Plans to convert the former Star Tribune Heritage Landing printing plant at 800 North 1st Street in Minneapolis, Hennepin County, Minnesota, into a data center were cancelled. [4] Filings on the record specify 1 planned or operational building. [1] Legacy Investing terminated purchase agreement for former Star Tribune printing facility [8]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
James Jorgenson, an engineering drafting and design education assistant professor at Dunwoody College of Technology, said data centers affect daily life more than many people realize and it isn't just for AI.(September 5, 2026) [6]
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Former Star Tribune Printing Plant Data Center.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 1 building | agency filing [1] cbsnews.com | |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
Proposed redevelopment would have converted former printing facility into 20 megawatt data center
Filing (source date; the content gives no date of its own)
Legacy Investing withdrew land use application for proposed data center at former Star Tribune site
(source date; the content gives no date of its own)
Legacy Investing terminated purchase agreement for former Star Tribune printing facility
(source date; the content gives no date of its own)
Legacy Investing withdrew from a purchase agreement for a 20 megawatt data center at the former Star Tribune printing facility in the North Loop neighborhood.
(source date; the content gives no date of its own)
Site is 13 acres in North Loop
(source date; the content gives no date of its own)
Legacy Investing proposed 20 megawatt data center at former Star Tribune printing plant site
(source date; the content gives no date of its own)
Legacy Investing ended purchase agreement for former Star Tribune printing plant
Filing (source date; the content gives no date of its own)
Legacy Investing withdrew its application for a city conditional use permit and terminated its purchase agreement.
· cancelled Moratorium (source date; the content gives no date of its own)
The former Star Tribune printing plant in Minneapolis' North Loop neighborhood is in talks to become the city's latest data center. The site is under the city's 350 thousand square foot moratorium limit.
· proposed (content date)
Developers proposed a data center at the former Star Tribune printing plant in the North Loop neighborhood of Minneapolis, drawing organized resident opposition at community meetings.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Every correction on the record is on the corrections page.
Verified data center records in Minnesota within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Atomic Data Minneapolis Data Center (MSP250) Minneapolis, Hennepin County | Less than 1 mi | Running | Atomic Data | 4 MW |
| TriTech Center Carrier Hotel Minneapolis Minneapolis, Hennepin County | Less than 1 mi | Running | DCI Technology | 4 MW |
| T5 Data Centers Minneapolis (T5@Minneapolis) Minneapolis, Hennepin County | Less than 1 mi | Running | T5 Data Centers | 12 MW |
| Cologix Minneapolis Carrier Hotel Campus (MIN1 to MIN3) Minneapolis, Hennepin County | 1 mi | Running | Cologix | 15 MW |
| H5 Data Centers Twin Cities (Energy Park) St. Paul, Ramsey County | 6 mi | Running | H5 Data Centers | 6 MW |
| DataBank Twin Cities Edina Data Center (MSP1) Minneapolis, Hennepin County | 9 mi | Running | DataBank | 15 MW |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
North Loop Redevelopment is the developer. No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is cancelled, as reported September 5, 2026. The newest entry, reported September 12, 2026: Proposed redevelopment would have converted former printing facility into 20 megawatt data center [8].
13 sources on file.
This site is in the MRO West (MROW) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Former Star Tribune Printing Plant Data Center. Last verified November 6, 2026. https://datacenterrecord.org/projects/former-star-tribune-printing-plant-data-center-minneapolis-mn. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Former Star Tribune Printing Plant Data Center
Data Center Record, "Former Star Tribune Printing Plant Data Center", https://datacenterrecord.org/projects/former-star-tribune-printing-plant-data-center-minneapolis-mn. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.