● Running Reported March 4, 2015 · 1 Building

Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3)

Street address 511 11th Avenue South, Minneapolis, MN 55415, Hennepin County verified address Exact, at the address cologix.com (opens in a new tab)

Overview, regulatory gates and specifications

Cologix operates the MIN1, MIN2, and MIN3 interconnection and colocation suites inside the 511 Building carrier hotel at 511 11th Avenue South in Minneapolis, Hennepin County, Minnesota. [2] Filings on the record specify disclosed capacity of 15 MW (the developer's figure), 1 planned or operational building. [2] Cologix lists Cologix MIN1, Cologix MIN2, Cologix MIN3, Cologix MIN4, Cologix MIN5, Cologix NNJ2, Cologix NNJ3, Cologix NNJ4, Cologix SV1 at Minneapolis, Minnesota on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
15 MW
the developer's figure

Equivalent to ~12,450 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.7% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 511 11th Avenue South, Minneapolis, MN 55415.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
15 MW developer figure Equivalent to the continuous electricity demand of about 12,500 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 0.1 percent of New York City's summer peak demand in 2024.
cologix.com (opens in a new tab)
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
cologix.com (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2015 (11 years)
Who leads it
Cologix as stated by the source
Official project website
cologix.com (opens in a new tab) verified October 28, 2026
cologix.com (opens in a new tab)
Archived promotional websites
cologix.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3), capacity: 15 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 15 ÷ 10,245 = 0.0015 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Cologix
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 15 MW 15 MW the developer's figure
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Cologix acquired a data center from vXchnge in Minneapolis

    [5] datacenterknowledge.com

  2. · Status: running (source date; the content gives no date of its own)

    Cologix opened its third data center in Minneapolis

    [4] datacenterdynamics.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Cologix lists Cologix MIN1, Cologix MIN2, Cologix MIN3, Cologix MIN4, Cologix MIN5, Cologix NNJ2, Cologix NNJ3, Cologix NNJ4, Cologix SV1 at Minneapolis, Minnesota on its own page of data center locations, read September 14, 2026.

    [1] cologix.com

Nearest data centers in Minnesota

Verified data center records in Minnesota within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
T5 Data Centers Minneapolis (T5@Minneapolis) Minneapolis, Hennepin County Less than 1 mi Running T5 Data Centers 12 MW
TriTech Center Carrier Hotel Minneapolis Minneapolis, Hennepin County Less than 1 mi Running DCI Technology 4 MW
Atomic Data Minneapolis Data Center (MSP250) Minneapolis, Hennepin County Less than 1 mi Running Atomic Data 4 MW
Former Star Tribune Printing Plant Data Center Minneapolis, Hennepin County 1 mi Stalled or cancelled North Loop Redevelopment 1 building
H5 Data Centers Twin Cities (Energy Park) St. Paul, Ramsey County 5 mi Running H5 Data Centers 6 MW
DataBank Twin Cities Edina Data Center (MSP1) Minneapolis, Hennepin County 8 mi Running DataBank 15 MW

Blank cell: not disclosed by any source on file.

Common questions about Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3)

Answered directly from the verified filings and local actions on this page.

Who is building Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3)?

Cologix is the developer. No construction contractor is named on the record yet.

How much power and water does Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3) say it needs?

Power: 15 MW (the developer's figure, cologix.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3) stand today?

It is running, as reported March 4, 2015. The newest entry, reported June 1, 2024: Cologix acquired a data center from vXchnge in Minneapolis [5].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Cologix: Data centers (opens in a new tab), Cologix, September 14, 2026

Reporting

  1. Cologix Opens Third Minneapolis Data Center - DataCenterKnowledge (opens in a new tab), DataCenterKnowledge, March 5, 2015, news outlet
  2. Cologix Expands In Minnesota's Most Connected Building - DataCenterKnowledge (opens in a new tab), DataCenterKnowledge, May 31, 2024, news outlet
  3. Cologix opens doors to third data center in Minneapolis - Data Center Dynamics (opens in a new tab), Data Center Dynamics, March 4, 2015, trade press
  4. Cologix Acquires vXchnge Data Center in Midwest Interconnection Hub - Data Center Knowledge (opens in a new tab), Data Center Knowledge, June 1, 2024, trade press

5 sources on file.

Regional grid context

This site is in the MRO West (MROW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3)", https://datacenterrecord.org/projects/cologix-minneapolis-mn, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3)", https://datacenterrecord.org/projects/cologix-minneapolis-mn. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
44.971408, -93.25458
How the location is known
Location from the site's street address.
Location source
https://www.cologix.com/data-centers/minneapolis/
Coordinate source
Cologix 511 Building Minneapolis specification
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
15 MW, the developer's figure
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3) · 5 sources, 3 entries · basis and source tier on every row · verified October 27, 2026

Download CSV JSON