Iron Mountain Kansas City Data Center (KCM1)

Kansas City, Jackson County, MODeveloper: Iron Mountain Data CentersCensus GEOID 29095

Stage
Running
Power
9 MW
the developer's figure
Buildings
1 building
operator page, verified October 27, 2026
Undisclosed in public filings
Land, Water

Iron Mountain Data Centers operates the KCM1 underground colocation facility at 6301 Winchester Avenue in Kansas City, Jackson County, Missouri. It is running; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

1 hearing on the record, 2026

Last verified · 1 source, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Running, ringed
  • data center
  • Smaller pins: 24 other published records in Missouri
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
1 building operator page, verified October 27, 2026
[1] ironmountain.com
Power it would draw
9 MW the developer's figure About 0 percent of New York City's summer peak demand in 2024.
[1] ironmountain.com
Who leads it
Iron Mountain Data Centers as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Iron Mountain Kansas City Data Center (KCM1), capacity: 9 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 9 ÷ 10,245 = 0 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 9 MW the developer's figure [1] ironmountain.com (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Iron Mountain Data Centers as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 1 building operator page, verified October 27, 2026 [1] ironmountain.com (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Jackson County and Kansas City about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Independence case by case In Independence Missouri, voters recalled a City Council member who supported tax breaks for a proposed data center latimes.com (opens in a new tab)
Independence case by case Independence, MO residents held a recall vote related to a data center decision dailykos.com (opens in a new tab)
Independence case by case Missouri voters recalled councilman over Nebius data center tax break yahoo.com (opens in a new tab)
Independence case by case An Independence councilman was recalled by voters in his district after his vote for data center tax incentives kshb.com (opens in a new tab)
Independence case by case John Perkins, Independence councilman, was recalled after voting to approve a multibillion dollar data center kmbc.com (opens in a new tab)
Independence case by case Independence councilman faces recall over data center vote kctv5.com (opens in a new tab)
4 earlier decisions on the county's rows
DateWhoDecisionSource
Independence case by case An Independence council member faced a recall election after voting for a data center kshb.com (opens in a new tab)
Independence case by case Bly Road residents filed a 52 page lawsuit to stop the Independence AI data center project kshb.com (opens in a new tab)
Independence case by case Two of five city councilmembers who voted to give an AI data center 90% tax abatement were ousted in elections on April 8, 2026. kcur.org (opens in a new tab)
Independence case by case City council voted to give Nebius more than $6 billion in tax breaks in March 2026. kcur.org (opens in a new tab)
March 2, 2026 Independence, MO Independence City Council Nebius AI Factory Tax Abatement and Zoning Hearing Independence City Council 3clips

At a packed March 2, 2026 meeting, the Independence City Council debated Chapter 100 industrial revenue bonds and zoning for European cloud operator Nebius Group's multi billion dollar AI Factory campus as residents raised concerns over municipal power utility rates and water consumption.

  1. Rory Rowland, Mayor, City of Independence Elected Official transcribed from the official recording
    "BRIAN. BRYA I’VE COVERED A LOT OF THESE MEETINGS OVER THE YEARS, BUT THIS ONE WAS PACKED WAY MORE ATTENDANCE THAN ANY OF THE CITY COUNCIL MEETING I’VE EVER SEEN. THEY HAVE THE MAIN ROOM FULL. THEY’VE GOT AN OVERFLOW FULL. THE WHOLE PARKING LOT HAD WAS TERRIBLY FULL. PEOPLE HAD TO WALK REALLY FAR AWAY. THEY HAD 60 DIFFERENT PEOPLE SIGN UP TO SPEAK. THEY EACH GET UP TO FIVE MINUTES. SO THIS IS GOING TO BE A LONG NIGHT. TAKE A LOOK INSIDE FROM VIDEO WE SHOT EARLIER."
  2. Resident public comment Resident Public Comment transcribed from the official recording
    "NEVUS IS THE COMPANY. THEY’RE ASKING THE CITY TO TAKE LEGAL TITLE OF THIS DATA CENTER IF APPROVED, SO THAT THE DEVELOPMENT IS TAX EXEMPT. IT’S A 20 YEAR DEAL. THE COMPANY IS ASKING FOR A 90% TAX ABATEMENT FOR THOSE 20 YEARS. THAT WILL COVER. THE COMPANY WAS WANTING THAT TAX BREAK ON BOTH THE BUILDING AND THE SERVERS INSIDE THOSE SERVERS. THEY WILL REPLACE EVERY FIVE YEARS, THEY SAY. NOW, IN LIEU OF TAXES, NEBIA WILL PLAN TO PAY HUNDREDS OF MILLIONS OF DOLLARS TO THE CITY AND THE SCHOOL DISTRICT."
  3. Independence City Council Member Elected Official transcribed from the official recording
    "IT WILL COVER ABOUT 2,000,000FT OF WAREHOUSES. NOW, THE DATA CENTER WILL USE LOTS OF POWER, AND THAT WAS ONE POINT OF CONTENTION, EQUIVALENT TO ABOUT 500,000 NEW HOMES. ONCE COMPLETED, THE CENTER WILL EMPLOY ABOUT 130 FULL TIME JOBS. NOW, THOSE IN FAVOR SEE THIS AS A HUGE CONSTRUCTION PROJECT. GREAT FOR THE AREA. THOSE AGAINST HAVE CONCERNS ABOUT NOISE, UTILITY COSTS AND THOSE TAX CREDITS. THESE ARE JUST HYPOTHETICALS."

What happened

No dated entry is on the record yet.

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Missouri state agency permits, utility dockets, municipal planning filings, or operator campus specifications.

    [1] ironmountain.com

The site

The pin is the site's address.

The site map is at the top of the page.

Where
6301 Winchester Avenue, Kansas City, MO 64133, Kansas City, Jackson County, Missouri [1] ironmountain.com (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of Iron Mountain Kansas City Data Center (KCM1)
LAT 39.01086 / LON -94.50128 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Iron Mountain Kansas City Data Center (KCM1)?

The record has 2 measures of its size: 9 MW (the developer's figure, ironmountain.com (opens in a new tab)) and 1 building (operator page, verified October 27, 2026, ironmountain.com (opens in a new tab)). Its acreage is not disclosed.

Who is building Iron Mountain Kansas City Data Center (KCM1)?

Iron Mountain Data Centers is the developer. No construction contractor is named on the record yet.

How much power and water does Iron Mountain Kansas City Data Center (KCM1) say it needs?

Power: 9 MW (the developer's figure, ironmountain.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Iron Mountain Kansas City Data Center (KCM1) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Kansas City or Jackson County decided about it?

Independence (rated case by case): In Independence Missouri, voters recalled a City Council member who supported tax breaks for a proposed data center (reported September 14, 2026, latimes.com (opens in a new tab)); and Independence: Independence, MO residents held a recall vote related to a data center decision (reported September 3, 2026, dailykos.com (opens in a new tab)). 10 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Iron Mountain Kansas City Data Center (KCM1) Official Disclosure (opens in a new tab), Iron Mountain Data Centers, query feed

1 source on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Iron Mountain Kansas City Data Center (KCM1)", https://datacenterrecord.org/projects/iron-mountain-data-centers-iron-mountain-data-center-kansas-city-kcm1-kansas-city-mo, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Iron Mountain Kansas City Data Center (KCM1)", https://datacenterrecord.org/projects/iron-mountain-data-centers-iron-mountain-data-center-kansas-city-kcm1-kansas-city-mo. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
39.010862, -94.501281
How the location is known
Location from the site's street address.
Location source
https://www.ironmountain.com/data-centers/locations/kansas-city-data-center
Coordinate source
Iron Mountain KCM1 underground specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
9 MW, the developer's figure
Rating of the county's rows
Case by case
Published
October 21, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection

Researcher view · Iron Mountain Kansas City Data Center (KCM1) · 1 source, 1 entry, 10 decisions nearby · basis and source tier on every row · verified October 27, 2026