Raeden Gibraltar Data Center
Raeden's data center development in Gibraltar, Michigan was halted by a municipal moratorium, which the developer claims unlawfully stopped the project and has challenged in court. It is reported, as reported August 20, 2026.
How much power it needs, how much water it would use and who would use it have not been disclosed.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
What is known
Each figure as its source gave it. The number in brackets is its place in the source list.
- Land
- Not disclosed
- Power it would draw
- Not disclosed
- Water
- Not disclosed
- Who leads it
- Raeden
- as stated by the source
- Who would use it
- Not disclosed
- Jobs once it runs
- Not disclosed
- Tax each year
- Not disclosed
Every field, with who said it and when (Researcher view)
Impact figures
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | Not disclosed | |||
| How much water it would use | Not disclosed | |||
| How loud it would be | Not disclosed | |||
| Jobs once it runs | Not disclosed | |||
| Tax it would pay each year | Not disclosed |
The record's fields
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Raeden | as stated by the source | September 17, 2026 | |
| Who is constructing it | Not disclosed | |||
| How much land | Not disclosed | |||
| Where its power comes from | Not disclosed | |||
| Grid connection | Not disclosed | |||
| How it is cooled | Not disclosed |
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
Still not public, and where it would show up
The record adds each the day a source gives it. Why these documents.
- Water useA state water right filing or a water supply agreement.
- Who would use itA lease announcement or a tenant named in a filing.
- Power the campus would drawA utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
- Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.
What was decided
Acts of Wayne County and Gibraltar about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Van Buren Township | Van Buren Township Planning Commission approved preliminary site plan for Project Cannoli Data Center on Wednesday night with conditions | wemu.org |
What happened
-
· Status: rumored (source date; the content gives no date of its own)
Raeden proposed to repurpose McLouth Steel industrial site into 100 megawatt inference data center [4]
The full Raeden Gibraltar Data Center timeline, in order
10 corrections to this record
Every correction, with its reason
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the draft of a status history row
Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.
-
· the draft of a status history row
Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.
-
· the draft of a status history row
Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.
-
· the draft of a status history row
Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.
-
· the draft of a status history row
Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.
Every correction on the record is on the corrections page.
The site
Where in Wayne County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.
Tap a pin for the data center, the parcel for its record
- This record: Proposed, ringed
- data center
- Dashed edge: the exact site is not in the public record
- Smaller pins: 10 other published records in Michigan
Details
- this record's location, ringed
- parcel outline, from the county parcel record
- city limits, U.S. Census Bureau, on a town level record
- county boundary
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
- Where
- Gibraltar, Wayne County, Michigan
- How exactly it is located
- County level, the county seat
- The parcel
- No parcel outline in the public record
- Nearest homes
- Not computed for a record placed at a place center
- Nearest records
- Nearest records are not computed for a record placed at a county seat.
Questions about this project
4 questions answered from the record
Who is building Raeden Gibraltar Data Center?
-
Raeden is the developer. No construction contractor is named on the record yet.
How much power and water does Raeden Gibraltar Data Center say it needs?
-
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
Where does Raeden Gibraltar Data Center stand today?
-
It is reported, as reported August 20, 2026. The newest entry, reported August 20, 2026: Raeden proposed to repurpose McLouth Steel industrial site into 100 megawatt inference data center [4].
What has Gibraltar or Wayne County decided about it?
-
Van Buren Township: Van Buren Township Planning Commission approved preliminary site plan for Project Cannoli Data Center on Wednesday night with conditions (February 11, 2026, source). 1 event is on the county's rows; a rule about the area is not a decision about this record.
Sources
Reporting
- Raeden claims Michigan moratorium unlawfully stopped its Gibraltar data center development - Data Center Dynamics, Data Center Dynamics, August 24, 2026, trade press
- Raeden claims Michigan moratorium unlawfully stopped its Gibraltar data center development - Data Center Dynamics, Data Center Dynamics, August 24, 2026, trade press
- Raeden Gibraltar Data Center: 100 MW data center in Michigan, morethanjustparks.com, July 13, 2026, local outlet
- Developers challenge Gibraltar's data center moratorium in court - Detroit Free Press, Detroit Free Press, August 20, 2026, local outlet
- Data center developer sues Michigan city, challenging one-year pause on projects - MLive.com, MLive.com, August 20, 2026, local outlet
- Data center developer accuses Gibraltar city officials of unlawfully imposing 1 year moratorium - cbsnews.com, cbsnews.com, August 21, 2026, local outlet
6 sources on file.
Cite this record
Data Center Record, "Raeden Gibraltar Data Center", https://datacenterrecord.org/projects/raeden-gibraltar-data-center-mi, last verified September 17, 2026.
Cite this page
Data Center Record, "Raeden Gibraltar Data Center", https://datacenterrecord.org/projects/raeden-gibraltar-data-center-mi. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
For researchers
- Slug
- raeden-gibraltar-data-center-mi
- Status value
- rumored
- Stage
- Proposed
- Tier
- skeleton
- Tags
- skeleton
- Place id
- us/mi/wayne-county/gibraltar
- Coordinates
- 42.33167, -83.0475
- Location precision
- county
- Location source
- County seat (Detroit), Wikidata, placed at county level
- Coordinate source
- wikidata county seat
- Location source number
- Not disclosed
- Location last verified
- September 16, 2026
- EPA registry id
- Not disclosed
- Use type values
- not_disclosed
- Tenancy value
- not_disclosed
- Cooling type value
- not_disclosed
- Capacity basis
- not_disclosed
- Water basis
- not_disclosed, gallons_per_day
- Acreage basis
- Not disclosed
- Interconnection value
- not_disclosed
- Capacity, if disclosed
- Not disclosed
- Rating of the county's rows
- Not disclosed
- Published
- 2026-09-05
- Last verified
- 2026-09-17