Data Center Record.
States / Missouri

Missouri, year by year.

Every act on the record for Missouri, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.

The record by year

On the record as of October 27, 2026.

An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.

28 acts on the line for Missouri, from 123 dated lines in the records' histories and the scorecard. 37 more acts are dated only by the article that reported them and sit under their month. 11 lines report an act already listed. 47 lines are background, plans or statements. 8 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).

Narrow the acts
Kind
Topic
Developer

Each count is the number of lines on this page the chip keeps. Topics are matched from the words of each line and are a finding aid, not a fact about the event.

2026 26 acts on the line from 34 reports; 35 reported, dated only by the article; 46 lines of background, plans and statements

September 2026 13 acts on the line from 21 reports; 22 reported; 35 lines of background, plans and statements

  1. Approval Ferguson, Missouri

    Ferguson City Council voted 4-3 to approve a $1.8 billion data center hub project for a 217 acre former Emerson Electric campus on September 22, 2026.

    yahoo.com (opens in a new tab), national outlet

    2 more reports of this
    1. Reported September 23 Ferguson City Council voted 4-3 to give tax incentives for a tech hub and data center at the former Emerson campus stltoday.com (opens in a new tab)
    2. Reported September 23 Ferguson City Council voted 4-3 to approve tax incentives and redevelopment plan for data center at former Emerson campus stlpr.org (opens in a new tab)
  2. reported St. Louis Armory Data Center, St. Louis, Missouri

    TerraWatt plans to build a 120 megawatt data center in the old Famous Barr warehouse on Market Street as part of a planned technology district.

    stlpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Filing reported St. Louis Midtown Data Center, St. Louis, Missouri

    Developer David Lambiaso filed suit against the city's Board of Adjustment challenging two conditions imposed on the data center construction

    stlpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Moratorium Missouri

    Hundreds of Missourians rallied at the Capitol rotunda on Wednesday in support of a moratorium on data centers until state regulations are in place

    abc17news.com (opens in a new tab), local outlet

  5. Moratorium Missouri

    Around 200 people gathered at the Missouri Capitol on Wednesday to demand a statewide moratorium on hyperscale data center construction.

    kcur.org (opens in a new tab), local outlet

  6. Moratorium Missouri

    Advocacy groups from across Missouri held a demonstration against AI data centers on Wednesday, September 16, 2026, inside the Rotunda of the Missouri State Capitol, calling for a moratorium on data center development until proper regulations are in place.

    krcgtv.com (opens in a new tab), local outlet

    1 more report of this
    1. Reported September 16 Rally and march against data centers held at Missouri Capitol abc17news.com (opens in a new tab)
  7. Litigation Montgomery County, Missouri

    On September 15, 2026, Cole County judge dismissed the state of Missouri as a defendant but the case remains active against Montgomery County.

    abc17news.com (opens in a new tab), local outlet

  8. Approval Franklin County, Missouri

    Franklin County Commission approved rezoning requests for two large data center projects on September 15, 2026.

    firstalert4.com (opens in a new tab), news outlet

    3 more reports of this
    1. Reported September 15 Franklin County commissioners approved rezoning for Diamond Farms data center yahoo.com (opens in a new tab)
    2. Reported September 15 Franklin County commissioners approved rezoning for Crooked Creek data center yahoo.com (opens in a new tab)
    3. Sep 15 Franklin County Commissioners approved zoning regulations for two data center projects on Sept. 15, 2026 stltoday.com (opens in a new tab)
  9. Approval approved St. Louis Midtown Data Center, St. Louis, Missouri

    Land Clearance for Redevelopment Authority approved community benefit plan for TerraWatt data center at 3728 Market Street

    stlpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  10. Rate rule Missouri

    Brad Christ filed formal comments on Monday, Sept. 14, with the Missouri Public Service Commission calling on regulators to scrutinize Ameren's rate case.

    kctv5.com (opens in a new tab), local outlet

  11. Ordinance St. Louis, Missouri

    St. Louis Board of Aldermen unanimously approved Board Bill 49 on September 11, 2026, establishing a regulatory framework for data centers with three classes, setback requirements, electricity, water, noise, and renewable energy requirements.

    stl.news (opens in a new tab), local outlet

    1 more report of this
    1. Reported September 11 Board Bill 49 establishing zoning rules for data centers passed unanimously by St. Louis Board of Aldermen stlpr.org (opens in a new tab)
  12. Ordinance St. Louis, Missouri

    The Board of Aldermen approved citywide regulations on Friday

    stltoday.com (opens in a new tab), local outlet

  13. Desloge, Missouri

    City of Desloge held a town hall public forum on data centers on September 9, 2026

    dailyjournalonline.com (opens in a new tab), local outlet

    1 more report of this
    1. Reported September 9 Town hall meeting on data center regulation held in Desloge with about 150 residents in attendance mymoinfo.com (opens in a new tab)
Reported in September 2026, dated only by the article that carried them: 22 acts
  1. Statement Ferguson, Missouri

    Onder has agreed to donate $7.5 million to the Ferguson Neighborhood Improvement Program if the city approves incentives.

    stltoday.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Moratorium Missouri

    The No MO Dirty Data Centers Coalition requested a moratorium until regulations are in place to ensure data center costs are not shifted onto communities, power grid protections during high use times, and water resource protections for farmers

    dailyjournalonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Moratorium Missouri

    Scores of anti data center protesters filled Missouri Capitol Rotunda and marched demanding moratorium on data center development.

    abc17news.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

    1 more report of this
    1. Reported September 17 Protesters marched from the Missouri Capitol to the Governor's Mansion to deliver petitions calling for a moratorium. kcur.org (opens in a new tab)
  4. Litigation St. Louis, Missouri

    TerraWatt developer sued St. Louis Board of Adjustment

    independent.co.uk (opens in a new tab), international outlet (dated only by the report that carried it, so under the month of the report)

  5. Filing St. Louis Armory Data Center, St. Louis, Missouri

    The developer filed suit against the city this week; the company plans to build a data center as part of a planned technology district.

    stlpr.org (opens in a new tab), local outlet (in the days before the report that carried it, with no day of its own, so under the month of the report)

  6. Hearing Missouri

    Missouri Rural Crisis Center announced a people's hearing in the Capitol Rotunda for farmers, landowners and everyday Missourians to share how data center developments could affect them.

    komu.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  7. Hearing Missouri

    The House hearing on data centers was canceled

    stlpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  8. Statement Missouri

    The platform presented by organizers demands no new data centers until protections are in place for health and environmental issues, utility burdens, tax incentives and transparency throughout the process.

    krcgtv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  9. Approval Franklin County, Missouri

    Franklin County just approved land for a hyperscale data center next door to Watson's property this week.

    krcgtv.com (opens in a new tab), local outlet (in the days before the report that carried it, with no day of its own, so under the month of the report)

  10. Ordinance Franklin County, Missouri

    Franklin County commissioners voted to approve data center development regulations

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  11. Franklin County, Missouri

    Franklin County Commission adopted data center regulations with a 1,000 foot setback from inhabited homes, noise standards, construction hours, and developer fines of $20,000 per day with $10 million escrow requirement.

    firstalert4.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  12. Referendum Independence, Missouri

    In Independence Missouri, voters recalled a City Council member who supported tax breaks for a proposed data center

    latimes.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  13. Moratorium Benton County, Missouri

    Benton County data center blocked by moratorium

    morethanjustparks.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  14. Rate rule Missouri

    Missouri regulators adopted large load customer protections requiring minimum service commitments of at least 12 years, with a possible additional five year ramp up period.

    stl.news (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  15. Approval St. Louis, Missouri

    St. Louis aldermen approved rules governing where data centers can be built, noise and heat emissions limits, and renewable energy requirements

    stltoday.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

    1 more report of this
    1. Reported September 12 St. Louis aldermen approved a broad suite of rules governing data center development stltoday.com (opens in a new tab)
  16. Moratorium St. Louis, Missouri

    aldermen voted separately to approve bill prohibiting city tax breaks for data center projects

    stltoday.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  17. Statement Desloge, Missouri

    Several hundred regional residents attended and public comments largely opposed the idea

    dailyjournalonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  18. Moratorium Missouri

    Missouri residents used recalls, moratoriums, and 10 hour hearings to oppose data center plans

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  19. Referendum Independence, Missouri

    Independence, MO residents held a recall vote related to a data center decision

    dailykos.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  20. Referendum Missouri

    Missouri voters recalled a councilman over a Nebius data center tax break

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  21. Approval Independence, Missouri

    John Perkins, Independence councilman, was recalled after voting to approve a multibillion dollar data center

    kmbc.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  22. Referendum Independence, Missouri

    An Independence councilman was recalled by voters in his district after his vote for data center tax incentives

    kshb.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

    1 more report of this
    1. Reported September 3 Missouri voters recalled councilman over Nebius data center tax break yahoo.com (opens in a new tab)
Also on the record for September 2026, not acts of their own: 35 lines of background, plans and statements
  1. St. Louis, Missouri

    St. Louis recently passed new regulations for data centers including annual third party noise reports, acoustically treated enclosures, and 600 feet setbacks from schools, residential facilities or parks

    stlpr.org (opens in a new tab) (no act in the sentence)

  2. St. Louis Midtown Data Center, St. Louis, Missouri

    Armory data center in Midtown is approved before new St. Louis regulations and is regulated by conditional use permit with different sound policies

    stlpr.org (opens in a new tab) (a description, not an act)

  3. Ferguson, Missouri

    City Council will vote Tuesday night on a proposal to give $1.5 billion in tax incentives to developer Jim Onder to turn the 218 acre Emerson campus into a center for technology, energy innovation, advanced manufacturing and research.

    stltoday.com (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Missouri

    More than 370 Missourians from 53 counties traveled to the Capitol on Sept. 16 to demand a moratorium on data centers

    dailyjournalonline.com (opens in a new tab) (no act in the sentence)

  5. Missouri

    Advocates called for more protections as AI and data center development continue to grow across Missouri

    komu.com (opens in a new tab) (a statement; who said what is on the statements pages)

  6. Missouri

    A House hearing on data centers scheduled for the same day as the rally was canceled.

    kcur.org (opens in a new tab) (a plan or a schedule, not an act yet)

  7. Missouri

    Over 100 people rally at Missouri State Capitol on Wednesday calling for data center construction moratorium

    columbiamissourian.com (opens in a new tab) (no act in the sentence)

  8. Missouri

    Protesters cite concerns about noise, utility impacts, and water preservation as reasons for data center construction moratorium

    columbiamissourian.com (opens in a new tab) (no act in the sentence)

  9. St. Louis Armory Data Center, St. Louis, Missouri

    The project is planned at an 11 acre site in the old Famous Barr warehouse.

    stlpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  10. St. Louis Armory Data Center, St. Louis, Missouri

    The city's renewable energy requirements require the data center to use 2.4 megawatts of renewable energy.

    stlpr.org (opens in a new tab) (a description, not an act)

  11. Missouri

    Around 200 people crowded inside the Missouri Capitol rotunda for a rally Wednesday demanding a statewide moratorium on the construction of hyperscale data centers

    stlpr.org (opens in a new tab) (no act in the sentence)

  12. Missouri

    Protesters called for health and environmental protections, barring tax incentives for data center development, and requiring transparency and community buy in

    stlpr.org (opens in a new tab) (a statement; who said what is on the statements pages)

  13. St. Louis Midtown Data Center, St. Louis, Missouri

    Renewable energy must power 50% of facility in first five years, 100% within 10 years

    stlpr.org (opens in a new tab) (a description, not an act)

  14. St. Louis Midtown Data Center, St. Louis, Missouri

    Construction expected to begin August 2027 and be completed by late 2029

    stlpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  15. St. Louis, Missouri

    A city development board on Tuesday is expected to approve a benefits deal with TerraWatt

    stltoday.com (opens in a new tab) (a plan or a schedule, not an act yet)

  16. St. Louis, Missouri

    Major data centers in St. Louis must maintain a 600 foot setback from residential properties, schools, and public parks.

    stl.news (opens in a new tab) (a description, not an act)

  17. St. Louis, Missouri

    Standard data centers in St. Louis must maintain a 300 foot separation requirement from sensitive uses.

    stl.news (opens in a new tab) (a description, not an act)

  18. St. Louis, Missouri

    Micro data centers in St. Louis must maintain a 150 foot setback requirement.

    stl.news (opens in a new tab) (a description, not an act)

  19. St. Louis, Missouri

    Standard and major data centers in St. Louis must demonstrate that at least 25 percent of their electricity comes from renewable sources when operations begin.

    stl.news (opens in a new tab) (a description, not an act)

  20. St. Louis, Missouri

    St. Louis data centers must increase renewable electricity to 50 percent by the end of the fifth year of operation.

    stl.news (opens in a new tab) (a description, not an act)

  21. St. Louis, Missouri

    St. Louis data centers must reach 100 percent renewable electricity by the end of the tenth year of operation.

    stl.news (opens in a new tab) (a description, not an act)

  22. St. Louis, Missouri

    Rules address where new data centers can be built, noise levels and heat emissions

    stltoday.com (opens in a new tab) (a description, not an act)

  23. St. Louis, Missouri

    Rules require data center power to come from renewable energy sources

    stltoday.com (opens in a new tab) (a description, not an act)

  24. St. Louis, Missouri

    Rules allow operators to request waivers from city Board of Public Service when requirements cannot be met, with waivers extendable every two years

    stltoday.com (opens in a new tab) (a description, not an act)

  25. St. Louis, Missouri

    Separate bill prohibits city tax breaks for data center projects

    stltoday.com (opens in a new tab) (a description, not an act)

  26. St. Louis, Missouri

    New zoning rules classify data centers by size, dictate where they can be located, and impose renewable energy requirements plus light and sound restrictions

    stlpr.org (opens in a new tab) (a description, not an act)

  27. Ferguson, Missouri

    Ferguson councilmembers reintroduced legislation Wednesday for $1.5 billion in tax incentives and up to $22 billion in industrial revenue bonds for the Emerson campus data center redevelopment

    stlpr.org (opens in a new tab) (no act in the sentence)

  28. Ferguson, Missouri

    The proposal requires the developer to pay Ferguson Neighborhood Improvement Program $7.5 million over 10 years

    stlpr.org (opens in a new tab) (a description, not an act)

  29. St. Louis, Missouri

    Board of Aldermen Bill 24 recently advanced to establish a zoning framework for where data centers can operate and how the city addresses energy use, noise, lighting and compatibility with surrounding neighborhoods

    stltoday.com (opens in a new tab) (a description, not an act)

  30. St. Louis, Missouri

    The proposed Board of Aldermen Bill 24 is scheduled for a final board vote Friday

    stltoday.com (opens in a new tab) (a plan or a schedule, not an act yet)

  31. Desloge, Missouri

    Public comments called for a planning moratorium on data centers

    dailyjournalonline.com (opens in a new tab) (a statement; who said what is on the statements pages)

  32. Desloge, Missouri

    Desloge Board of Aldermen discussing probable regulations and moratorium for data centers

    mymoinfo.com (opens in a new tab) (no act in the sentence)

  33. Missouri

    Planned AI data center in Missouri city led to voter recall of council member

    nbcnews.com (opens in a new tab) (no act in the sentence)

  34. Benton County, Missouri

    Data center moratorium dispute is being litigated in Benton County courtroom

    ky3.com (opens in a new tab) (a description, not an act)

  35. St. Louis, Missouri

    St. Louis experiencing dispute over data center projects

    cbsnews.com (opens in a new tab) (no act in the sentence)

August 2026 1 act on the line; 11 reported; 10 lines of background, plans and statements

  1. Desloge, Missouri

    Board of Aldermen held meeting on August 10 to address data center concerns from residents

    dailyjournalonline.com (opens in a new tab), local outlet

Reported in August 2026, dated only by the article that carried them: 11 acts
  1. Litigation St. Louis, Missouri

    Residents and organizations filed a lawsuit against a proposed Midtown data center

    firstalert4.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  2. Moratorium Springfield, Missouri

    Springfield city council voted to put an administrative delay on any data center development

    ky3.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Springfield, Missouri

    A public engagement session on data centers was held in Springfield with hundreds of residents in attendance

    ky3.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Hearing Springfield, Missouri

    Springfield held community meetings about data center development

    ky3.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. Hearing Missouri

    Maryville City Council meeting held to hear resident concerns about White Cloud Acres data center and natural gas energy plant

    nwmissourinews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  6. Missouri

    Maryville City Council approved $9,780 contract amendment with HDR Engineering for impact study on White Cloud Acres data center effects

    nwmissourinews.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  7. Moratorium adopted Ralls County, Missouri

    Ralls County Commission approved a one year moratorium on data centers halting economic development applications until September 2027.

    muddyrivernews.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  8. St. Louis County, Missouri

    St. Louis County has established a draft framework with four categories of data centers - micro, small, standard, and major - with requirements increasing by power demands and community impacts.

    aol.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  9. Hearing St. Louis County, Missouri

    St. Louis County has held several public hearings on data centers since May 2026.

    aol.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  10. Springfield, Missouri

    Springfield temporarily delayed potential data center developments while studying community impacts

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  11. Litigation Independence, Missouri

    Bly Road residents filed a 52 page lawsuit to stop the Independence AI data center project

    kshb.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for August 2026, not acts of their own: 10 lines of background, plans and statements
  1. St. Louis, Missouri

    St. Louis Board of Aldermen set to discuss data center regulations

    fox2now.com (opens in a new tab) (a plan or a schedule, not an act yet)

  2. Springfield, Missouri

    Another public engagement session on data centers scheduled for Tuesday September 1st at 4:30 p.m.

    ky3.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Missouri

    Nodaway Says No, a group against local data center development, is active

    nwmissourinews.com (opens in a new tab) (a description, not an act)

  4. Independence, Missouri

    Independence councilman faces recall over data center vote

    kctv5.com (opens in a new tab) (a description, not an act)

  5. St. Louis County, Missouri

    St. Louis County Executive Sam Page and county leaders addressed data center concerns on Tuesday.

    aol.com (opens in a new tab) (no act in the sentence)

  6. St. Louis County, Missouri

    The largest data center facilities would be restricted to industrial districts and would require a conditional use permit or rezoning process.

    aol.com (opens in a new tab) (a plan or a schedule, not an act yet)

  7. Independence, Missouri

    An Independence council member faced a recall election after voting for a data center

    kshb.com (opens in a new tab) (no act in the sentence)

  8. Springfield, Missouri

    Public engagement sessions scheduled for Aug 27 at 5:30-7:30 p.m. and Sept 1 at 4:30-6:30 p.m.

    yahoo.com (opens in a new tab) (a plan or a schedule, not an act yet)

  9. Missouri

    Data centers in Missouri converted neighbors into activists across cities and farms

    spokesman.com (opens in a new tab) (no act in the sentence)

  10. St. Louis County, Missouri

    St. Louis County is considering data center guidelines

    spectrumlocalnews.com (opens in a new tab) (a plan or a schedule, not an act yet)

July 2026 2 acts on the line; 1 reported; 1 line of background, plans and statements

  1. reported Callaway County Data Center, Callaway, Missouri

    A data center in Callaway County is in initial planning stages

    komu.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. St. Louis Midtown Data Center, St. Louis, Missouri

    Permit upheld by Board of Adjustment in July

    independent.co.uk (opens in a new tab), international outlet (the month its own sentence names; no day is given; filed under Sep 17, 2026)

Reported in July 2026, dated only by the article that carried it: 1 act
  1. Moratorium adopted St. Charles County, Missouri

    St. Charles County officials approved a half year ban on data center projects

    stlpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for July 2026, not acts of their own: 1 line of background, plans and statements
  1. Callaway County Data Center, Callaway, Missouri

    Chamber of Commerce will share details at a meeting next week

    komu.com (opens in a new tab) (a plan or a schedule, not an act yet)

June 2026 3 acts on the line

  1. reported Amazon Montgomery County data center, Montgomery County, Missouri

    Amazon held a question and answer session about a data center campus in Montgomery County

    komu.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Approval Google New Florence data center, New Florence, Missouri

    Montgomery County Commission unanimously approved tax incentive package for Google data center

    komu.com (opens in a new tab), local outlet

  3. Groundbreaking Amazon Montgomery County data center, Montgomery County, Missouri

    Amazon data center in Montgomery County broke ground in June

    abc17news.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 17, 2026)

May 2026 3 acts on the line

  1. approved Google New Florence data center, New Florence, Missouri

    Google announced $15 billion investment in data center in New Florence, Montgomery County, Missouri

    komu.com (opens in a new tab), local outlet

  2. Ferguson, Missouri

    Ferguson City Council voted 3-3 with one abstention on a data center tax break proposal in May 2026

    stlpr.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 10, 2026)

  3. Expansion being built Google New Florence data center, New Florence, Missouri

    Google announced 15 billion USD investment in May 2026 for hyperscale data center campus in New Florence, Missouri including 500 MW additional power capacity.

    finance.yahoo.com (opens in a new tab), national outlet (the month its own sentence names; no day is given; filed under Aug 28, 2026)

April 2026 1 act on the line; 1 reported

  1. Independence, Missouri

    Two of five city councilmembers who voted to give an AI data center 90% tax abatement were ousted in elections on April 8, 2026.

    kcur.org (opens in a new tab), local outlet

Reported in April 2026, dated only by the article that carried it: 1 act
  1. St. Louis, Missouri

    St. Louis cleared a permit for the Armory data center as part of a $3 billion Innovation District

    ksdk.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

March 2026 1 act on the line

  1. Independence, Missouri

    City council voted to give Nebius more than $6 billion in tax breaks in March 2026.

    kcur.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Mar 1, 2026)

February 2026 1 act on the line

  1. Litigation Montgomery County, Missouri

    Preserve Montgomery County, LLC filed a case in February 2026 claiming the county violated Missouri's Sunshine Law in approving a data center.

    abc17news.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 18, 2026)

January 2026 1 act on the line

  1. Approval Missouri

    In January, elected officials for the city of Warrenton, Missouri, voted unanimously to approve a data center plan that would include two buildings each four times larger than a Costco warehouse or Walmart supercenter

    lailluminator.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 12, 2026)

2025 1 act on the line; 1 reported, dated only by the article

September 2025 No acts on the line; 1 reported

Reported in September 2025, dated only by the article that carried it: 1 act
  1. Hearing St. Louis, Missouri

    A hearing on the proposed Armory data center in the former Armory complex was postponed after the developer requested a delay

    ksdk.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

2025, no month given 1 act

  1. Missouri

    Missouri enacted legislation in 2025 requiring regulators to establish rates for large load customers, including data centers, to reflect those customers' costs.

    stl.news (opens in a new tab), local outlet (the year its own sentence names; filed under Sep 12, 2026)

2024 1 act on the line

2024, no month given 1 act

  1. Missouri

    City hired HDR Engineering in 2024 for $156,879 to carry out construction and planning for Water Treatment Plant

    nwmissourinews.com (opens in a new tab), local outlet (the year its own sentence names; filed under Aug 26, 2026)

2023 0 acts on the line; 1 line of background, plans and statements

September 2023 No acts on the line; 1 line of background, plans and statements

Also on the record for September 2023, not acts of their own: 1 line of background, plans and statements
  1. Meta Kansas City Data Center, Kansas City, Missouri

    Building completion is a major step for KC area contractor and Meta data center project

    bizjournals.com (opens in a new tab) (a description, not an act)

2022 0 acts on the line; 1 reported, dated only by the article

August 2022 No acts on the line; 1 reported

Reported in August 2022, dated only by the article that carried it: 1 act
  1. TierPoint St. Louis, St. Louis, Missouri

    TierPoint completed a new data center in St. Louis, Missouri

    datacenterdynamics.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools