Raeden Gibraltar Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

6 events, February 2026 to August 24, 2026. Also on the record, under the month each belongs to: 1 figure from another source and 2 dates when source pages were read and verified. The facts, newest first: the record; the place: Michigan.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. proposed
  2. stalled
  3. proposed

Now: proposed. A stage is the record's status after the entry that set it (the definitions).

2026 6 events

  1. (the month its own sentence names; no day is given; filed under Aug 24, 2026)

    Entry

    Raeden submitted application to Gibraltar in mid February 2026 [1]

  2. (the day its own sentence names; filed under Aug 21, 2026)

    Entry

    Raeden Acquisitions submitted an application to the city on February 17, 2026 for a data center at the former McLouth steel mill site [6]

  3. (the month its own sentence names; no day is given; filed under Aug 21, 2026)

    Entry · Moratorium ended

    The city council issued a letter in July 2026 stating it would not process the February application until the moratorium ended [6]

  4. (content date)

    proposed · Moratorium

    Raeden Acquisitions and CAL Realty filed a lawsuit in U.S. District Court for the Eastern District of Michigan on August 17, challenging the moratorium as unlawful and seeking approval of a plan to transform a former steel mill into a data center. (alleged in the filing, not a finding) [7]

  5. (source date; the content gives no date of its own)

    proposed

    Raeden proposed 100MW data center at 27800 W. Jefferson, former McLouth Steel site [1]

  6. (content date)

    stalled

    Raeden's data center development in Gibraltar, Michigan was halted by a municipal moratorium, which the developer claims unlawfully stopped the project and has challenged in court. [1]

  7. Also in August 2026: 1 figure from another source and 2 dates when source pages were read and verified
    1. (source date; the content gives no date of its own)

      Entry

      Raeden proposed to repurpose McLouth Steel industrial site into 100 megawatt inference data center [4]

    2. (source date; the content gives no date of its own)

      Figure · GovTech

      100 MW: The data center would initially require 100 megawatts of electricity. GovTech (opens in a new tab) national outlet

    3. (source date; the content gives no date of its own)

      Entry

      Raeden planned to install 35 backup diesel generators [1]

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
proposed
Events on the timeline
6
Under the months
3
Stage changes
3
Decisions
0
Statements
0
Figures
1
Entries and decisions under the months
2

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data