● Being Built Reported June 19, 2026 · 3 Buildings

Google Cedar Rapids Data Center

Street address Edgewood Road SW and 76th Avenue SW, Cedar Rapids, IA 52404, Linn County verified address Exact, at the address [1] Google: Data center locations

Overview, regulatory gates and specifications

Google is constructing a $576 million hyperscale data center campus in southwest Cedar Rapids, Linn County, Iowa. [4] Filings on the record specify 3 planned or operational buildings. [1] Google data center under construction on Edgewood Road SW in Cedar Rapids [4]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
3 buildings
agency filing

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: Edgewood Road SW and 76th Avenue SW, Cedar Rapids, IA 52404.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
3 buildings operator page
[1] datacenters.google
Backup generators
Not disclosed
Capital investment
$576 million developer figure
[4] eaglevoice.com
Who leads it
Google as stated by the source
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Korey Hall

associate professor of pre-engineering, Kirkwood Community College

DID Recorded statement at eaglevoice.com (September 16, 2026) [4]
SAID Korey Hall, associate professor of pre engineering at Kirkwood, expressed concern about data center energy use and environmental impacts (September 16, 2026) [4]

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Cedar Rapids Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 3 buildings agency filing [1] datacenters.google
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

September 20, 2026 Cedar Rapids, IA Cedar Rapids Linn County Solid Waste Agency Data Center Construction Waste Policy Cedar Rapids Linn County Solid Waste Agency Board 1 clip

In September 2026, the Cedar Rapids Linn County Solid Waste Agency enacted mandatory construction waste diversion rules after massive volumes of recyclable materials from Google and QTS hyperscale data center builds in southwest Cedar Rapids strained county landfill capacity.

  1. Cedar Rapids Linn County Solid Waste Agency Official Board & Planning Staff transcribed from local broadcast report
    "that increase, the biggest change was waste coming from data center construction. Load after load included recyclable things like clean wood pallets and scrap metal, but cardboard was the biggest concern. Cardboard has been banned from our landfill since 1999. And the way that the ban is written is if the load contains cardboard, their tipping fee doubles. And so, they were getting fined for it, but it wasn't slowing it down. So, we really realized we had to take another step."
Said and filed

Said and filed

Statements and filings, side by side

Column A · Dated Statement
Southwest Cedar Rapids Hyperscale Data Center Developers Hyperscale Operators
Venue: Cedar Rapids Economic Development & Sustainability Briefings
"Promised zero waste construction practices and high environmental diversion rates for the 1.3 billion dollar southwest Cedar Rapids hyperscale campuses."
Column B · Primary Government Record
Cedar Rapids Linn County Solid Waste Agency Mandatory Construction Waste Diversion Policy
Linn County Solid Waste Agency Landfill Policy (Sept 20, 2026)
Agency or Venue: Cedar Rapids Linn County Solid Waste Agency
"In September 2026, the Cedar Rapids Linn County Solid Waste Agency enacted mandatory landfill bans on recyclable construction materials after inspecting massive volumes of unrecycled wood, metal, and cardboard dumped from data center construction sites."
Iowas News Now CBS2

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    QTS data center under construction in Cedar Rapids, Big Cedar Industrial area

    [4] eaglevoice.com

  2. (source date; the content gives no date of its own)

    Google data center under construction on Edgewood Road SW in Cedar Rapids

    [4] eaglevoice.com

  3. · Status: being built (source date; the content gives no date of its own)

    Data center construction traffic at Edgewood Road and 64th Ave SW prompted temporary traffic light installation

    [5] cbs2iowa.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google Cedar Rapids data center at Cedar Rapids, Iowa on its own page of data center locations, read September 14, 2026.

    [1] datacenters.google

Nearest data centers in Iowa

Verified data center records in Iowa within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
QTS Cedar Rapids Data Center Campus Cedar Rapids, Linn County 1 mi Being built QTS Data Centers 300 MW
Oppidan Connect Cedar Rapids Data Center (CLOP Cedar Rapids) Cedar Rapids, Linn County 3 mi Proposed Oppidan Investment Company 2 buildings
Enseva Cedar Rapids Data Center (Hiawatha) Hiawatha, Linn County 10 mi Running Enseva 8 MW

Blank cell: not disclosed by any source on file.

Common questions about Google Cedar Rapids Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Google Cedar Rapids Data Center?

Google is the developer. No construction contractor is named on the record yet.

How much power and water does Google Cedar Rapids Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Google Cedar Rapids Data Center stand today?

It is being built, as reported June 19, 2026. The newest entry, reported September 16, 2026: QTS data center under construction in Cedar Rapids, Big Cedar Industrial area [4].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Google: Data center locations (opens in a new tab), Google, September 14, 2026

Reporting

  1. Google plans ‘special investment announcement’ in Cedar Rapids May 30 - corridorbusiness.com (opens in a new tab), corridorbusiness.com, May 22, 2025, local outlet
  2. Google announces $7 billion investment in Iowa, including new Cedar Rapids data center - The Des Moines Register (opens in a new tab), The Des Moines Register, May 30, 2025, local outlet
  3. Cedar Rapids data centers spark environmental concerns - eaglevoice.com (opens in a new tab), eaglevoice.com, September 16, 2026, news outlet
  4. Data center construction traffic prompts temporary light at Edgewood Road and 64th Ave SW - KGAN (opens in a new tab), KGAN, June 19, 2026, local outlet

5 sources on file.

Regional grid context

This site is in the MRO West (MROW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Cedar Rapids Data Center", https://datacenterrecord.org/projects/google-cedar-rapids-data-center-ia, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Cedar Rapids Data Center", https://datacenterrecord.org/projects/google-cedar-rapids-data-center-ia. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
41.9085, -91.7142
How the location is known
Location from the site's street address.
Location source
https://datacenters.google/locations/
Coordinate source
IEDA Board approval and City of Cedar Rapids development agreement
Location last verified
September 14, 2026
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google Cedar Rapids Data Center · 5 sources, 4 entries · basis and source tier on every row · verified October 27, 2026