Global Access Point Union Station (South Bend)

South Bend, St. Joseph County, INDeveloper: Global Access PointCensus GEOID 18141

Stage
Running
Power
8 MW
the developer's figure
Buildings
2 buildings
operator page, verified October 27, 2026
Undisclosed in public filings
Land, Water

Global Access Point operates a carrier hotel and colocation data center campus at Union Station, 506 West South Street, in South Bend, St. Joseph County, Indiana. It is running; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

1 hearing on the record, 2025

Last verified · 1 source, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Running, ringed
  • data center
  • Smaller pins: 28 other published records in Indiana
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
2 buildings operator page, verified October 27, 2026
[1] globalaccesspoint.com
Power it would draw
8 MW the developer's figure About 0 percent of New York City's summer peak demand in 2024.
[1] globalaccesspoint.com
Who leads it
Global Access Point as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Global Access Point Union Station (South Bend), capacity: 8 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 8 ÷ 10,245 = 0 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 8 MW the developer's figure [1] globalaccesspoint.com (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Global Access Point as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 2 buildings operator page, verified October 27, 2026 [1] globalaccesspoint.com (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of St. Joseph County and South Bend about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
St. Joseph County St. Joseph County Council is discussing developing a ban on data centers coming to the county. wsbt.com (opens in a new tab)
South Bend case by case South Bend's public works director Eric Horvath and city engineer Kara Boyles signed NDAs with Amazon in 2023 lpm.org (opens in a new tab)
South Bend case by case The proposed bill is set for first reading on September 28, 2026 lpm.org (opens in a new tab)
South Bend case by case South Bend Common Council members Oliver Davis Jr. and Sherry Bolden Simpson filed a bill banning NDAs about data centers lpm.org (opens in a new tab)
South Bend case by case South Bend Mayor James Mueller issued an executive order banning city staff from signing non disclosure agreements about data centers on September 16, 2026 lpm.org (opens in a new tab)
St. Joseph County Republican council members proposed a temporary moratorium on new data center projects in St. Joseph County wsbt.com (opens in a new tab)
1 earlier decision on the county's rows
DateWhoDecisionSource
St. Joseph County St. Joseph County leaders debated a two year data center moratorium wvpe.org (opens in a new tab)
December 10, 2025 South Bend, IN St. Joseph County Council New Carlisle Data Center Rezoning Hearing St. Joseph County Council 3clips

Ahead of the December 10, 2025 St. Joseph County Council rezoning decision near New Carlisle, community and faith groups testified against converting additional prime agricultural land for a third large scale data center campus.

  1. Resident public comment Resident Public Comment auto captions, unchecked
    "we've made our fair share commitment to two with two data centers. A pause. We want a vote. No, we want a no vote tonight, which is large enough and bipartisan that they will not probably try to set up in this county. >> One concern the group has is water usage. They claim the county would set a limit, but they are unsure about that limit. The other concern the group worries about is electricity rates that"
  2. Resident public comment Resident Public Comment auto captions, unchecked
    "to their proximity of the project. >> As he also mentioned, the electric rates will skyrocket. Our rates have already gone up 17 and a.5% over the past 12 months in Indiana and they're going to go up even more. >> St. Joseph County Commissioner Raphael Morton told WSBT22 that AE has told the county and city officials that residential electric bills and water use will not increase. >> We've had experts come in to talk about"
  3. St. Joseph County Council Member Elected Official auto captions, unchecked
    "that the water usage will not affect the residents in our county. Thanks for watching. Here's another story you may like and subscribe to the WSBT22 YouTube channel."

What happened

No dated entry is on the record yet.

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Indiana IDEM permits, IURC dockets, municipal zoning filings, or operator campus specifications.

    [1] globalaccesspoint.com

The site

The pin is the site's address.

The site map is at the top of the page.

Where
506 West South Street, South Bend, IN 46601, South Bend, St. Joseph County, Indiana [1] globalaccesspoint.com (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of Global Access Point Union Station (South Bend)
LAT 41.66953 / LON -86.25580 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Global Access Point Union Station (South Bend)?

The record has 2 measures of its size: 8 MW (the developer's figure, globalaccesspoint.com (opens in a new tab)) and 2 buildings (operator page, verified October 27, 2026, globalaccesspoint.com (opens in a new tab)). Its acreage is not disclosed.

Who is building Global Access Point Union Station (South Bend)?

Global Access Point is the developer. No construction contractor is named on the record yet.

How much power and water does Global Access Point Union Station (South Bend) say it needs?

Power: 8 MW (the developer's figure, globalaccesspoint.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Global Access Point Union Station (South Bend) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has South Bend or St. Joseph County decided about it?

St. Joseph County: St. Joseph County Council is discussing developing a ban on data centers coming to the county (reported September 22, 2026, wsbt.com (opens in a new tab)); and South Bend (rated case by case): South Bend's public works director Eric Horvath and city engineer Kara Boyles signed NDAs with Amazon in 2023 (reported September 20, 2026, lpm.org (opens in a new tab)). 7 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Global Access Point Union Station (South Bend) Official Disclosure (opens in a new tab), Global Access Point, query feed

1 source on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Global Access Point Union Station (South Bend)", https://datacenterrecord.org/projects/global-access-point-gap-union-station-south-bend-in, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Global Access Point Union Station (South Bend)", https://datacenterrecord.org/projects/global-access-point-gap-union-station-south-bend-in. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
41.669526, -86.255805
How the location is known
Location from the site's street address.
Location source
https://www.globalaccesspoint.com/
Coordinate source
Global Access Point Union Station specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
8 MW, the developer's figure
Rating of the county's rows
Case by case
Published
October 21, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection

Researcher view · Global Access Point Union Station (South Bend) · 1 source, 1 entry, 7 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON