Data centers in Pataskala, Ohio
Pataskala has 1 data center on the record; it is proposed. Pataskala has a scorecard row with no rating yet. The latest decision on the record: Pataskala city council unanimously voted to block construction of a proposed 200 megawatt three building data center, September 23, 2026. Licking County's own decisions are on the Licking County page.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
The data center in Pataskala
Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.
Pataskala data center proposal
Pataskala, Licking County
Latest, reported August 23, 2026: Aligned Data Centers expects to employ about 111 people long term thereportingproject.org local outlet
- Land
- Not disclosed
- Power
- Not disclosed
- Water
- Not disclosed
- Tenant
- Not disclosed
Where
Drag with one finger to move the map, pinch to zoom. Tap a pin for the data center, a county for its rules
1 data center in Pataskala: proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.
What Pataskala has decided
1 body, 4 decisions on the recordWhat the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.
Reported: the source's date; the item names no day of its own.
- Pataskalacity
Pataskala city council unanimously voted to block construction of a proposed 200 megawatt three building data center, reported September 23, 2026.
4 acts on this row
- denial
Pataskala city council unanimously voted to block construction of a proposed 200 megawatt three building data center.
- denial
Planning and Zoning Commission rejected the proposal 5-2
- denial
Pataskala City Council voted against data center proposal
Also reported by 1 source
- yahoo.com national outlet
- denial
Pataskala Planning and Zoning Commission voted 5 to 2 on June 3 to recommend rejection of Aligned Data Centers site plan
- denial
What happened
-
· Pataskala
Denial: Pataskala city council unanimously voted to block construction of a proposed 200 megawatt three building data center. spectrumnews1.com local outlet
-
· Pataskala
Denial: Planning and Zoning Commission rejected the proposal 5-2 yahoo.com national outlet
-
· Pataskala
Denial: Pataskala City Council voted against data center proposal nbc4i.com local outlet
-
· Pataskala data center proposal
Now reported: Aligned Data Centers proposes 200 megawatt facility in three buildings on 89 acres thereportingproject.org local outlet
-
· Pataskala
Denial: Pataskala Planning and Zoning Commission voted 5 to 2 on June 3 to recommend rejection of Aligned Data Centers site plan thereportingproject.org local outlet
The county and nearby counties
Disclosed figures
nothing disclosed by 1 record
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Not disclosed | Basis | |
|---|---|---|---|---|---|
| Power | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Water, stated per day | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Water, stated per year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Permanent jobs | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Tax each year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record |
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year | |
|---|---|---|---|---|---|---|
| Not disclosed | 1 | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed: power, water, jobs, tax each year |
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 1 tracked facility in Pataskala is for.
How the facilities are cooled
No source on file states how any of the 1 tracked facility in Pataskala is cooled.
Cite this page
Data Center Record, "Data centers in Pataskala, Licking County, Ohio", https://datacenterrecord.org/states/oh/licking-county/pataskala, updated September 23, 2026.
Cite this page
Data Center Record, "Data center records in Pataskala, Licking County, Ohio", https://datacenterrecord.org/states/oh/licking-county/pataskala. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
The rows here are part of the Ohio export.
For researchers
- Place id
- us/oh/licking-county/pataskala
- Level
- city
- Census GEOID
- Not disclosed
- Rating value
- Not disclosed
- Scale word
- Not disclosed