Data Center Record.
● 8 Facilities on Record 1 local rule row · 493 MW disclosed

Data centers in Jackson County, Missouri

Jackson County has 8 data centers on the record: 5 running, 1 being built and 2 proposed. No county rule about data centers is on the record for Jackson County itself; Independence, inside it, decides new data centers one at a time. The latest decision on the record: Independence, MO residents held a recall vote related to a data center decision (Independence), reported September 3, 2026.

The 8 data centers in Jackson County

Every Jackson County record 8 records · blank cell: not disclosed · sort by any column

Facility and county Stage Operator Power (MW) Latest entry Basis Located Tier Verified
Cube NA Data Center Kansas City (101 Holmes) Kansas City, Jackson County Running Cube NA Data Center Company 6 the developer's figure EPA registry 2 2026-10-27
DataBank Kansas City Data Center (MCI1) Kansas City, Jackson County Running DataBank 10 the developer's figure site 2 2026-10-27
Google Kansas City Data Center Campus (Project Ranger) Kansas City, Jackson County Being built Google site 1 2026-10-27
Iron Mountain Kansas City Data Center (KCM1) Kansas City, Jackson County Running Iron Mountain Data Centers 9 the developer's figure site 1 2026-10-27
Netrality Kansas City 1102 Grand Carrier Hotel Kansas City, Jackson County Running Netrality Data Centers 18 the developer's figure site 1 2026-10-27
Revitalization Unlimited Downtown Kansas City Data Center Kansas City, Jackson County Proposed Revitalization Unlimited A proposed data center would sit hundreds of yards away from Osawatomie State Hospital ca.news.yahoo.com (opens in a new tab) national outlet reported September 7, 2026 site 1 2026-11-06
Nebius AI Data Center Independence Independence, Jackson County Proposed Nebius Group 300 A multibillion dollar Nebius AI data center was proposed in Independence, Missouri, prompting a tax break vote and subsequent recall of Councilman John Perkins, as well as a lawsuit filed to stop the project. yahoo.com (opens in a new tab) national outlet September 3, 2026 the developer's figure site 4 2026-11-06
Meta Kansas City Data Center Campus (Golden Plains) Kansas City, Jackson County Running Meta 150 Building completion is a major step for KC area contractor and Meta data center project bizjournals.com (opens in a new tab) local outlet reported September 28, 2023 the developer's figure site 1 2026-11-06

Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.

The cities in Jackson County on the record (2)

2 of 2 cities have a record. A city without one is listed, not linked, until its first published record.

CityCensus GEOIDProjectsRulesHow it treats data centers
Kansas City293800070
Independence293500011case by case

A blank rating cell means no person has set one for the city. A city without a record is listed, not linked.

What Jackson County has decided 1 body, 6 decisions on the record

What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.

BodyLevelRatingIn force untilLatest actActsVerified
Independencecitycase by caseJohn Perkins, Independence councilman, was recalled after voting to approve a multibillion dollar data center. kmbc.com (opens in a new tab) local outlet Sep 2, 20266 acts on this row
Every act on the Independence row
  1. referendum

    Independence, MO residents held a recall vote related to a data center decision

    dailykos.com (opens in a new tab) national outlet

  2. referendum

    An Independence councilman was recalled by voters in his district after his vote for data center tax incentives

    kshb.com (opens in a new tab) local outlet

    Also reported by 2 sources

All 6 acts on the Independence record →

Last verified September 14, 2026.

62026-09-14

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.

March 2, 2026 Independence, MO Independence City Council Nebius AI Factory Tax Abatement and Zoning Hearing Independence City Council 3 clips

At a packed March 2, 2026 meeting, the Independence City Council debated Chapter 100 industrial revenue bonds and zoning for European cloud operator Nebius Group's multi billion dollar AI Factory campus as residents raised concerns over municipal power utility rates and water consumption.

  1. Rory Rowland, Mayor, City of Independence Elected Official transcribed from local broadcast report
    "Brian. Brya I’ve covered a lot of these meetings over the years, but this one was packed way more attendance than any of the city council meeting I’ve ever seen. They have the main room full. They’ve got an overflow full. The whole parking lot had was terribly full. People had to walk really far away. They had 60 different people sign up to speak. They each get up to five minutes. So this is going to be a long night. Take a look inside from video we shot earlier."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Nevus is the company. They’re asking the city to take legal title of this data center if approved, so that the development is tax exempt. It’s a 20 year deal. The company is asking for a 90% tax abatement for those 20 years. That will cover. The company was wanting that tax break on both the building and the servers inside those servers. They will replace every five years, they say. Now, in lieu of taxes, nebia will plan to pay hundreds of millions of dollars to the city and the school district."
  3. KMBC 9 Broadcast Report Broadcast Report transcribed from local broadcast report
    "It will cover about 2,000,000ft of warehouses. Now, the data center will use lots of power, and that was one point of contention, equivalent to about 500,000 new homes. Once completed, the center will employ about 130 full time jobs. Now, those in favor see this as a huge construction project. Great for the area. Those against have concerns about noise, utility costs and those tax credits. These are just hypotheticals."
Said and filed

Said and filed

Statements and filings, side by side

Tax Abatements Power & Grid Water Zoning
Column A · Dated Statement
Nebius Group & Independence Economic Development Proponents Developer & Municipal Proponents
Venue: Independence AI Factory Announcement & Tax Incentive Pitch
"Pitched the multi billion dollar Nebius AI Factory as a revenue generator that would modernize Independence Power and Light without burdening residential ratepayers."
Column B · Primary Government Record
Independence City Council Chapter 100 Tax Abatement & Municipal Utility Load Hearing
Independence City Council Hearing (March 2, 2026)
Agency or Venue: Independence City Council
"At the packed March 2, 2026 Independence City Council hearing, municipal records and resident testimony scrutinized multi decade Chapter 100 tax abatements, massive power generation requirements, and cooling water demand."
KMBC 9 News Kansas City

The rules across Missouri · Report missing data or a local act

What happened

  1. ReferendumIndependence

    Independence, MO residents held a recall vote related to a data center decision

  2. Ownership changeRevitalization Unlimited Downtown Kansas City Data Center

    Revitalization Unlimited acquired Western Newspaper Union building in 2025

  3. Now proposedRevitalization Unlimited Downtown Kansas City Data Center

    Revitalization Unlimited proposes 20 story highrise data center in Kansas City Quality Hill neighborhood designed by SOM

Missouri, year by year

Nearby places with records

22 miles away Clay County: 4 data centers on the record.
34 miles away Platte County: 1 data center on the record.
132 miles away Greene County: 1 data center on the record.
154 miles away Montgomery County: 2 data centers on the record.

Distances run between the centers the Census Bureau gives each place. Every Missouri county.

Disclosed figures

493 MW power

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedWithout a figureBasis
Power493 MW626 the developer's figure
Water, stated per day08
Water, stated per year08
Permanent jobs08
Tax each year08

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
No stated use8493 MW

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 8 tracked facilities in Jackson County are for.

How the facilities are cooled

No source on file states how any of the 8 tracked facilities in Jackson County are cooled.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Jackson County, Missouri", https://datacenterrecord.org/states/mo/jackson-county, updated November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Data center records in Jackson County, Missouri", https://datacenterrecord.org/states/mo/jackson-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Level
county
Census GEOID
29095
Census geography
County, Jackson County
Rating
Not rated

Researcher view · Jackson County, Missouri · 8 records, 1 rule row · Census GEOID 29095 · basis and source tier on every row · verified November 6, 2026

Download CSV JSON