Closed water loop design uses 87 times less water than original plan
Context & source notes
Provenance: Paraphrased; said in the source itself.
Primary source: Idaho Press (opens in a new tab).
Kuna has 2 data centers on the record: 1 running and 1 proposed. No city rule about data centers is on the record for Kuna yet. Ada County's own decisions are on the Ada County page.
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Meta Kuna Data Center Kuna, Ada County | Running | Meta | Groundbreaking was in 2022 idahopress.com (opens in a new tab) local outlet reported September 19, 2026 | EPA registry | 1 | 2026-11-06 | ||
| Kuna Data Centers (two projects) Kuna, Ada County | Proposed | centroid | 4 | 2026-09-17 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
No facility record and no county act is on the record for Kuna yet. The Idaho state rule applies: open.
KTVB report on Ada County Board of Commissioners and community proceedings in Kuna, ID: First data center in Idaho proposed on public lands. It would be four times larger than Meta's Kuna (September 21, 2026).
"And while the Bureau of Land Management will be evaluating the impacts of this project, some Idahoans worry about the environmental cost in the desert a few miles outside of Boise. Across from a bird reserve sits 3700 acres of open space where a Nevada based company wants to build a massive data center, , the first on public land in , Idaho. We're anticipating somewhere in the realm of a 4 million square foot facility."
"BLM also says Raya Data, a subsidiary of Arabia Power, also plans for a natural gas plant to power the data center. We're thinking that would be about 450 megawatts that that has potential to produce, but that's more as a redundancy or a contingency in during. Peak loading or when they need additional power. , Jared , Blades, a BLM field manager, says through its resource management planning process, the BLM identifies open land for energy and infrastructure,"
"the computing power to be able to do that, Hamilton says. Supporters argue data centers create jobs and support long term technology advancements without having to rely on foreign countries and their infrastructure. We just need to make sure that we go into this with our eyes open. And we make sure that when it's that if it's done, it's done right. The Idaho chapter of the Sierra Club, a national environmental advocacy group, just found out about the project a few days ago. To use"
Using this data in a report? Support the record.
Went liveMeta Kuna Data Center
Meta's Kuna data center formally opened on September 4, 2026
Lisa Grow says the pace and scale of Idaho's growth is unprecedented and Idaho Power must adapt and innovate to keep up with growth statewide and manage resources to keep costs down.
Meta aims to be net water positive by 2030
Scott Stillings, critical operations manager, said the same water used to cool the facility today will be used for the next 10 years
Kuna welcomes Meta to our city and values their commitment to our community. As the first large anchor in the city's East Kuna Industrial area, their infrastructure investment is a catalyst for expanding the city's ability to support well-paying jobs and attract other industrial and manufacturing users the Kuna.
View all 8 Idaho statements on the record →
Closed water loop design uses 87 times less water than original plan
Provenance: Paraphrased; said in the source itself.
Primary source: Idaho Press (opens in a new tab).
Zero operational water use for majority of year with closed loop system
Provenance: Paraphrased; said in the source itself.
Primary source: Idaho Press (opens in a new tab).
Brad Davis, Meta Director of Global Economic Development, said the closed loop cooling system runs without extra cooling water for much of the year and needs refill every 7 to 10 years
Provenance: Paraphrased; said in the source itself.
Primary source: Coeur d'Alene Press (opens in a new tab).
"We are thrilled to be breaking ground on our newest data center in Kuna, Idaho. Thank you to all of our partners who helped us move this project forward. Kuna is a great place to call home and we are committed to investing in the community's long-term vitality. We look forward to having a strong, fruitful partnership for years to come."
Provenance: Quoted; content date; reported from elsewhere.
Setting: Meta press announcement.
Primary source: Data Center Dynamics (opens in a new tab).
Distances run between the centers the Census Bureau gives each place. Every Idaho county.
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 0 | 2 | ||
| Water, stated per day | 0 | 2 | ||
| Water, stated per year | 0 | 2 | ||
| Permanent jobs | 0 | 2 | ||
| Tax each year | 0 | 2 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 2 |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
No source on file states what any of the 2 tracked facilities in Kuna are for.
No source on file states how any of the 2 tracked facilities in Kuna are cooled.
Report a correction · Send a tip about Kuna · The rows here are part of the Idaho export.
Data Center Record, "Data center records in Kuna, Ada County, Idaho", https://datacenterrecord.org/states/id/ada-county/kuna. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.