor's word, September 23, 2026; its sources and history moved with it, its name is kept as an alias, and its address redirects. merged google-missouri-ai-hyperscale-campus-mo into google-new-florence-data-center-mo: 3 sources moved, 0 duplicate sources dropped, "Google Missouri AI Hyperscale Campus" kept as an alias

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  6. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: komu.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: komu.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Missouri

Verified data center records in Missouri within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Amazon Montgomery County Data Center Proposal New Florence, Montgomery County Less than 1 mi Proposed Amazon Web Services 4 buildings
TierPoint St. Louis Millpark Data Center (Maryland Heights) Maryland Heights, St. Louis County 58 mi Running TierPoint 6 MW

Blank cell: not disclosed by any source on file.

Common questions about Google New Florence Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Google New Florence Data Center?

Google is the developer. No construction contractor is named on the record yet.

How much power and water does Google New Florence Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Google New Florence Data Center stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Google: Data center locations (opens in a new tab), Google, September 14, 2026

Reporting

  1. Missouri Data Center to Receive $15 Billion from Google, Largest Single Investment in State History - Construction Review (opens in a new tab), Construction Review, May 21, 2026, news outlet
  2. Google data center in rural Missouri plan raises tax and transparency questions - KCUR (opens in a new tab), KCUR, May 23, 2026, local outlet
  3. Google plans huge Missouri data center amid AI boom - Latest news from Azerbaijan (opens in a new tab), Latest news from Azerbaijan, May 21, 2026, news outlet
  4. Google Announces $15B Data Center Investment in Missouri - tedmag.com (opens in a new tab), tedmag.com, May 21, 2026, news outlet
  5. Timeline: Montgomery County considers data center proposals - KOMU 8 (opens in a new tab), KOMU 8, January 22, 2026, local outlet
  6. Google Invests Billions in New Missouri Data Center - Readers.id (opens in a new tab), Readers.id, May 24, 2026, news outlet
  7. 'Our fields are becoming buildings': $15B data center begins to reshape rural life in Missouri - kvue.com (opens in a new tab), kvue.com, May 24, 2026, local outlet
  8. Google Commits $15 Billion to Build Beside Amazon in Rural Missouri - globaldatacenterhub.com (opens in a new tab), globaldatacenterhub.com, May 31, 2026, news outlet
  9. Missouri governor and Google announce $15 billion data center in Montgomery County (opens in a new tab), KOMU 8, May 20, 2026, local outlet
  10. Montgomery County approves a tax incentive package for Google data center (opens in a new tab), KOMU 8, June 11, 2026, local outlet
  11. North America Data Center Construction Market Report 2026-2031 Now Available — Published as Google Commits $15B to New Missouri AI Hyperscale Campus - Yahoo Finance (opens in a new tab), Yahoo Finance, August 28, 2026, national outlet

12 sources on file.

Regional grid context

This site is in the SERC Midwest (SRMW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google New Florence Data Center", https://datacenterrecord.org/projects/google-new-florence-data-center-mo, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google New Florence Data Center", https://datacenterrecord.org/projects/google-new-florence-data-center-mo. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
38.9102, -91.4485
How the location is known
Location from the site's street address.
Location source
https://datacenters.google/locations/
Coordinate source
Montgomery County Chapter 100 industrial bond parcel
Location last verified
September 14, 2026
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google New Florence Data Center · 12 sources, 5 entries · basis and source tier on every row · verified October 27, 2026