Data Center Record.

The sourced public record of data center development.

States · Utah

Box Elder County

closed 1 data center project, 1 scorecard row

9 GW disclosed across 1 project. A rating belongs to the scorecard row for this county; the events beneath it are what it rests on.

Last verified

Projects on the record
1
waiting on permits
1
How much power is disclosed
9 GW
What officials said
0 statements
Sources read here
1

Every figure above is computed from the records on this page at build time. Power is summed only where a project disclosed it; nothing is estimated.

Map

Colors are how each place treats data centers, from open to closed; pins are projects, colored by where each stands. Tap once for the summary, again to open the record.

Details

Colors show how each city treats data centers, from open to closed, based on the rules it has passed. A state takes the color of its strictest rule. Grey means we have records there but no rule yet.

Pins are projects. The color says where each one stands, from rumored to running; the size says how much power it would use, where that has been disclosed. A hollow pin means we know the town but not the exact site.

Tap a state to see its counties and projects. Tap a pin for the quick facts, and tap again to open its full record.

Rating scale
  • Open green
  • Case by case yellow
  • Restrictive orange
  • Closed red
  • No published rating

A state's rating is the most restrictive published jurisdiction rating in the state. Ratings sit on the jurisdictions themselves in the state view. A county or city shaded grey has at least one record.

Status enum
  • rumored rumored
  • proposed proposed
  • waiting on permits permitting
  • approved approved
  • being built under_construction
  • running operational
  • stalled stalled
  • cancelled cancelled
  • approximate location (city or county centroid)

Pin radius is 7 pixels where capacity is not disclosed, and scales from 7 to 18 pixels between 0 and 1,000 MW where it is.

The outline is the U.S. Census Bureau boundary for Box Elder County. Pin color is status. Pin size is disclosed capacity. Hollow pins are approximate, placed at a city or county centroid because a more precise location is not in the public record.

What has been disclosed in Box Elder County

FigureDisclosed totalDisclosedNot disclosedBasis
Power9 GW101 the developer's figure
Water, stated per dayNot disclosed01
Water, stated per yearNot disclosed01
Permanent jobsNot disclosed01
Tax each yearNot disclosed01

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends. Nothing here is modeled or estimated by the record.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
AI, type not stated19 GWNot disclosedNot disclosedNot disclosed
Cloud19 GWNot disclosedNot disclosedNot disclosed
Government and defense19 GWNot disclosedNot disclosedNot disclosed

A record that lists several uses counts once under each; 1 does here. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

UseFacilitiesShare of facilitiesAttributed MWShare of attributed MW
AI, type not stated1100%Not disclosed
Cloud1100%Not disclosed
Government and defense1100%Not disclosed
Split between uses not disclosed19 GW100%

1 facility in Box Elder County. 1 lists more than one use and counts under each, so the facility column can sum past the total. Capacity is attributed to a use only where a source states the share, or where a facility lists a single use. Nothing is divided by estimate.

Projects

  • waiting on permitsStratos Project

    O'Leary Digital and the Military Installation Development Authority propose a data center campus with an onsite natural gas power plant on about 40,000 acres of unincorporated land in Hansel Valley, north of the Great Salt Lake, after Box Elder County commissioners consented to the MIDA project area on 2026-05-04.

    Box Elder County · 9 GW · Last verified September 13, 2026

Box Elder County, year by year

On the record as of September 13, 2026.

The chart counts what is on the record: 1 published project in Box Elder County, with 23 dated events, 2 of them jurisdiction actions. A project counts in a year by the status its history shows at the end of that year, and its capacity, water and noise figures are the ones disclosed for it now, applied to every year it is on the record. Capacity is summed only where a source disclosed it; the count of projects without a disclosed figure sits beside every sum. A year with nothing on it has nothing on the record yet, which is not the same as nothing having happened.

Milestones Projects on the record at year end 0 1 Disclosed capacity at year end, MW 0 5,000 2023 2024 2025 2026, Announced, proposed, permitting or approved: 1 project, 9 GW disclosed 2026, Announced, proposed, permitting or approved: 1 project, 9 GW disclosed 2026
Operational Under construction Announced, proposed, permitting or approved Milestone, one dot per flagged event Tap a year or a dot to open that year. Stalled and cancelled projects stay in the yearly totals below and off the bars.
Narrow the events in every year
Topic
Use

Topics are matched from the words of each summary and are a finding aid, not a fact about the event. Counts in the chart do not change with the filters.

2026 1 project on the record at year end, 23 events

At the end of 2026

Operational
0 projects, 0 MW disclosed
Under construction
0 projects, 0 MW disclosed
Announced, proposed, permitting or approved
1 project, 9 GW disclosed

Capacity, by how it was disclosed

Not disclosed for any of the 1 project on the record.

Water, by how it was disclosed

Not disclosed for any of the 1 project on the record.

Noise, by how it was disclosed

Not disclosed for any of the 1 project on the record.

Sound levels are not summed. The range is the lowest and highest level a source stated.

Events in 2026

  1. May 4, 2026 (content date) Other Box Elder County (jurisdiction): Box Elder County commissioners voted unanimously to consent to the Stratos MIDA project area at a special meeting where about 1,100 people gathered and a referendum effort formed within days. Source, local outlet
  2. May 4, 2026 (content date) Otherapproved Stratos Project : Box Elder County commissioners voted unanimously for two resolutions consenting to a Military Installation Development Authority project area for a 40,000 acre data center campus with its own natural gas power plant, at a special meeting attended by about 1,100 people. Source, local outlet . Developer O'Leary Digital
  3. May 5, 2026 (content date) Otherwaiting on permits Stratos Project : The first water right change application for the project, filed by the landowner to move water from irrigation to industrial use, was withdrawn, and the company said it would refile with additional supporting information. Source, local outlet . Developer O'Leary Digital
  4. May 8, 2026 (content date) Otherwaiting on permits Stratos Project : Kevin O'Leary told CNN that developers had invested about 20 million dollars, would seek letters of intent from tenants and further investment for a project that could cost more than 100 billion dollars, and aimed to have the first gigawatt operating within two years. Source, local outlet . Developer O'Leary Digital
  5. May 11, 2026 (content date) Otherwaiting on permits Stratos Project : The Box Elder Accountability Referendum filed two referendum applications to put the county commission's approval before voters, which would require 5,422 signatures in 45 days if the applications were accepted. Source, local outlet . Developer O'Leary Digital
  6. May 14, 2026 (content date) Otherwaiting on permits Stratos Project : Demonstrators rallied at the Utah Capitol and delivered a letter signed by about 6,000 people asking Governor Spencer Cox to take binding action on the Great Salt Lake and the project. Source, local outlet . Developer O'Leary Digital
  7. May 22, 2026 (content date) Otherwaiting on permits Stratos Project : The second water right change application for the project, filed by Murray Hollow L.C., was withdrawn by a notice dated May 22 that gave no reason, after nearly 700 protest letters had been filed against it. Source, local outlet . Developer O'Leary Digital
  8. May 23, 2026 (content date) Otherwaiting on permits Stratos Project : Hundreds of people rallied on the Utah Capitol steps demanding a halt to the project, with speakers raising air quality, greenhouse gas and water supply concerns. Source, local outlet . Developer O'Leary Digital
  9. May 28, 2026 (content date) Otherwaiting on permits Stratos Project : Box Elder County Attorney Stephen R. Hadfield rejected three referendum applications, finding the commission's resolutions were administrative actions that cannot be referred to voters under Utah law. Source, local outlet . Developer O'Leary Digital
  10. June 10, 2026 (content date) Other Box Elder County (jurisdiction): Box Elder County commissioners unanimously passed an ordinance imposing a 180 day moratorium on new data centers and data center power plants on unincorporated land while the county studies zoning and development standards. Source, local outlet
  11. June 10, 2026 (content date) Otherwaiting on permits Stratos Project : Box Elder County commissioners passed a 180 day moratorium on new data centers and data center power plants on unincorporated county land, which county officials said does not apply to the Stratos project area under MIDA's land use authority. Source, local outlet . Developer O'Leary Digital
  12. Reported August 13, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : O'Leary agreed to cut the project by half to 20,000 acres after public outcry Source, query feed . Developer O'Leary Digital
  13. Reported August 13, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : The project was initially proposed at 40,000 acres Source, query feed . Developer O'Leary Digital
  14. Reported August 19, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : Stratos project was originally pitched at up to 9 gigawatts across a 40,000 acre site near the Great Salt Lake Source, query feed . Developer O'Leary Digital
  15. August 20, 2026 (content date) Otherwaiting on permits Stratos Project : Governor Spencer Cox said at his monthly news conference that the Stratos approval process was not good and that he would push legislation to reform the Military Installation Development Authority, including a larger role for the governor's office. Source, local outlet . Developer O'Leary Digital
  16. Reported August 20, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : Litigation over referendum challenging Box Elder County Commission's vote to consent to MIDA project area has complicated future of Stratos Source, query feed . Developer O'Leary Digital
  17. Reported August 20, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : Cox proposed changes to MIDA in 2025 but they did not pass Source, query feed . Developer O'Leary Digital
  18. August 20, 2026 (content date) Otherwaiting on permits Stratos Project : The Military Installation Development Authority gave an initial green light to the Stratos data center project in Box Elder County Source, query feed . Developer O'Leary Digital
  19. Reported August 21, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : Another fire is burning north of the Bear River Migratory Bird Refuge Source, query feed . Developer O'Leary Digital
  20. Reported August 21, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : The Salt Wells Fire is burning in Box Elder County's Hansel Valley, where the Stratos data center and energy campus is planned Source, query feed . Developer O'Leary Digital
  21. Reported August 27, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : A hyperscale data center was proposed in Box Elder County and faced opposition Source, query feed . Developer O'Leary Digital
  22. Reported September 1, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : The Stratos Project is set to take over 20,000 acres of desert brush and farmland in Box Elder County, abutting the Great Salt Lake Source, query feed . Developer O'Leary Digital
  23. Reported September 1, 2026 (source date; the content gives no date of its own) Otherwaiting on permits Stratos Project : Kevin O'Leary, backed by investor, plans to rename Hansel Valley to Wonder Valley Source, query feed . Developer O'Leary Digital

Close 2026

2025 0 projects on the record at year end, 0 events

At the end of 2025

Operational
0 projects, 0 MW disclosed
Under construction
0 projects, 0 MW disclosed
Announced, proposed, permitting or approved
0 projects, 0 MW disclosed

Capacity, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Water, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Noise, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Sound levels are not summed. The range is the lowest and highest level a source stated.

Events in 2025

No dated event on the record in 2025.

Close 2025

2024 0 projects on the record at year end, 0 events

At the end of 2024

Operational
0 projects, 0 MW disclosed
Under construction
0 projects, 0 MW disclosed
Announced, proposed, permitting or approved
0 projects, 0 MW disclosed

Capacity, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Water, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Noise, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Sound levels are not summed. The range is the lowest and highest level a source stated.

Events in 2024

No dated event on the record in 2024.

Close 2024

2023 0 projects on the record at year end, 0 events

At the end of 2023

Operational
0 projects, 0 MW disclosed
Under construction
0 projects, 0 MW disclosed
Announced, proposed, permitting or approved
0 projects, 0 MW disclosed

Capacity, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Water, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Noise, by how it was disclosed

Not disclosed for any of the 0 projects on the record.

Sound levels are not summed. The range is the lowest and highest level a source stated.

Events in 2023

No dated event on the record in 2023.

Close 2023

The same chart for the whole state is at Utah, year by year, and for every state at the national timeline.

Scorecard

Each rating is derived from the dated events beneath it, never typed in. Events are listed newest first with their source.

  • Box Elder Countycountyclosed

    Box Elder County commissioners consented to the Stratos MIDA project area on 2026-05-04 over organized opposition, then on 2026-06-10 passed a 180 day moratorium on new data centers and data center power plants on unincorporated land that the county says does not reach the Stratos area.

    Ordinance imposing a 180 day moratorium on new data centers and data center power plants on unincorporated land, June 10, 2026. upr.org, local outlet

    1. June 10, 2026 (content date)moratoriumclosed

      Box Elder County commissioners unanimously passed an ordinance imposing a 180 day moratorium on new data centers and data center power plants on unincorporated land while the county studies zoning and development standards.

      upr.org, local outlet

    2. May 4, 2026 (content date)agreementrestrictive

      Box Elder County commissioners voted unanimously to consent to the Stratos MIDA project area at a special meeting where about 1,100 people gathered and a referendum effort formed within days.

      utahnewsdispatch.com, local outlet

    Last verified September 13, 2026

Sources read for Box Elder County

What the ingestion Worker reads for Box Elder County: feeds every four hours, pages daily. A headline from any of these becomes a record only after a person reads the source and publishes it. State and national sources are on the Utah page.

Agendas and notices

This page as data CSVJSON
Cite this page

Data Center Record, "Data center records in Box Elder County, Utah", https://datacenterrecord.org/states/ut/box-elder-county. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change

The rows here are part of the Utah export. Know of a filing, docket or project in Box Elder County that is missing? Send a tip.

For researchers
Place id
us/ut/box-elder-county
Level
county
Census GEOID
49003
Rating value
red