● Running Reported September 28, 2023 · 4 Buildings

Meta Kansas City Data Center Campus (Golden Plains)

Street address 13201 NW 128th Street, Kansas City, MO 64163, Jackson County verified address Exact, at the address [2] plattecountycitizen.com

Overview, regulatory gates and specifications

Meta operates its Kansas City hyperscale data center campus at 13201 NW 128th Street in the Golden Plains Technology Park in Kansas City, Missouri. [2] Filings on the record specify disclosed capacity of 150 MW (the developer's figure), 4 planned or operational buildings. [2] Meta lists Meta Kansas City Data Center at Kansas City, Missouri on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [2]
150 MW
the developer's figure

Equivalent to ~124,500 U.S. homes (U.S. EIA 830 homes/MW baseline) · 7.2% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
4 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 13201 NW 128th Street, Kansas City, MO 64163.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
150 MW developer figure Equivalent to the continuous electricity demand of about 124,500 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 1 percent of New York City's summer peak demand in 2024.
[2] plattecountycitizen.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
4 buildings operator page
[1] datacenters.atmeta.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2024 (2 years)
Who leads it
Meta as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Meta Kansas City Data Center Campus (Golden Plains), capacity: 150 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 150 ÷ 10,245 = 0.01 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Meta
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Meta Kansas City Data Center Campus (Golden Plains).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 150 MW 150 MW the developer's figure [2] plattecountycitizen.com
Site Footprint (Acres)
Data Hall Buildings 4 buildings 4 operator page [1] datacenters.atmeta.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

March 2, 2026 Independence, MO Independence City Council Nebius AI Factory Tax Abatement and Zoning Hearing Independence City Council 3 clips

At a packed March 2, 2026 meeting, the Independence City Council debated Chapter 100 industrial revenue bonds and zoning for European cloud operator Nebius Group's multi billion dollar AI Factory campus as residents raised concerns over municipal power utility rates and water consumption.

  1. Rory Rowland, Mayor, City of Independence Elected Official transcribed from local broadcast report
    "Brian. Brya I’ve covered a lot of these meetings over the years, but this one was packed way more attendance than any of the city council meeting I’ve ever seen. They have the main room full. They’ve got an overflow full. The whole parking lot had was terribly full. People had to walk really far away. They had 60 different people sign up to speak. They each get up to five minutes. So this is going to be a long night. Take a look inside from video we shot earlier."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Nevus is the company. They’re asking the city to take legal title of this data center if approved, so that the development is tax exempt. It’s a 20 year deal. The company is asking for a 90% tax abatement for those 20 years. That will cover. The company was wanting that tax break on both the building and the servers inside those servers. They will replace every five years, they say. Now, in lieu of taxes, nebia will plan to pay hundreds of millions of dollars to the city and the school district."
  3. KMBC 9 Broadcast Report Broadcast Report transcribed from local broadcast report
    "It will cover about 2,000,000ft of warehouses. Now, the data center will use lots of power, and that was one point of contention, equivalent to about 500,000 new homes. Once completed, the center will employ about 130 full time jobs. Now, those in favor see this as a huge construction project. Great for the area. Those against have concerns about noise, utility costs and those tax credits. These are just hypotheticals."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: running (source date; the content gives no date of its own)

    Building completion is a major step for KC area contractor and Meta data center project

    [12] bizjournals.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Meta lists Meta Kansas City Data Center at Kansas City, Missouri on its own page of data center locations, read September 14, 2026.

    [1] datacenters.atmeta.com

Nearest data centers in Missouri

Verified data center records in Missouri within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Lincoln Rackhouse Kansas City Data Center Kansas City, Platte County 2 mi Running Lincoln Rackhouse 6 MW
Google Kansas City Data Center Campus (Project Ranger) Kansas City, Jackson County 13 mi Being built Google 4 buildings
NOCIX North Kansas City Clay Data Center North Kansas City, Clay County 13 mi Running NOCIX 4 MW
NOCIX North Kansas City Data Center (1530 Swift) North Kansas City, Clay County 14 mi Running NOCIX 5 MW
Edged Kansas City Data Center Campus (KCM01) Kansas City, Clay County 15 mi Being built Edged Energy 100 MW
LightEdge Kansas City SubTropolis Data Center (KCI1) Kansas City, Clay County 15 mi Running LightEdge Solutions 12 MW

Blank cell: not disclosed by any source on file.

Common questions about Meta Kansas City Data Center Campus (Golden Plains)

Answered directly from the verified filings and local actions on this page.

Who is building Meta Kansas City Data Center Campus (Golden Plains)?

Meta is the developer. No construction contractor is named on the record yet.

How much power and water does Meta Kansas City Data Center Campus (Golden Plains) say it needs?

Power: 150 MW (the developer's figure, plattecountycitizen.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Meta Kansas City Data Center Campus (Golden Plains) stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Meta: Our U.S. data center fleet (opens in a new tab), Meta, September 14, 2026

Reporting

  1. 'Historic' $800 million Meta (Facebook) facility coming to Platte/Clay county line - The Platte County Citizen (opens in a new tab), The Platte County Citizen, March 31, 2022, news outlet
  2. Meta Announces $800M Data Center in Kansas City - CommercialSearch (opens in a new tab), CommercialSearch, March 25, 2022, news outlet
  3. Meta confirms data center development plans for Kansas City, Missouri - Data Center Dynamics (opens in a new tab), Data Center Dynamics, March 24, 2022, news outlet
  4. Social media giant plans to occupy big Northland data center - The Business Journals (opens in a new tab), The Business Journals, March 10, 2022, local outlet
  5. Meta acquires 500 more acres in Diode’s Golden Plains park in Kansas City, Missouri - Data Center Dynamics (opens in a new tab), Data Center Dynamics, January 12, 2023, news outlet
  6. Exclusive: School district's tax windfall delayed from KC Meta data center - The Business Journals (opens in a new tab), The Business Journals, March 3, 2025, local outlet
  7. Meta Data Center In Kansas City Officially Operates, Ready To Serve Data Traffic - VOI.ID (opens in a new tab), VOI.ID, August 22, 2025, news outlet
  8. Meta chooses Kansas City for construction of $800M data center - KSHB 41 Kansas City (opens in a new tab), KSHB 41 Kansas City, March 24, 2022, local outlet
  9. Facebook parent Meta announces new $800M data center in Missouri - KSDK (opens in a new tab), KSDK, March 24, 2022, local outlet
  10. Meta's Northland data center leads to legal battle between father and son - Data Center Dynamics (opens in a new tab), Data Center Dynamics, July 10, 2024, news outlet
  11. Building's completion is a big step for KC area contractor and Meta project - The Business Journals (opens in a new tab), The Business Journals, September 28, 2023, local outlet

12 sources on file.

Regional grid context

This site is in the SERC Midwest (SRMW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Meta Kansas City Data Center Campus (Golden Plains)", https://datacenterrecord.org/projects/meta-kansas-city-data-center-mo, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Meta Kansas City Data Center Campus (Golden Plains)", https://datacenterrecord.org/projects/meta-kansas-city-data-center-mo. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
39.3245, -94.6482
How the location is known
Location from the site's street address.
Location source
https://datacenters.atmeta.com/
Coordinate source
Meta Kansas City Golden Plains Technology Park specification
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
150 MW, the developer's figure
Published
September 14, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Meta Kansas City Data Center Campus (Golden Plains) · 12 sources, 2 entries · basis and source tier on every row · verified November 6, 2026