"Maintained industrial corridor zoning across Ashburn and Sterling supporting over 180 operating and planned hyperscale data center facilities before enacting Phase 1 by right restrictions."
"On September 15, 2026, the Loudoun County Board of Supervisors voted 7 to 1 with 1 abstention directing staff to draft a 12 month staggered pause on new data center applications while evaluating grid capacity, residential electric rates, and backup generator emissions."