● Running Recorded November 21, 2025

Compass Loudoun County campus

Street address 42254 Thunderball Drive, Leesburg, VA 20175, Loudoun County permit coordinates Exact, the point of the EPA's facility record [3] EPA ECHO detailed facility report: Compass IAD Datacenter

Overview, regulatory gates and specifications

Compass Datacenters lists a data center at Loudoun County, Virginia among the sites it operates. [1] Compass Datacenters lists Compass Loudoun County campus at Loudoun County, Virginia on its own page of data center locations, read September 14, 2026. [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
2 generators permitted
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings
Not disclosed
Acreage not stated in public filings yet

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 42254 Thunderball Drive, Leesburg, VA 20175.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
2 generators (4 MW) permitted
[1] deq.virginia.gov
Capital investment
Not disclosed
Commissioned
Operational since 2018 (8 years)
Who leads it
Compass Datacenters as stated by the source
Permitted legal entity
Compass Datacenters, LLC what a permit allows
[1] deq.virginia.gov [3] echo.epa.gov
State air permit registration
74160 state air permit register
[1] deq.virginia.gov
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Compass Datacenters · Applicant / Shell LLC: Compass Datacenters, LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Compass Loudoun County campus.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators 2 units (4 MW) what a permit allows [1] deq.virginia.gov
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

2025 to 2026 hearings
September 15, 2026 Loudoun County, VA Loudoun County Board of Supervisors Data Center Pause Resolution Loudoun County Board of Supervisors 3 clips

The Loudoun County Board of Supervisors voted 7 to 1 with 1 abstention to direct county staff to draft a 12 month staggered pause on new data center applications while evaluating grid capacity and ratepayer protections.

  1. Phyllis Randall, Chair, and Juli Briskman, Supervisor, Loudoun County Board of Supervisors Elected Official transcribed from local broadcast report
    "it clear the measure was not a ban or a moratorium. She described it as a way to give the county time to craft new laws concerning the facilities and how they affect nearby communities. News 4's Jackie Bensen has the late breaking details. Tonight's vote directs board staff to draft a resolution that would pause data center applications for 12 months. This has obviously been"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "jobs. Just down the street. There's one family has four children. Young children all have got respiratory illnesses since that went up because there is a gas turbine generator that runs 24 over seven. We should not impose a pause on building data centers. Don't stop. Instead, raise the bar, hold these owners to account. Tell them that we want them to invest in our young people, in our trades, in our"
  3. NBC4 Washington Broadcast Report Broadcast Report transcribed from local broadcast report
    "Tell them that we want them to pay their own way for power, so that new investments in capacity don't lead to higher rates for our residents. That motion will pass 711, with Miss Umstead voting against it. And Mr. Kershner abstaining. The plan calls for the applications to be staggered. Each one would be paused for one year"
2019 to 2024 hearings
August 15, 2019 Leesburg, VA Data Center Alley: Computing Power of 10 Million Servers at Plug and Play Price Loudoun County Board of Supervisors 3 clips

Loudoun County Board of Supervisors hearing on Data Center Alley expansion, grid transmission strain, and backup diesel generator emissions (August 15, 2019).

  1. Leesburg Economic Development and Applicant Presentation Developer Representative transcribed from the official recording
    "of Dulles Airport in Virginia we're about 30 minutes west of Washington DC with the largest concentration of data centers and it works in the world data centers are where the internet lives everything we do on the internet or on our corporate networks is stored on servers in these data centers you know people that's what's the cloud the cloud is just other people's computers and those other people's computers are"
  2. Loudoun County Board of Supervisors Member Elected Official transcribed from the official recording
    "important initiative for enterprises around the world it makes a lot of sense to put your data scientists close to your data you want to be able to easily and rapidly manipulate large data sets we saw recently in the black hole simulation and experimentation that was done the way they did their data science and the way they did their analysis was by shipping via fedex large numbers of flash drives and hard drives containing"
  3. Resident public comment Resident Public Comment transcribed from the official recording
    "their data and that's fine if you've got a long time if you're not in a hurry to do your analysis if you've got years that's great but if you need to move the speed of business you need to be able to put your data on the wire and the only way to put your data on the wire is to go somewhere where there's enough capacity and to do it very very quickly to do it in seconds and minutes not in"
Said and filed

Said and filed

Statements and filings, side by side

Column A · Dated Statement
Phyllis Randall & Juli Briskman, Loudoun County Board of Supervisors Chair & Supervisor, Loudoun County Board of Supervisors
Venue: Loudoun County Industrial Zoning & Data Center Alley Policy Record
"Maintained industrial corridor zoning across Ashburn and Sterling supporting over 180 operating and planned hyperscale data center facilities before enacting Phase 1 by right restrictions."
Loudoun County Broadcast Record
Column B · Subsequent Recorded Position
Loudoun County Board of Supervisors 7 to 1 Vote Directing Staff to Draft a 12 Month Staggered Pause on Data Center Filings
Loudoun County Board of Supervisors Resolution (7 to 1 to 1 Vote) · September 15, 2026
Agency or Venue: Loudoun County Board of Supervisors
"On September 15, 2026, the Loudoun County Board of Supervisors voted 7 to 1 with 1 abstention directing staff to draft a 12 month staggered pause on new data center applications while evaluating grid capacity, residential electric rates, and backup generator emissions."
Loudoun County Broadcast Record
Column A · Dated Statement
Suhas Subramanyam U.S. Representative, Virginia 10th Congressional District
Venue: Congressional Legislative Briefing & Loudoun Now Record
"I have warned the data center industry: if we do nothing to protect ratepayers and neighborhoods from diesel backup generators and transmission costs, I think that a national moratorium will win."
Loudoun Now & Blue Virginia Timestamp 00:45
Column B · Primary Government Record
Responsible Data Center Siting Act Package & Virginia DEQ Diesel Backup Generator Variance Record
119th Congress Data Center Legislative Package (Sept 9, 2026) · Virginia DEQ Diesel Generator Permit Queue
Agency or Venue: U.S. House of Representatives & Virginia Department of Environmental Quality (DEQ)
"Primary federal legislative findings accompanying Representative Subramanyam's September 9, 2026 four bill package (Responsible Data Center Siting Act, Data Center Fair Share Act, Data Infrastructure Risk Reduction Act, and Data Infrastructure Energy Measurement and Standards Act) and Virginia DEQ air permit filings document over 4,000 permitted diesel backup generators across Loudoun and Prince William Counties."
NBC4 Washington
Column A · Dated Statement
Buddy Rizer and Loudoun Economic Development Officials Executive Director, Loudoun County Department of Economic Development
Venue: Loudoun County Data Center Alley Recruitment and Board Briefings
"Loudoun County Data Center Alley thrives on predictable by right industrial zoning and plug and play permitting, generating hundreds of millions of dollars in local tax revenue without burdening residential neighborhoods or straining grid reliability."
Loudoun County Economic Development
Column B · Subsequent Recorded Position
Loudoun County Board of Supervisors Zoning Ordinance Amendment Eliminating By Right Data Centers and Utility Substation Votes
Loudoun County CPAM and ZOA Elimination of By Right Data Center Uses (2025 to 2026)
Agency or Venue: Loudoun County Board of Supervisors
"Reversing two decades of by right industrial permitting, the Loudoun County Board of Supervisors amended the county zoning ordinance to require a Special Exception public hearing vote for all new data centers and utility substations following transmission line proliferation next to homes and schools."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: running (content date)

    Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to Compass Datacenters, LLC, registration 74160 (permit action 74160-3), Loudoun County, on November 21, 2025. The permit document authorizes 2 emergency backup generators totaling 4 MW of permitted backup generator rating at 42255, 42254, 42311 and 42310 Thunderball Drive, Leesburg, Virginia (Loudoun County).

    [1] deq.virginia.gov

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Compass Datacenters lists Compass Loudoun County campus at Loudoun County, Virginia on its own page of data center locations, read September 14, 2026.

    [2] compassdatacenters.com

Nearest data centers in Virginia

Verified data center records in Virginia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
STACK NVA06 Leesburg, Loudoun County Less than 1 mi Running STACK Infrastructure 1 building
Amazon Data Services Inc - IAD-667, IAD-668, IAD-669, IAD-670, and IAD-671 Leesburg, Loudoun County Less than 1 mi Proposed Amazon Web Services
Microsoft Compass Creek Data Center Leesburg, Loudoun County Less than 1 mi Proposed Microsoft
Vantage Data Centers Ashburn Ashburn, Loudoun County 3 mi Running Vantage Data Centers 3 buildings
SDC Capital Partners - Belmont Innovation Campus Ashburn, Loudoun County ~5 mi Proposed SDC Capital Partners
Amazon Data Services, Inc. IAD-114 IAD-115 Ashburn, Loudoun County ~5 mi Proposed Amazon Web Services

Blank cell: not disclosed by any source on file.

Common questions about Compass Loudoun County campus

Answered directly from the verified filings and local actions on this page.

Who is building Compass Loudoun County campus?

Compass Datacenters is the developer. No construction contractor is named on the record yet.

How much power and water does Compass Loudoun County campus say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Compass Loudoun County campus stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Virginia DEQ Air Permit 74160-3: Compass IAD Datacenter (Compass Datacenters, LLC) (opens in a new tab), Virginia Department of Environmental Quality, November 21, 2025
  2. Compass Datacenters: Data center markets (opens in a new tab), Compass Datacenters, September 14, 2026
  3. EPA ECHO detailed facility report: Compass IAD Datacenter (opens in a new tab), U.S. Environmental Protection Agency

3 sources on file.

Regional grid context

This site is in the SERC Virginia and Carolina North (SRVC-N) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Compass Loudoun County campus", https://datacenterrecord.org/projects/compass-loudoun-county-campus-va, last verified October 26, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Compass Loudoun County campus", https://datacenterrecord.org/projects/compass-loudoun-county-campus-va. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
39.10356, -77.55481
How the location is known
Location from an EPA facility record.
Location source
EPA ECHO Detailed Facility Report (FRS ID 110071344611) for Compass IAD Datacenter at 42254 Thunderball Drive, Leesburg, VA 20175.
Coordinate source
EPA ECHO FRS ID 110071344611
Location last verified
October 24, 2026
Published
September 14, 2026
Last verified
October 26, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Compass Loudoun County campus · 3 sources, 2 entries · basis and source tier on every row · verified October 26, 2026