November 10, 2026
A permanent public ledger of 25 verified actions on the record. Each entry links directly to its underlying primary government document, council minutes, regulatory filing, or corroborated news report.
Opposition and Press Signals for November 10, 2026
National press investigations, local moratoriums, litigation and community ratepayer pushbackTaos County weighs 18-month preemptive pause on data centers (opens in a new tab)
The Taos County Commission discussed a draft ordinance to impose an 18 month moratorium on data center development while staff develop regulations for the industry.
-
Claire Wayner, Senior Associate, RMI
"Maybe they're upgrading a part of the grid that they were going to have to upgrade anyway because it's aging infrastructure. If that's the case, they should have to demonstrate that, and then maybe cross socialization makes sense. But, if that upgrade was not going to be built without the data center, without benefits modeling or just a demonstration of the benefits to the rest of the zone, it's difficult to make the claim that all ratepayers in that zone should pay for it." Said November 10, 2026, Interview with Utility Dive.
-
AnJanette Brush, Commissioner, Taos County Commission
"We have no protection right now for something that has pretty significant impacts on land, water, temperature, noise." Said November 10, 2026, Taos County Commission meeting.
-
Patrick Trujillo, Contract attorney, Taos County
"If anything, I think it frees us up." Said November 10, 2026, Taos County Commission meeting.
-
Don Walters, Mayor, City of Cuyahoga Falls
"We wanted to do something that was right-sized, so we didn't prohibit industry, but also protect everyone. And this is a good balance. A lot of communities are just doing outright bans. We think that is extreme. Might be great for their community, but we want the best of both worlds here." Said November 10, 2026, City of Cuyahoga Falls.
-
Don Walters, Mayor, City of Cuyahoga Falls
"We would be the ones that would have to approve that. When we put a strict limit on it, we know that we're capable of providing that and it won't affect our customers." Said November 10, 2026, City of Cuyahoga Falls.
-
Steve Stivers, President and CEO, Ohio Chamber of Commerce
"I think the lesson of the 2026 election was pretty clear, but I think it's being a little bit misconstrued. I think voters basically said they don't like the current business model of data centers. They want to make sure there's real benefits to them, their communities and the residents around them. It's never too late, but I think the industry does need to change its current business model. And I think that's the real lesson of 2026. I don't believe it to be an existential issue today, but if the business practices don't change, I think it will be an existential issue." Said November 10, 2026, Press statement regarding Ohio Chamber of Commerce data center report.
-
Ellen Miller, Chief Economic Development and Quantitative Analyst, Joint Legislative Audit and Review Commission
"Data center growth in the state has resulted in dramatic increases in spending estimates on the exemption beginning in fiscal year 2021." Said November 10, 2026, Legislative hearing before Virginia lawmakers.
-
SpaceX is behind proposed data center in Cochise County
SpaceX held a community meeting in Cochise County on a proposed 750 acre data center using 6,000 megawatts of energy at full buildout, its first facility in Arizona if approved.
-
Alberta's Gigawatt Play: Why Building Data Centers Means Building an Industry
Data Center West founder Vlad Oujegov discusses Alberta's transition from data center planning to construction, examining workforce, infrastructure and regulatory challenges as gigawatt class projects materialize.
-
Florida regulators reject Duke Energy’s data center plan as too risky for consumers
Florida regulators rejected Duke Energy's plan to provide data center power, citing inadequate consumer protections and bill increase risks.
-
Are data centers really paying their share? AES Indiana's Google deal highlights a thorny question
The Indiana Utility Regulatory Commission approved AES Indiana's plan to serve a 390 megawatt Google data center in Monrovia at an estimated project cost of $737 million, raising questions about cost allocation across ratepayers for regional grid upgrades.
power grid tax -
The Kraft Group wants to build a $16 billion data center campus in a small Central Mass. town
The Kraft Group proposed a 16 billion dollar 900 megawatt data center campus with 10 buildings in Sutton, Massachusetts, which would be the fourth largest in the United States if approved.
-
Severn data center expansion would add nearly 88,000 square feet
A proposed expansion of the Sandy Farm Data Center in Severn would add approximately 88,000 square feet, include 13 generators, clear wooded land, and is subject to Anne Arundel County review.
zoning land -
Hannah Pingree says Jay shouldn’t be data center ‘testing ground’ as project restarts
Maine governor elect Hannah Pingree said Jay should not be a data center testing ground before strong state regulations are in place, as the developer filed state permits for the former mill project.
-
Planning for Jay data center moves forward, but deal not yet final
Jay data center project revived as JGT2 Redevelopment and Sentinel Data Centers resume discussions toward a final agreement, with state environmental permitting underway and a public meeting tentatively planned for December.
-
Data center restrictions pass in Saginaw Township and Romulus
Saginaw Township approved a data center ordinance with noise, setback and cooling requirements, and Romulus enacted a 180 day moratorium on data center approvals.
-
Applied Digital is building in the only US town to say yes to data centers
Harwood, North Dakota rejected anti data center legislation in the 2026 midterm elections, the only US town to do so, with 75.6 percent voting against rules requiring independent reviews and public hearings for data center projects.
-
Poll: North Dakotans worry data centers will strain power, water
North Dakota poll found 76% of residents worried data centers will increase electricity bills and strain water resources, with 45% opposing AI data center development statewide.
-
Voters pushed back on data centers, but business group says Ohio rakes in revenue from them
The Ohio Chamber of Commerce reported that data centers contributed more than $9 billion to Ohio's gross domestic product last year and said the industry needs to change its business model following voter approval of restrictions in 21 communities.
-
Here’s how every data center-related ballot measure fared in Ohio
Ohio voters approved multiple local ballot measures restricting large data centers, with margins ranging from 53% to 87%, driven by concerns over electricity costs and water use.
-
CITY MEETING: Data center code interpretation vote postponed to Thursday
Salem City Council postponed its vote on whether the city's zoning code includes AI and hyperscale data centers to a special meeting on Thursday, November 12, to allow time to review written public testimony.
-
PPL advanced stage data center pipeline hits 35GW in Pennsylvania
PPL's Pennsylvania data center pipeline reached 35.3GW in Q3 2026, with 11.4GW under electric service agreements, and PPL agreed to supply 2GW to a QTS project in Salem Township.
-
Application filed for $8bn data center project in Quanah, Texas
Integra has filed an application for a 756MW data center campus in Quanah, Hardeman County, Texas with an estimated investment of $8 billion and construction planned from November 2026 through December 2028.
-
Forum highlights debate over data centers, public input in Utah County
At a public forum in Utah County, Volition's CEO defended its Spanish Fork data center project against concerns over emissions and water use, while a grassroots group pursued a referendum on data center ordinances.
-
Janesville passes ballot measure as part of national wave against data centers
Janesville voters approved a ballot measure requiring public referendum approval for developments exceeding $450 million at the former GM site, with 63% support, part of a national wave against data centers.