Data Center Record.

Running Built from one source

DataBank Brooklyn Park Data Center (MSP3 North Metro)

Brooklyn Park, Hennepin County, MNDeveloper: DataBankCensus GEOID 27053

Stage
Running
Power
30 MW
the developer's figure
Buildings
2 buildings
operator page, verified October 27, 2026
Undisclosed in public filings
Land, Water

DataBank operates the MSP3 North Metro colocation data center campus at 8111 Oxbow Creek North in Brooklyn Park, Hennepin County, Minnesota. It is running; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

1 hearing on the record, 2026

Last verified · 2 sources, 1 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Running, ringed
  • data center
  • Smaller pins: 26 other published records in Minnesota
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
2 buildings operator page, verified October 27, 2026
Power it would draw
30 MW the developer's figure About 0 percent of New York City's summer peak demand in 2024.
Who leads it
DataBank as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. DataBank Brooklyn Park Data Center (MSP3 North Metro), capacity: 30 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 30 ÷ 10,245 = 0 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 30 MW the developer's figure databank.com (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it DataBank as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 2 buildings operator page, verified October 27, 2026 databank.com (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Hennepin County and Brooklyn Park about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Minneapolis restrictive The city council approved a temporary moratorium on data centers in most of the city yahoo.com (opens in a new tab)
Minneapolis restrictive Minneapolis Planning Commission will meet October 13 to consider new zoning ordinances for possible future data centers yahoo.com (opens in a new tab)
Minneapolis restrictive The Minneapolis City Council passed a six month ban on data centers larger than 350,000 square feet. mprnews.org (opens in a new tab)
Minneapolis restrictive The six month freeze in Minneapolis does not apply to downtown data centers that occupy less than 350,000 square feet. yahoo.com (opens in a new tab)
Minneapolis restrictive Minneapolis City Council passed a temporary freeze on new data center development in June 2026. yahoo.com (opens in a new tab)
Minneapolis restrictive North Loop residents held community meeting over data center cbsnews.com (opens in a new tab)
1 earlier decision on the county's rows
DateWhoDecisionSource
Minneapolis restrictive Minneapolis City Council halts new data center developments until November mndaily.com (opens in a new tab)
June 15, 2026 Minneapolis, MN Meta to build data center on former University of Minnesota land Minneapolis City Council 2clips

In Minneapolis, Hennepin County (MN), Minneapolis City Council and local residents debated municipal data center siting, utility infrastructure load, water consumption, and zoning rules during the June 15, 2026 session.

  1. Minneapolis City Council Officials and Speakers Elected Official auto captions, unchecked
    "CITY SUBURB, META, FACEBOOK'S COMPANY, IS COMING TO ROSEMOUNT PLANNING TO BUILD A DATA CENTER ALONG COUNTY ROAD 42 THAT IS JUST EAST OF DAKOTA COUNTY TECHNICAL COLLEGE. WCCO'S KRISTEN MITCHELL WAS AT THE ANNOUNCEMENT THIS MORNING AND HAS MORE . HI, KIRSTEN. >> Reporter: OFFICIALS ARE CALLING THIS $800 MILLION INVESTMENT A SIGNIFICANT WIN FOR ROSEMOUNT AND THE BROADER COMMUNITY. THIS PLOT OF LAND"
  2. Resident public comment Resident Public Comment auto captions, unchecked
    "GROW BUSINESSES. THIS PROJECT HAS BEEN UNDER WRAPS FOR YEARS, EVEN HAD A CODING CALLED PROJECT BIGFOOT HAD SOME COMMUNITY MEMBERS EXPRESS CONCERNS ABOUT THE SECRECY OF THIS PROJECT AS WELL AS THE DATA CENTER'S IMPACT ON NOISE, ENVIRONMENT, AND ELECTRICAL USAGE. EXPERTS SAY THEY LOOKED AT OTHER DATA CENTERS AND ARE WORKING WITH EXCEL TO MAKE SURE"

What happened

  1. · Status: being built (content date)

    DataBank broke ground on an 86,000 square foot data center in Brooklyn Park, Minnesota, its third facility in the state.

    [2] bizjournals.com

The full DataBank Brooklyn Park Data Center (MSP3 North Metro) timeline, in order

The site

The pin is the site's address.

The site map is at the top of the page.

Where
8111 Oxbow Creek North, Brooklyn Park, MN 55445, Brooklyn Park, Hennepin County, Minnesota [source] (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of DataBank Brooklyn Park Data Center (MSP3 North Metro)
LAT 45.14362 / LON -93.38580 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is DataBank Brooklyn Park Data Center (MSP3 North Metro)?

The record has 2 measures of its size: 30 MW (the developer's figure, databank.com (opens in a new tab)) and 2 buildings (operator page, verified October 27, 2026, databank.com (opens in a new tab)). Its acreage is not disclosed.

Who is building DataBank Brooklyn Park Data Center (MSP3 North Metro)?

DataBank is the developer. No construction contractor is named on the record yet.

How much power and water does DataBank Brooklyn Park Data Center (MSP3 North Metro) say it needs?

Power: 30 MW (the developer's figure, databank.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does DataBank Brooklyn Park Data Center (MSP3 North Metro) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. The newest entry, November 20, 2020: DataBank broke ground on an 86,000 square foot data center in Brooklyn Park, Minnesota, its third facility in the state. [2]

What has Brooklyn Park or Hennepin County decided about it?

Minneapolis (rated restrictive): The city council approved a temporary moratorium on data centers in most of the city (reported September 15, 2026, yahoo.com (opens in a new tab)); and Minneapolis: Minneapolis Planning Commission will meet October 13 to consider new zoning ordinances for possible future data centers (reported September 15, 2026, yahoo.com (opens in a new tab)). 7 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. EPA ECHO detailed facility report: Databank MSP3 (opens in a new tab), U.S. Environmental Protection Agency

Reporting

  1. DataBank breaks ground on 86,000-square-foot data center in Brooklyn Park, its third in Minnesota - The Business Journals (opens in a new tab), The Business Journals, November 20, 2020, query feed

2 sources on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "DataBank Brooklyn Park Data Center (MSP3 North Metro)", https://datacenterrecord.org/projects/databank-brooklyn-park-data-center-mn, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "DataBank Brooklyn Park Data Center (MSP3 North Metro)", https://datacenterrecord.org/projects/databank-brooklyn-park-data-center-mn. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
45.143622, -93.3858
How the location is known
Location from the site's street address.
Location source
https://www.databank.com/data-centers/minneapolis/
Coordinate source
DataBank MSP3 Brooklyn Park specification
Location source number
[1]
Location last verified
October 6, 2026
EPA registry id
110070945564
How capacity was disclosed
the developer's figure
Capacity, if disclosed
30 MW, the developer's figure
Rating of the county's rows
Restrictive
Published
September 28, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection