Data Center Record.
Census GEOID: 18141 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary sources

● Running First recorded October 21, 2026 · 1 Building

Aunalytics South Bend Data Center (AUSB)

Street address 1440 Ignition Drive, South Bend, IN 46601, St. Joseph County verified address Exact, at the address [1] echo.epa.gov

Overview, regulatory gates and specifications

Aunalytics operates the AUSB commercial colocation data center at 1440 Ignition Drive in the Ignition Park technology campus in South Bend, St. Joseph County, Indiana. [1] Filings on the record specify disclosed capacity of 4 MW (the developer's figure), 1 planned or operational building. [2] Verified facility status from Indiana IDEM permits, IURC dockets, municipal zoning filings, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Indiana Department of Enviro
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [2]
4 MW
the developer's figure

Equivalent to ~3,320 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.2% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [2]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 1440 Ignition Drive, South Bend, IN 46601.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
4 MW developer figure Equivalent to the continuous electricity demand of about 3,320 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.039 percent) of New York City's summer peak demand in 2024.
[2] aunalytics.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[2] aunalytics.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2018 (8 years)
Who leads it
Aunalytics as stated by the source
[2] aunalytics.com
State permit status
Indiana Department of Environmental Management Stationary Emergency Generator and Commercial Facility Record (1440 Ignition Drive, South Bend, IN 46601) the state's permit register, as of November 6, 2026
[1] echo.epa.gov
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Aunalytics South Bend Data Center (AUSB), capacity: 4 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 4 ÷ 10,245 = 0.00039 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Aunalytics
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Aunalytics South Bend Data Center (AUSB).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 4 MW 4 MW the developer's figure [2] aunalytics.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [2] aunalytics.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

December 10, 2025 South Bend, IN St. Joseph County Council New Carlisle Data Center Rezoning Hearing St. Joseph County Council 2 clips

Ahead of the December 10, 2025 St. Joseph County Council rezoning decision near New Carlisle, community and faith groups testified against converting additional prime agricultural land for a third large scale data center campus.

  1. Resident public comment Resident Public Comment transcribed from local broadcast report
    "we've made our fair share commitment to two with two data centers. A pause. We want a vote. No, we want a no vote tonight, which is large enough and bipartisan that they will not probably try to set up in this county. One concern the group has is water usage. They claim the county would set a limit, but they are unsure about that limit. The other concern the group worries about is electricity rates that"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "to their proximity of the project. As he also mentioned, the electric rates will skyrocket. Our rates have already gone up 17 and a.5% over the past 12 months in Indiana and they're going to go up even more. St. Joseph County Commissioner Raphael Morton told WSBT22 that AE has told the county and city officials that residential electric bills and water use will not increase. We've had experts come in to talk about"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Indiana IDEM permits, IURC dockets, municipal zoning filings, or operator campus specifications.

    [1] echo.epa.gov

Nearest data centers in Indiana

Verified data center records in Indiana within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Global Access Point Union Station (South Bend) South Bend, St. Joseph County Less than 1 mi Running Global Access Point 8 MW
Amazon Web Services Project Rainier (New Carlisle) New Carlisle, St. Joseph County 10 mi Being built Amazon Web Services 2.2 GW
Microsoft La Porte Data Center Campus La Porte, LaPorte County 23 mi Being built Microsoft 200 MW
Google Michigan City data center Michigan City, LaPorte County 32 mi Being built Google 200 MW
Amazon Web Services Wheatfield Data Center Campus (Project Rise) Wheatfield, Jasper County 52 mi Proposed Amazon Web Services 500 MW
Amazon Web Services Hobart Data Center Campus Hobart, Lake County 55 mi Proposed Amazon Web Services 300 MW

Blank cell: not disclosed by any source on file.

Common questions about Aunalytics South Bend Data Center (AUSB)

Answered directly from the verified filings and local actions on this page.

Who is building Aunalytics South Bend Data Center (AUSB)?

Aunalytics is the developer, aunalytics.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Aunalytics South Bend Data Center (AUSB) say it needs?

Power: 4 MW (the developer's figure, aunalytics.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Aunalytics South Bend Data Center (AUSB) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. US EPA ECHO and Indiana Department of Environmental Management Stationary Generator & Parcel Record (1440 Ignition Drive, South Bend, IN 46601) (opens in a new tab), U.S. Environmental Protection Agency and Indiana Department of Environmental Management, November 6, 2026
  2. Aunalytics Facility Specifications (1440 Ignition Drive, South Bend, IN 46601) (opens in a new tab), Aunalytics, November 6, 2026

2 sources on file.

Regional grid context

This site is in the RFC West (RFCW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Aunalytics South Bend Data Center (AUSB)", https://datacenterrecord.org/projects/aunalytics-south-bend-datacenter-ausb-in, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Aunalytics South Bend Data Center (AUSB)", https://datacenterrecord.org/projects/aunalytics-south-bend-datacenter-ausb-in. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
41.661423, -86.257342
How the location is known
Location from the site's street address.
Location source
https://aunalytics.com/
Coordinate source
Aunalytics South Bend (AUSB) specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
4 MW, the developer's figure
Published
October 21, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Aunalytics South Bend Data Center (AUSB) · 2 sources, 1 entry · basis and source tier on every row · verified November 6, 2026

Download CSV JSON