Meta
New buildings will use closed loop liquid cooling system with dry cooling requiring no water during normal operations
Eagle Mountain has 2 data centers on the record: 2 being built. Eagle Mountain has a scorecard row with no rating yet. The latest decision on the record: Eagle Mountain walked back its first tax hike but residents will still pay about double the old rate, August 22, 2026. Utah County's own decisions are on the Utah County page.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.
Eagle Mountain, Utah County · Meta
Latest, reported September 14, 2026: Meta first broke ground in 2018 kutv.com local outlet
Drag with one finger to move the map, pinch to zoom. Tap a pin for the data center, a county for its rules
2 data centers in Eagle Mountain: all being built. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.
What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.
Reported: the source's date; the item names no day of its own.
Eagle Mountain walked back its first tax hike but residents will still pay about double the old rate, reported August 22, 2026.
Eagle Mountain walked back its first tax hike but residents will still pay about double the old rate
Meta and Google received tax incentives or breaks for data centers in Eagle Mountain
Eagle Mountain raised property taxes 183%
· Meta Eagle Mountain Data Center
Broke ground: Meta expands Eagle Mountain data center with $2.5 million community investment kutv.com local outlet
· Eagle Mountain
Scorecard event: Eagle Mountain walked back its first tax hike but residents will still pay about double the old rate sltrib.com local outlet
· Eagle Mountain
Scorecard event: Meta and Google received tax incentives or breaks for data centers in Eagle Mountain sltrib.com local outlet
· Eagle Mountain
Scorecard event: Eagle Mountain raised property taxes 183% sltrib.com local outlet
· Meta Eagle Mountain Data Center
Broke ground: Solar farm is scheduled to be in service at the end of 2023 datacenterdynamics.com trade press
Campus annual water use will be less than typical golf course in region
The project would not include a long term significant employment base according to West Jordan city manager
Every Utah statement, by speaker
Meta
New buildings will use closed loop liquid cooling system with dry cooling requiring no water during normal operations
| Figure | Disclosed total | Disclosed | Not disclosed | Basis | |
|---|---|---|---|---|---|
| Power | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Water, stated per day | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Water, stated per year | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Permanent jobs | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Tax each year | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records |
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
| Use | Records | Power | Water | Jobs | Tax each year | |
|---|---|---|---|---|---|---|
| Not disclosed | 2 | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed: power, water, jobs, tax each year |
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
No source on file states what any of the 2 tracked facilities in Eagle Mountain are for.
No source on file states how any of the 2 tracked facilities in Eagle Mountain are cooled.
Data Center Record, "Data centers in Eagle Mountain, Utah County, Utah", https://datacenterrecord.org/states/ut/utah-county/eagle-mountain, updated October 4, 2026.
Data Center Record, "Data center records in Eagle Mountain, Utah County, Utah", https://datacenterrecord.org/states/ut/utah-county/eagle-mountain. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
The rows here are part of the Utah export.