Data centers in St. Louis County, Missouri
St. Louis County has 2 data centers on the record: 1 running and 1 proposed. St. Louis County has a scorecard row with no rating yet. The latest decision on the record: Ferguson City Council voted 4 to 3 to approve a $1.8 billion data center hub project for a 217 acre former Emerson Electric campus on September 22, 2026 (Ferguson).
The 2 data centers in St. Louis County
Every St. Louis County record 2 records · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Oppidan Berkeley Data Center Campus Berkeley, St. Louis County | Proposed | Oppidan Investment Company | EPA registry | 2 | 2026-10-27 | |||
| TierPoint St. Louis Millpark Data Center (Maryland Heights) Maryland Heights, St. Louis County | Running | TierPoint | 6 | the developer's figure | site | 1 | 2026-10-27 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
The cities in St. Louis County on the record (3)
| City | Census GEOID | Projects | Rules | How it treats data centers |
|---|---|---|---|---|
| Berkeley | 2904906 | 0 | ||
| Maryland Heights | 2946586 | 0 | ||
| Ferguson | 2923986 | 1 |
A blank rating cell means no person has set one for the city. A city without a record is listed, not linked.
What St. Louis County has decided 2 bodies, 5 decisions on the record
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| St. Louis County | county | not rated | St. Louis County has held several public hearings on data centers since May 2026. aol.com (opens in a new tab) national outlet Reported Aug 252 acts on this rowEvery act on the St. Louis County row
| 2 | 2026-09-10 | |
| Ferguson | city | Ferguson City Council voted 4 to 3 to give tax incentives for a tech hub and data center at the former Emerson campus. stltoday.com (opens in a new tab) local outlet Sep 23, 20263 acts on this rowEvery act on the Ferguson row
| 3 | 2026-09-23 |
Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
The rules across Missouri · Report missing data or a local act
What happened
-
ApprovalFerguson
yahoo.com (opens in a new tab) national outlet -
StatementFerguson
stltoday.com (opens in a new tab) local outlet -
HearingSt. Louis County
St. Louis County has held several public hearings on data centers since May 2026.
aol.com (opens in a new tab) national outlet -
Scorecard eventSt. Louis County
aol.com (opens in a new tab) national outlet -
Scorecard eventFerguson
stlpr.org (opens in a new tab) local outlet
Nearby places with records
Distances run between the centers the Census Bureau gives each place. Every Missouri county.
Disclosed figures
6 MW power
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 6 MW | 1 | 1 | 1 the developer's figure |
| Water, stated per day | 0 | 2 | ||
| Water, stated per year | 0 | 2 | ||
| Permanent jobs | 0 | 2 | ||
| Tax each year | 0 | 2 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 2 | 6 MW |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 2 tracked facilities in St. Louis County are for.
How the facilities are cooled
No source on file states how any of the 2 tracked facilities in St. Louis County are cooled.
About this data
Report a correction · Send a tip about St. Louis County · The rows here are part of the Missouri export.
Cite this page
Data Center Record, "Data center records in St. Louis County, Missouri", https://datacenterrecord.org/states/mo/st-louis-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Level
- county
- Census GEOID
- 29189
- Census geography
- County, St. Louis County
- Rating
- Not rated