The data center in Box Elder County
Every Box Elder County record1 record · blank cell: not disclosed · sort by any column
Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.
What Box Elder County has decided1 body, 26 decisions on the record
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
Body
Level
Rating
In force until
Latest act
Acts
Verified
Box Elder County
county
restrictive until December 7, 2026
2026-12-07
Ordinance imposing a 180 day moratorium on new data centers and data center power plants on unincorporated land.upr.org (opens in a new tab)local outlet · Jun 10, 2026 · 26 acts on this rowEvery act on the Box Elder County row
litigation
Kevin O'Leary filed response to defamation lawsuit filed in July by Alliance for a Better Utah and Elevate Strategies.
O'Leary Digital filed a response asking the 1st District Court in Brigham City to dismiss the lawsuit over Box Elder County's rejection of the Stratos referendum, arguing that the county's two Stratos resolutions were administrative and cannot be put to voters.
Defamation suit filed by Alliance for a Better Utah, Elevate Strategies, Joshua Kanter and Gabrielle Finlayson on July 15 alleging O'Leary defamed them by suggesting they had links to China.
Box Elder County commissioners unanimously passed an ordinance imposing a 180 day moratorium on new data centers and data center power plants on unincorporated land while the county studies zoning and development standards.
Box Elder County attorney Stephen Hadfield denies BEAR referendum applications, concluding approved resolutions were administrative actions not subject to referendum
Alliance for a Better Utah and five unnamed Box Elder County plaintiffs filed suit in 3rd District Court in Salt Lake City arguing that the approvals of the Stratos plans by the Military Installation Development Authority and Box Elder County commissioners violate the Utah Constitution, and asking that they be nullified. (alleged in the filing, not a finding)
Box Elder County Commission unanimously approved a resolution giving MIDA consent to create the Stratos project area on land owned by Department of Defense and Utah Trust Lands Administration
Thousands of Utahns submitted negative comments, and hundreds of Box Elder residents attended May 4 county commission meeting shouting down politicians.
Box Elder County commissioners voted unanimously to consent to the Stratos MIDA project area at a special meeting where about 1,100 people gathered and a referendum effort formed within days.
Box Elder County Commission adopted Ordinance 642 consenting to the Utah Inland Port Authority AgriTech Project Area near Garland and Tremonton for agricultural technology and manufacturing, a separate tax increment district distinct from the May 2026 Military Installation Development Authority Stratos data center project area in Hansel Valley.
Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.
May 4, 2026Tremonton, UTBox Elder County Commission Special Meeting at Box Elder County FairgroundsBox Elder County Commission4 clips
At a special meeting at the Box Elder County Fairgrounds in Tremonton attended by approximately 1,100 residents, Box Elder County Commissioners Tyler Vincent, Boyd Bingham, and Stan Summers announced no public comment would be taken, exchanged words with the crowd, walked off the stage while attendees chanted People over profit, and reconvened in a closed room via video call projected onto the arena screen to vote 3 to 0 approving Resolution 26-14 and the 40,000 acre Stratos data center project area interlocal agreement with the Military Installation Development Authority.
Tyler Vincent, Boyd Bingham, and Stan Summers, Box Elder County CommissionersElected Officialtranscribed from the official recording
"This is a special commission meeting to consider the interlocal agreement with the Military Installation Development Authority. We will not be taking public comment at this meeting today."
Boyd Bingham, Commissioner, Box Elder County CommissionElected Officialtranscribed from the official recording
"Grow up. For hell's sake, grow up."
Tyler Vincent, Commissioner, Box Elder County CommissionElected Officialtranscribed from the official recording
"We will not allow shouting, we will not allow cat calling. We expect you to be kind. Can you be quiet and let our citizens hear what needs to be said, please?"
Tyler Vincent, Boyd Bingham, and Stan Summers, Box Elder County CommissionersElected Officialtranscribed from the official recording
"People over profit! People over profit! All in favor of the resolution and interlocal agreement with MIDA say aye. Aye. Aye. Aye. Motion carries unanimously 3 to 0."
Kevin O'LearyChairman, O'Leary Ventures and O'Leary Digital (Stratos Developer)
Venue:CNN Newsroom Broadcast & Fox 13 News Utah
"Sustainability concerns around air, water use, heat, and noise pollution are at the heart of our proposal. The facility uses a closed loop cooling system that recirculates water with little to no ongoing water consumption."
CNN Broadcast Transcript & Fox 13 Utah Timestamp 04:12
Utah Division of Water Rights Change Application a55167 on Water Right 13-2
Change Application a55167 · Water Right 13-2 (O'Leary Digital Utah DC Sub I, LLC)
Agency or Venue:Utah Division of Water Rights
"Change Application a55167 on Water Right 13-2 filed by O'Leary Digital Utah DC Sub I, LLC in Hansel Valley seeks industrial groundwater withdrawal of 1,712.0 acre feet per year (equivalent to 1,528,767 gallons per day) for data center cooling and power generation."
Kevin O'LearyChairman, O'Leary Ventures and O'Leary Digital (Stratos Developer)
Venue:Fox News Broadcast & Social Media Statements
"Ninety percent of the protesters against the data center project were bused in from out of state with paid signs, and three Utah individuals opposing the project are funded by money moving through Arabella Advisors tracing back to China."
Box Elder County Clerk Referendum Petition on Resolution 26-14 (MIDA Stratos Project Area), 1st District Court Filing & June 25 Retraction
Resolution 26-14 Referendum Application · 1st District Court Petition · June 25, 2026 Retraction
Agency or Venue:Box Elder County Clerk, 1st District Court, and On Air Retraction Record
"Referendum petitions challenging Resolution 26-14 and the MIDA Stratos Project Area Interlocal Cooperation Agreement were filed May 11, 2026 by local Box Elder County registered voters organized as Box Elder Accountability Referendum and Box Elder County Alliance for Responsible Growth. On June 25, 2026, Kevin O'Leary issued a written retraction stating he had 'no evidence' linking Utah opponents to China, and Fox News anchor Maria Bartiromo issued an on air apology on June 26, 2026."
Venue:Utah Senate Correspondence, NBC News, and Moneywise
"On June 1, 2026, O'Leary called Senate President J. Stuart Adams' demand for a 75 percent reduction from 40,000 acres to 10,000 acres 'outrageous'; on June 4, 2026, the Utah Senate announced O'Leary agreed to a 75 percent reduction to 10,000 acres; on August 13, 2026, O'Leary stated the campus was cut by half to 20,000 acres."
Box Elder County Resolution 26-14 & MIDA Stratos Project Area Interlocal Agreement and Subsequent Engineering Filings
Box Elder County Resolution 26-14 · MIDA Stratos Project Area (40,000 Acres / 9 GW vs. 7.5 GW)
Agency or Venue:Box Elder County Commission & Military Installation Development Authority (MIDA)
"Resolution 26-14 and the MIDA Interlocal Cooperation Agreement adopted May 4, 2026 consent to an approximately 40,000 acre MIDA Project Area in Hansel Valley for up to 9 gigawatts of onsite natural gas generation (distinct from Box Elder County Ordinance 642 of December 17, 2025, which established the separate Utah Inland Port Authority AgriTech Project Area near Garland and Tremonton). Subsequent October 2026 water filings describe 11 data center clusters and 7.5 gigawatts of thermal power generation across 2,000 to 2,500 developed acres within a 20,000 acre boundary, while MIDA has not adopted an amended project area boundary resolution."
Venue:Box Elder County Commission Special Meeting at Tremonton Fairgrounds
"We will not be taking public comment at this meeting today... Grow up. For hell's sake, grow up... All in favor of the resolution and interlocal agreement with MIDA say aye. Aye. Aye. Aye. Motion carries unanimously 3 to 0."
Box Elder County Commission 180 Day Moratorium on Unincorporated Data Centers (Exempting MIDA Stratos Area)
Box Elder County 180 Day Data Center Moratorium Ordinance · June 10, 2026
Agency or Venue:Box Elder County Commission & Utah Public Radio (NPR)
"Five weeks after voting 3 to 0 via closed room video call to approve the 40,000 acre Stratos MIDA project area without public comment, Box Elder County Commissioners passed a 180 day moratorium on new data centers and data center power plants on unincorporated county land, while stating the moratorium does not apply to the Stratos project area already transferred to MIDA."
"Concerns about water and power use at the Box Elder County data center contain incorrect information. The project is built for this use, is right next to a natural gas pipeline so they can build their own power plant, and the state will not run out of water or power."
Agency or Venue:KUER 90.1 Utah (NPR) & Utah News Dispatch
"The approval process surrounding the Stratos project was not good. MIDA has had mission creep from its initial responsibilities and goals, and I will push legislation for major reform to MIDA, including a larger role for the governor's office and closed loop cooling requirements."
"That's never going to happen. The very first phase will be natural gas, but the other phases should not be. They should be nuclear, and they should be geothermal, and solar and other technology."
Column B · Primary Government Record
O'Leary Digital State Water Rights Filing and EmPower Analytics / NRDC Air Modeling of 7.5 GW to 9.0 GW Methane Gas RICE Buildout
Utah Division of Water Rights Change Application a55167 (Water Right 13-2) · EmPower Analytics Group Air Dispersion Report
Agency or Venue:Utah Division of Water Rights & EmPower Analytics Group for NRDC
"State filings by O'Leary Digital Utah DC Sub I, LLC specify a 7.5 gigawatt buildout across 15 blocks (500 MW each) powered by on site methane gas fired reciprocating internal combustion engines (RICE) fed via the Ruby Pipeline, with EmPower Analytics modeling showing up to 3,140 tons per year of PM2.5 and 5 to 45 premature deaths per year across a 9 GW gas scenario."
Wonder Valley's private gas generation and water recycling deliver grid independence without competing with Wasatch Front residential water or power demands.
Kevin O'Leary, Investor, Stratos Project / O'Leary Ventures · October 17, 2026 · paraphrased · FOX 13 (opens in a new tab)local outlet
Gov. Spencer Cox has called on the federal government to create more regulatory policy on AI, though the state is considering creating additional legislation itself
166 more on this page, one per speaker and claim; 181 statements in all
"The technology choices do change the size of harm a lot, but every gas scenario we evaluate harms health. In either scenario, if you are going to build a facility this size with methane gas, there are going to be health harms."
Hansel Valley residents and farmers voiced alarm over groundwater depletion from 1,712 acre-feet industrial pumping, unmitigated turbine noise from 15 natural gas generation blocks, and the county's refusal to put the zoning overlay to a public ballot pending 1st District Court review.
7.5 GW of thermal generation and 11 data center clusters cannot operate without massive evaporative consumption in an arid Great Salt Lake sub basin, and shifting 1,712 acre-feet of agricultural rights to industrial cooling in Hansel Valley directly threatens down gradient spring flows into the lake.
Closed loop cooling with 10% freshwater makeup from agricultural water right 13-2 preserves Hansel Valley aquifer levels while avoiding any direct Great Salt Lake tributary depletion.
Paul Palandjian, CEO of O'Leary Digital, stated that public sentiment matters and the Box Elder County project includes elements to address public concerns.
Humans First conducted the 29th stop of its nationwide Data Center Revolt tour in Brigham City on October 1, 2026, with the tour starting in Texas on September 12.
Paul Palandjian said 'The project is not on hold,' and that O'Leary Digital is in early design and engineering of the project's infrastructure, gas supply and power generation, with engineering, environmental and economic impact studies underway under guidelines set by the state of Utah and the Military Installation Development Authority.
Kevin O'Leary and Fox News seek dismissal of defamation lawsuit from Stratos opponents; argue statements about Chinese funding connections were protected speech
Zach Boyd said the U.S. does have a lead over China in AI, depending on how you measure the race, and the nation should be able to maintain it for some time
Larger hyperscale facilities generally support more permanent workers, particularly when they operate advanced computing equipment or include their own power generation infrastructure
President Donald Trump posted on Truth Social saying data centers will serve economic self interest and national security, telling supporters to 'let Data Reign' or risk being 'backwards and poor'
The article describes data center opposition as rooted in opposition to water rationing, spikes in electrical bills, and resource plunder affecting quality of life
Ryan Cooper of The American Prospect characterizes the data center rollout as reflective of Silicon Valley arrogance by billionaires promoting AI as revolutionary and requiring trillions in spending
Shon Hiatt, associate professor at USC, found investor owned utilities like Rocky Mountain Power experienced no effect on power prices from data center entry from 2020 to 2025
Trump warned that if Americans 'kill the Golden Goose' on data centers, 'you will have only yourselves to blame' and that China is happy about anti data center sentiment
Growing cross partisan grassroots opposition to the Stratos data center in Utah demanding agency, fairness, and accountability in development decisions
The thermal energy coming off the Stratos Project could be equivalent to 23 atomic bombs being deposited on this valley every day in the form of waste heat, potentially raising nighttime temperatures by as much as 12 degrees Fahrenheit
The project raises significant concerns regarding energy and water usage, potentially requiring billions of gallons annually in a state already facing drought conditions
Robert Davies, associate professor of physics at Utah State University, calculated the project's electricity consumption at more than double what the developers suggest
Texas Democratic gubernatorial candidate Gina Hinojosa asserted that Gov. Greg Abbott is too sympathetic to data centers and that there needs better balance between tech and community concerns
Pennsylvania Gov. Josh Shapiro shifted his stance from generally supporting data centers to placing restrictions after Republican opposition criticism, recently signing an executive order imposing new rules
Ohio Democratic Senate candidate Sherrod Brown is running an ad calling incumbent Sen. Jon Husted the 'face of data centers' for supporting tax breaks and economic benefits
Tim Davis, head of Utah's Department of Environmental Quality, told lawmakers the state has 'major gaps' in regulating potential impacts of new data centers, particularly heat and noise
Davis stated that the Department of Environmental Quality has not yet begun air quality permitting work for the Box Elder County Stratos project and that once it does, it will take a year just to obtain data on existing air quality before developers can apply
Jake Garfield, Utah Office of Energy Development Deputy Director, said adopting new water efficient technologies is necessary in a state with constrained water resources
Position note: Follows earlier support for Utah data center expansion, shifting in August 2026 toward calling for reform of the Military Installation Development Authority after the Stratos project controversy.
Context & source notes
Provenance: Paraphrased; content date; reported from elsewhere.
Rep. Jon Hawkins, R Pleasant Grove, chair of the Economic Development and Workforce Services Interim Committee, stated that lawmakers have received probably hundreds of emails on data centers and that it is a big concern
Tim Davis, commissioner of Utah's Department of Environmental Quality, noted that no single state agency can fully approve a data center on its own and showed lawmakers a chart displaying many layers of approvals required
Rep. Doug Fiefia, R Herriman, expressed concern about who constituents could hold accountable if something falls through the cracks in a data center approval process
Jessica Wiarda, Salt Lake City resident, expressed concerns about data center effects on wildlife, especially deer, and about lack of public information on the Stratos project before officials voted on it
Three fellows at the Aspen Institute's Aspen Policy Academy undertook research into data center growth in Utah and the Great Salt Lake water level as part of the 2024 Science and Technology Policy Fellowship
Feras Batarseh, Virginia Tech professor and AI lab director, said groundwater is connected to surface water and ten percent of the Great Salt Lake's water comes from groundwater
Curtis said the Stratos Project is a massive data center campus that sparked opposition in the state because of its magnitude and quick approval process through the Military Installation Development Authority
Curtis said he wants to work on bringing reliable, predictable measuring techniques at the federal level so the public can have access to standard metrics to determine whether projects are sustainable
Fox News journalist Maria Bartiromo apologized on behalf of Fox News on June 26 for airing unsubstantiated claims about Chinese ties to data center opponents
Kevin O'Leary clarified in a June 25 social media post that he has no evidence that Alliance for a Better Utah or Elevate Strategies are funded by China or the Chinese Communist Party
Utah Senator Todd Weiler apologized on social media on June 30, saying he was duped after posting earlier claims about Chinese funding of Alliance for a Better Utah
Heat generated by the Stratos data center complex could create a local heat island that raises daytime temperatures by five degrees Fahrenheit and nighttime temperatures by twenty eight degrees Fahrenheit
Utah Senate President Stuart Adams praised O'Leary's concessions, saying they address concerns and reduce effective project footprint by 75 percent, but opponent Brenna Williams expressed skepticism that Thursday's announcement represents meaningful change.
O'Leary committed to heat capture technology and independent scientific and engineering reviews of environmental impacts, water use, infrastructure demands and long term sustainability
Kevin O'Leary rejected Adams' demand for 75% reduction, calling it outrageous and comparing it to selling a house and being told to live in the upstairs toilet
Governor Spencer Cox said the Stratos Project will never be powered solely by natural gas; future phases should use nuclear, geothermal, and solar power
Tim Davis, commissioner of the Utah Department of Environmental Quality, stated the project must comply with federal Clean Air Act and Clean Water Act requirements and will require air quality permits for natural gas powered generators and diesel fired backup generators
Kevin O'Leary claimed three Utah individuals opposing the data center project were working against American national security and received financial support from China
Energy experts have calculated the Stratos project would raise Utah's emissions by as much as 64 percent, producing more carbon pollution than the state's entire transportation sector, The Salt Lake Tribune and Grist reported on May 18, 2026, in a story published through their partnership; the outlets did not name the experts.
"Ninety percent of the protesters at the Box Elder County meeting were bused in from out of state with paid signs, and three individuals opposing the Utah data center project are funded by money tracing back to China."
Position note: Retracted on June 25, 2026 in a written statement acknowledging no evidence linked Utah residents opposing the Stratos project to foreign funding.
Context & source notes
Provenance: Quoted; content date; reported from elsewhere.
Gabi Finlayson of Elevate Strategies denied being Chinese foreign operatives and said opposition focuses on impacts to electrical grid, water supply and Great Salt Lake
"That's never going to happen. The very first phase will be natural gas, but the other phases should not be. They should be nuclear, and they should be geothermal, and solar and other technology."
Thermal output from the Utah data center could raise daytime temperatures by five degrees Fahrenheit and nighttime temperatures by up to twenty eight degrees Fahrenheit
Utah Military Installation Development Authority stated the Stratos Project aligns with long term national defense, energy resilience, and economic development goals
Lee Perry, Box Elder County Commissioner, said the vote is not the end of the process and the project will be subject to continued oversight and regulatory review
Palandjian said the data center will use a modern closed loop cooling system with water and glycol that will use significantly less water than agriculture on the same plots of land
Governor Cox stated that concerns about water and power use contain incorrect information and the state will not allow centers to take all power or increase utility rates.
Governor Cox stated the project is built for this use, is right next to a natural gas pipeline so they can build their own energy, and is not next to somebody's house.
127 miles awayUtah County: 6 data centers on the record.
186 miles awayCarbon County: 1 data center on the record.
212 miles awayUintah County: 1 data center on the record.
Distances run between the centers the Census Bureau gives each place. Every Utah county.
Disclosed figures
7.5 GW power, water from 1 record, 4,850 jobs
Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.
Power, water, jobs and tax
Figure
Disclosed total
Disclosed
Without a figure
Basis
Power
7.5 GW
1
0
1 the developer's figure
Water, stated per day
1,528,767 gallons a day
1
0
1 the developer's figure
Permanent jobs
4,850 jobs
1
0
1 the developer's figure
Tax each year
0
1
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
Use
Records
Power
Water
Jobs
Tax each year
AI, type not stated
1
7.5 GW
1,528,767 gallons a day
4,850 jobs
Cloud
1
7.5 GW
1,528,767 gallons a day
4,850 jobs
Government and defense
1
7.5 GW
1,528,767 gallons a day
4,850 jobs
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each; 1 does here. Each cell is the sum over the records with that use, disclosed rows only. The power column adds up to 22.5 GW across the uses, more than the 7.5 GW disclosed in all, because a record with several uses is in each of its rows.
What the facilities are for
Use
Facilities
Share of facilities
Attributed MW
Share of attributed MW
AI, type not stated
1
100%
Cloud
1
100%
Government and defense
1
100%
Not split between uses
1
7.5 GW
100%
A blank cell means no source attributes power to that use.
1 facility in Box Elder County. 1 lists more than one use and counts under each, so the facility column can sum past the total. Capacity is attributed to a use only where a source states the share, or where a facility lists a single use. Nothing is divided by estimate.
How the facilities are cooled
Method
Facilities
Share of facilities
Closed loop liquid
1
100%
1 facility in Box Elder County. A facility carries one cooling method; nothing here is estimated.
Sources read for Box Elder County
1 source
1 source is read for Box Elder County. State and national sources are on the Utah page.
Agendas and notices
Box Elder County Commission agendas and minutes
Every feed, with its kind and tier
What is read for Box Elder County: feeds every four hours, pages daily. A headline from any of these becomes a record only after a person reads the source and publishes it.
FiguresOnly what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
LicenseData CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this pageData Center Record, "Data centers in Box Elder County, Utah", https://datacenterrecord.org/states/ut/box-elder-county, updated October 28, 2026.CSV · JSON
Data Center Record, "Data center records in Box Elder County, Utah", https://datacenterrecord.org/states/ut/box-elder-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.